HomeMy WebLinkAboutAgenda Report - September 2, 1992 (53)The irregularity is that the second lowest bidder, along with failing to submit additional information, also failed to sign their bid. Thi: City Attorney has stated that unsigned bids are not proper bids and therefore unacceptable. It is our opinion that the omission of the additional information with the bid provided no material advantage to the low bidder and is insignificant in nature. W therefore recommend awarding the contract to SEMCO in the amount of $14,543.65. If the Council disagrees with this recommendation, it is suggested that all bids be rejected and this contract be readvertised for rav bids. APPROVED. l _ - • L ' THOMAS A PETERSON «.: .. CTANK.1/TXTW.02M (CO.COM) August 25, 1992 Ingineer's-:.Estimate,; $159350.00:. �SEMCONbdesto $14,543.65 !Stockton Station;,Equip. Co., Inc. Stockton;. 315,700.00 Service Energy Associates,., Stockton;:: 515;986.46 ,'Falcon NerbstEngineering, Inc: Sacramento ;318;505.00 RHRM Plumbing Co.,,Inc.`n Stockton. $29,281.00' ddiiion' al information submitted. dditional information"submitted and did not sign bid. IN6: °�Origi.naily :Budgeted: 1989/90 CTANK.i/TXTW.02M (CO.COM) August 25, 1992 RESOLUTION NO. 92-153 ssaasssssssassssssasamsss A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT FOR ABOVEGROUND VAULTED FUEL STORAGE TANK, 125 NORTH STOCKTON STREET ssssssassasssssssssssssssssssssssssssassssassssassssasssssasassssssssss WHEREAS, in answer to notice duly published in accordance with. law. and the order of thiS City Council, sealed bids were received and publicly.opened on August 19, 1992 at 11:00 A.M. for the contract for aboveground :'vaulted -fuel storage tank, 125 North Stockton Street.' described in the specifications therefor approved by the City Council on August 5,;1992; and WHEREAS, said bids have been compared, checked, and tabulated and a,report thereoffiled with the City Manager as follows: Bidder Lgcat.i.on SEitCO Modesto $14,543.65 **Stockton Service Station i 'Equip.-Co'.,.,Inc. Stockton $15,700.00 Falcon snem Associates Stockton $15,986.46 Herbst Engineering, Inc. Sacramento $18,505.00 HRK Plumbing Co., Inc. Stockton $29,281.00 i * No additional information submitted. **No 'additional information submitted and did not sign bid. z WHEREAS, the City Manager recraimends that award of the contract for aboveground vaulted fuel storage tank be made to the low bidder, SEMCO; NON, THEREFORE, BE IT RESOLVED that the Lodi City Council hereby waives the low bidder's informality, who along with two other bidders, failed to provide additional information, which provided no material advantage to the low bidder, is insignificant in nature and was later provided to the City by the low bidder; and BE IT FURTHER RESOLVED, that award of contract for aboveground vaulted fuel storage tank, 125 North Stockton Street be and the same is hereby awarded to SENCO, the low bidder, in the amount of $14,543.65. Dated: September 2, 1992 ssaassasmsamsaaasmsssssssasssa:asmacs:ssssaasssassssssssasasssasasasaaaa I hereby certify that Resolution No. 92-153 was passed and adopted by the City Council of the City of Lodi in a regular meeting held September 2, 1992 by the following vote: Ayes: Council Members - Hinchman, Pennino, Sieglock, Snider and Pinkerton (Mayor) Noes: Council Members - None Absent: Council Members - None Alice M. Reimche City Clerk ��'-d tt RES92153/TXTA.02J