HomeMy WebLinkAboutAgenda Report - May 5, 2010 D-08AGENDA ITEM D A
&% CITY OF LODI
COUNCIL COMMUNICATION
Im
AGENDA TITLE: Adopt Resolution Establishing a Standardized Question nairefor Bidder
Qualification as Provided by Public Contracts Code Section 20101
MEETING DATE: May 5,2010
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt a resolution establishing a standardized questionnaire for bidder
qualification as provided by Public Contracts Code Section 20101.
BACKGROUND INFORMATION: Public Contracts Code Section 20101 gives public entities the right to
use a Bidder Qualification Questionnaire in order to ensure that
prospective bidders have the appropriate experience, qualifications
and financial stability to perform the work for a specific project. The
Code requires "the PublicAgency to adopt and apply a uniform system of rating bidders on the basis of the
completed questionnaire and financial statements, in order to determine both the minimum requirements
permitted for qualification to bid, and the type and size of the contracts upon which each bidder shall be
deemed qualified to bid." The uniform system of rating prospective bidders shall be based on objective
criteria. An appeals process is also required to permit bidders to appeal the rating.
The proposed City of Lodi questionnaire (attached) is compiled from and modeled after an example
questionnaire created by the State of California Department of Industrial Relations. The qualification
questionnaire is an information and scoring utility that provides the City with contractor information
regarding 1) history of the business and organizational performance, 2) compliance with occupational
safety and health laws and workers' compensation and other labor legislation, 3) completion of recent
projects and quality of performance, and 4) experience and resumes of project personnel. It is intended
that project specific information will be added on a project -by -project basis. The qualification process will
typically be used on very large projects or projects where specialty expertise and experience is required.
Some projects will require the prime contractor, as well as major subcontractors, to be qualified.
The qualification process has been used with great success on previous City projects, such as
Hutchins Street Square, White Sough Water Pollution Control Facility, Lodi Station Parking Structure,
Police Facility and Central Plume PCE/TCE Interim Improvements Measures. Establishing a Standardized
Questionnaire will eliminate the need for City Council to approve the pre -qualification questionnaire on a
project -by -project basis. The Surface Water Treatment Plant construction project will be the next project
the questionnaire is used for.
FISCAL IMPACT: Qualification of bidders for specific projects will help ensure the citizens of Lodi
are receiving only experienced and qualified contractors to perform work.
FUNDING AVAILABLE: Not required.
'A I /? / 1. -, J/_) A 1-d. AF I
F. Wally S delin
Public Works Director
Prepared by Gary Wiman, Construction Project Manager
FWS/GW/pmf
Attachment
cc: City Attorney
APPROVED:
Bluer King, C' Manager
KAWP\PROJECTS\Project Boiler Plate Specifcations\CAdopt Bidder QuaTiflegionues ionnaire.doc 4/23/2010
City WLodl
PROJECT
Prime Contractor Prequalification Date
DATF
The City of Lodi is seeking Qualification of Bidders for the Construction of the PROJECT. This Qualification is
for Candidates seeking qualification as Prime contractor.
Qualification Packets can be requested by emailing to cwiman0lodi.gov or by faxing the Public
Works Department at (209) 333-6710. A return email address must be included to receive the
documents.
All pertinent information is enclosed in the Qualification Packet and this Request.
The City of Lodi is issuing this Requestfor Qualifications ("RFQ) in search of Prime Contractors ("Candidates")
who have the necessary qualifications as set forth in this RFQ to be pre-qualifiedto bid. Whether a Candidate
has such qualifications will be determined through the evaluation process described in this RFQ. Candidates
chose through this process ("Qualified Candidates") will be notified of their eligibilityto bid on the PROJECT.
Candidates responding to this RFQ do so with the understanding that they are not guaranteed the awarding of
contracts and work.
Each Questionnaire must be signed under penalty of perjury by an individualwho has the legal authority to bind
the Contractor on whose behalf that person is signing. If any information provided by the Contractor becomes
inaccurate, the Contractor must immediately notify the City of Lodi and provide updated accurate information in
writing, under penalty of perjury.
The City of Lodi reserves the right to limit, suspend or rescind the pre -qualification status based on subsequently
learning information and after giving notice of the proposed action to the Contractorand an opportunity for a
hearing consistentwith the hearing proceduresdescribed for appealing a pre-qualificationdetermination.
Each Candidate shall complete and submit one (1) copy of Parts I, 11, 111 and IV; and all other information as
requested in the RFQ. Completed questionnaires may be delivered in person or via courier or U.S. mail
(other means of transmission, including facsimile, will not be accepted). Submittals must be signed and
dated. No telephone or telegraphic submittals will be accepted. Any submittal received after the deadline
will not be considered regardless of postmark or reason for late delivery.
INFORMATION MUST BE INA SEALED PACKAGEAND CLEARLY MARKEDAS FOLLOWS:
"Qualification of Bidders for the Construction of the PROJECT.
Hand Delivery or Courier:
City of Lodi
Public Works Department
Attn: GaryWiman
221 West Pine Street
Lodi, CA 95240
U.S. Mail:
City of Lodi
PublicWorks Department
Attn: GaryWiman
P.O. Box 3006
Lodi, CA 95241-1910
The City of Lodi may refuse to grant pre -qualification status where the requested information and materials are
not provided. There is no appeal from a denial due to an incomplete application; however, the Candidate will be
informedwhich documents or information are required to complete the application and shall be permitted two (2)
working days to submit a complete application.
