HomeMy WebLinkAboutAgenda Report - August 21, 1991 (73)CITY OF LO D I COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Hrn Lane Improvements, Kettleman
Lane to Vine Street Contract
MEETING DATE: August 21, 1991
'REPARED BY: Public Works Director
2ECOMMENDED ACIION That the City Council accept the improvements under the 'Um
Lane Improvements, Kettleman Lane to Vine Street" contract, and
direct the Public Works Director to file a Notice of Completion
with the County Recorder's office.
BACKGROUND t4CFAIXTUN The contract was awarded to Ragsdale & Son, Inc., of
Waterford, on April 3, 1991, in the amount of $138,137.00.
The contract has been completed in substantial conformance
with the plans and specifications approved by the City
Counci 1.
The contract completion date was July 8, 1991, and the actual completion date was
July 26, 1991. The final contract price was $140,218.00. The difference between
the contract amount and the final contract price is mainly due to the additional
cost to have the contractor pour the tennis court parking lot in two sections.
Splitting the pour permitted continuous access to the parking lot.
A Change order
was also issued to have the contractor modify the installation of the traffic signal
detector loops.
FLMIN x Originally Budgeted: 1987
Budgeted Fund: Federal Aid Urba
Current Appropriation: $180,000
Total Project EstijAwtea. $1684M
.QL-ja �1
q, Jack L. Ronsko U
Public Works Director
Prepared by Wesley F u j i t a n i, Senior Civil Engineer
JLR/WF/in
cc: Purchasing Officer
APPROVED: /-�
THOMAS A. PETERSON
6 i A4nAnaa�
CC -1
'NAMLAN)
Cc MW.01L (CC .COM) August 13, 1991