HomeMy WebLinkAboutAgenda Report - June 15, 2011 C-09AGENDA ITEM W9
CITY OF LODI
,. COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Authorizing City Managerto Execute Contract Change Orderwith
Knife River Construction, Inc., of Stockton, for Additional Work Related to the Water
Meter Program Phase 1 Project ($226,885) and Appropriating Funds ($230,000)
MEETING DATE: June 15,2011
PREPARED BY: PublicWorks Director
RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute contract
change order with Knife River Construction, Inc., of Stockton, for
Additional Work Related to the Water Meter Program Phase 1
Project in the amount of $226,885 and appropriating funds in the
amount of $230,000.
BACKGROUND INFORMATION: The contract with Knife River Construction was approved by Council
on March 16, 2011. The project is Phase 1 of the Water Meter
Installation Program.
At the May 18, 2011 City Council meeting, Council authorized advertising for bids for the 2011 Alley
Reconstruction Project. The City has discovered that the existing water lines in the alleys included in the
2011 Alley Project are too shallow to permit the alley improvementwork to be performed. The area was
originallyto be included in the Water Meter Program Phase 7 work. This change order will expedite the
water line work in these alleys to be completed prior to the Alley Reconstruction Project.
Knife River Construction was the low bidder of eleven (11) bids received for the Water Meter Program
Phase 1 Project. The contract amount awarded was $1,872,285.00. Knife River has crews available to
perform the alley waterline work without impacting the base Phase 1 contract work or schedule. The
work will be performed under the current Water Meter Program Phase 1 contract requirements.
FISCAL IMPACT: The work will expedite the Water Meter Program and Alley Reconstruction
work in this area.
FUNDING AVAILABLE: Requested Appropriation:
Water Fund (181464) $230,000
Q-A" A --U A
Jordan Ayers
Deputy City Manager/internal Services Director
JIA /12 IL. A2 .,rV, L
F. ally S dehn
Public Works Director
Prepared by Gary Wiman, Construction Project Manager
FWS/GW/pmf
APPROVED: r
Konradt Bartlam,, City Manager
K:\WP\PROJECTS\WATER\Water Meter Program Phase 1\CC WMPP1 Alley CO,doc
6/2/2011
I
SEE SHEET Cl
IIWASHINGTON ST.
PROJECT LIMIT
W Vfll�NIAIN INSTALLATION
40
S
ALLEYNORTI] OFTOK 0
250'E/ STOCKTON ST -
NV
ASHINGTON ST
EXHIBIT A
FT -
NU4
SHEET C2
SEE SHEET C4
EXHIBIT A
LC
\T -,R jlIAlN lNSTALLATION Cln- OFLODI
O. ALLEY NORTH OI' EDEN ST
1.1-KNIA -1;N-1
PHONE'l- )I"--
Cl.-.'NTRAI.,kVE FAN
250'1-'./ CU-NTRALAVE
-B NOINDOIS
JS NOINDOIS
V c
ISAV-NOIAO Rl,�IONA'Tl A
NOLIXTIVI�Nl
ICTO'lJO,UID
vR
\} }. }\ \\}\ }\ \} }j } � ( ( : } � �� � \ (
M Z
1, o, I
U
H 0
<
iI9IHX3
ZO IDDHS aS
Is NOi>J:Do +i
------------��������� 6a'///�\d/\
WATER MAIN INSTALLATION
ALLE'YNORTI-1 0F FDI",N ST
25WE/ ST
CITYOF LODI
EXHIBIT A
KNIFE RIVER
CONSTRUCTIONI
AN MDURESOURCES COMPANY
EXHIBIT B
Water Meter Program - Phase 1
CO Request#1
Alley Improvements
# Description QTY UM Unit Cost Total
CO Request#1
1
Traffic Control
1
LS
$6,000.00
2
Shoring/Trench Plates
1
LS
$1,500.00
3
Pothole Existing Utilities
1
LS
$12,000.00
4
6 Water Main
1,295
LF
$53.00
5
6" Gate Valves
4
EA
$1,450.00
6
1"Service w/ Meter Assembly
42
EA
$1,900.00
7
Install Service from Box to Hose Bibb on Tokay Street
13
EA
$1,600.00
8
Tie -In to Existing Main
4
EA
$3,500.00
g
Abandon Existing Main
4
EA
$900.00
10
Abandon Existing Service
g
EA
$750.00
11
Mobilization
1
LS
$8,000.00
TOTAL
1 2 days of potholing per alley figured (4 TOTAL). Any additional potholing required will be on T&M
