AGENDA TITLE: Acceptance of Improvements Under Demolition of Elevated Water Storage
Tank, 114 North Main Street, Contract
MEETING DATE: July 1, 1992
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Demolition of Elevated Water Storage Tank, 114 North Main
Street" contract, and direct the Public Works Director to file
a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Ruff Stuff of Stockton on
April 15, 1992 in the amount of $28,000. The contract has
been completed in substantial conformance with the plans
and specifications approved by the City Council.
The contract completion date was July 6, 1992, and the actual completion date was
June 5, 1992. The final contract price was $29,700. The difference between the
contract amount and the final contract price is mainly due to a change order for
extra work of demolition not originally in the scope of work.
FUNDING: Originally Budgeted: 1990/1991
Budgeted Fund: Water Capita; Outlay
Total Project Estimate: $55,000
Bid Opening Date: April 8, 1992
Jack L. Ronsko
Public Works Director
Prepared by Mark Lindseth, Associate Civil Engineer
JLR/MC/1m
cc: Purchasing Officer
APPROVED:
THOMAS A. PETERSON �ZC1Z
City Manager
cc -1
CDEMOTN2/TXTW.02M (CO -CCM)
June 17, 1992