2 Connection to existing service will be withing 5' of new meter box, trenching around houses is not figured.
3 .
4
5 No removal or handling of AC (transite) pipe is included.
6 Due to PVC volatility, pipe will need to be ordered within 5 days to maintain pricing.
7 Knife River will need approximately 30 Working days to complete this work.
Page 1 of 1
$6,000.00
$1,500.00
$12,000.00
$68,635.00
$5,800.00
$79,800.00
$20,800.00
$14,000.00
$3,600.00
$6,750.00
$8,000.00
$226,885.00
1. AA#
2. JV#
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Change order to contract with Knife River Construction for additional work related to the water meter program phase 1 project.
If Council has authorized the appropriation adjustment, complete the following:
Date: Res No: Attach copy of resolution to this form.
ent Head Signature:
Deputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Division with any required documentation.
Final approvalwill be provided in electronic copy format.
CITY OF LODI
AP PROPRIATION,ADJUSTMENTREQUEST
TO:
linternai Services Dept. - Budget Division
3. FROM:
Rebecca Areida-Yadav 5. DATE:
06/06/2011
4. DEPARTMENT/DIVISION: Public Works
6. REQUEST ADJUSTMENT
OF:APPROPRIATION ASLISTED, BELOW
FUND# BUS. UNIT# ACCOUNT# ACCOUNT TITLE
AMOUNT
A.
181 3205 Fund Balance
$ 230 000.00
SOURCE OF
FINANCING
B.
181 181464 1825.2200 Water Meter Program Phase 1
230 000.00
USE OF
FINANCING
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Change order to contract with Knife River Construction for additional work related to the water meter program phase 1 project.
If Council has authorized the appropriation adjustment, complete the following:
Date: Res No: Attach copy of resolution to this form.
ent Head Signature:
Deputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Division with any required documentation.
Final approvalwill be provided in electronic copy format.
RESOLUTION NO. 2011-92
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
THE CITY MANAGER TO EXECUTE CONTRACT CHANGE
ORDER WITH KNIFE RIVER CONSTRUCTION, INC., OF
STOCKTON, FOR ADDITIONAL WORK RELATED TO THE
WATER METER PROGRAM PHASE 1 PROJECT AND
FURTHER APPROPRIATING FUNDS
WHEREAS, the contract with Knife River Construction, Inc., of Stockton, for the Water
Meter Program Phase 1 Project was approved by Council on March 16,2011; and
WHEREAS, at the May 18, 2011, City Council meeting, Council authorized advertising
for bids for the 2011 Alley Reconstruction Project; and
WHEREAS, the City has discovered the existing water lines in the alleys included in the
2011 Alley Reconstruction Project are too shallow to permit the alley improvement work to be
performed; and
WHEREAS, Knife River Construction was the low bidder of 11 bids received for the
Water Meter Program Phase 1 Project. The contract amount awarded was $1,872,285.00; and
WHEREAS, Knife River has crews available to perform the alley water line work without
impacting the base Phase 1 contract work schedule.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute a contract change order in the amount of $226,885 with
Knife River Construction, Inc., of Stockton, California, for additional work related to the Water
Meter Program Phase 1 Project; and
BE IT FURTHER RESOLVED that funds in the amount of $230,000 be appropriated
from the Water Fund.
Dated: June 15,2011
hereby certify that Resolution No. 2011-92 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 15, 2011, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Katzakian, Mounce, Nakanishi, and
Mayor Johnson
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS— None
DI �JOHL
City Clerk
2011-92