All information must be received no later than 5:00 p.m. on DATE.
Firms submitting the required information by the due date and meeting the minimum scoring
requirements will be invited to bid on the project. The city of Lodi will evaluate the submittals and strive to
make determinations in a timely manner.
Sincerely,
Gary R. Wiman
Construction Project Manager
BP Contractor Qualification Questionaire.doc 1 of30 4/14/2010
City of Lodi
PROJECT
Prime Contractor
GENERAL INFORMATION
Date
Failureto complete the following requirements may result in the City of Lodi refusing to list the
Contractoras an approved bidder. Failure to completely address the required criteria may result in
disqualification.
Firms submitting a proposal shall designate a person responsiblefor questions and clarifications for
the Prequalification Statement. Submission of an RFQ constitutes Bidder's consent for the City to
conduct reasonable investigations and reference checks of the Bidder, proposed subcontractors,
suppliers and other persons and organizations.
Any questions regarding pre-qualificationsshall be directed to Gary Wiman at (209) 333-6800
ext 2054, Fax (209) 333-6710 or email at gwimang-Nodi.gov.
A) Project Description:
1) The City of Lodi PROJECT consists of:
a) .
b)
C)
B) Schedule:
1) Illustrate that the company has sufficient resources available to meet the Project Schedule.
Provide a bar chart showing all ongoing work, and planned work that is to be undertaken
between DATE.
2) The project is anticipated to bid in DATE with a construction schedule of months.
C) Project Construction Estimate:
1) The current project construction cost estimate is $000
D) Contractor Qualification Questionnaire and Instructions
1) Complete the following Sections
BP Contractor Qualification Questionaire.doc 2 of 30 4/14/2010
City of Lodi
PROJECT
T
Prime Contractor Prequalification
Draft Site Plan
RM
BP Contractor Qualification Questionaire.doc 3 of 30 4/14/201.0
City of Lodi
PROJECT
Prime Contractor Prequalification
CONTRACTOR
QUALIFICATION
QUESTIONNAIRE
Date
These forms are intended for City of Lodi use only. The City wiii attempt to maintain
confidentiality subject to the requirements of the California Public Records Act.
BP Contractor Qualification Questionaire.doc 4 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
CONTACT INFORMATION
Firm Name: Check One:
❑ Corporation
(as it appears on license)
❑ Partnership
❑ Sole Prop.
Contact Person:
Address:
Phone: Fax: Email:
If firm is a sole proprietor or partnership:
Owner(s) of Company
Contractor's License Number(s) and expiration dates (list all licenses held):
Tax ID Number:
General Tax Exemption Number:
Dunn and Bradstreet Number (if applicable):
Each prospective contractor must have a CLASS California Contractor's license which is current,
active and in good standing with the California Contractors State License Board (CSLB), on the date
and time the request for qualifications submittal is due and must submit this request for qualification
with all portions completed, including required attachments. Each prospective Contractor must answer
all of the following questions and provide all requested information, where applicable. Any
prospective Contractor failing to do so may be deemed unqualified to bid. It is critical that prospective
Contractors fill out all information required accurately, completely, truthfully and to the best of their
knowledge. Ambiguous or incomplete information may lead to an unfavorable evaluation resulting in
a determination of non -qualification.
I, the undersigned, certify and declare that I have read all the answers to this prequalification
questionnaire and know their contents. The Matters stated in the questionnaire answers are true of my
own knowledge and belief, except as to those matters stated on information and belief, and as to those
matters stated on information and belief, and as to those matters I believe them to be true. I declare
under penalty of penury under the laws of the State of California, that the foregoing is correct.
Signature
Print Name
Date
BP Contractor Qualification Questionaire.doc 5 of30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Pre4ualification Date
QUESTIONS
AND SCORING INSTRUCTIONS
Contractor must complete all answers
OUESTIONS AND THE SCORING INSTRUCTIONS
The questions arise in four different areas:
(I) History of the business and organizational performance;
(11) Compliance with occupational safety and health laws, workers' compensation and
other labor legislation;
(111) Completion of recent projects and quality of performance;
(IV) Experience and Resumes.
Note: Not all questions in the questionnaire are scorable; some questions simply ask for
information about the contractor firm's structure, officers and history.
Scores Needed for Qualification
To qualify, a contractor would be required to have a passing grade within Sections I, II
and III referred to below.
Section I, History of the business and organizational performance, a passing score of 65 on
this portion of the questionnaire (of a maximum score of 76 on this portion of the
questionnaire). Total of 16 questions.
Section 11, Compliance with occupational safety and health laws, workers' compensation
and other labor le isg lation a passing score of 45 on this portion of the questionnaire (of a
maximum score of 55 points on this portion of the questionnaire). Total of 11 questions.
Section III, Completion of recent projects, a passing score of 70 on this portion of the
questionnaire (of a maximum score of 90 points on this portion of the questionnaire). Total of 3
projects. Scores are based off information provided from the 3 references for the 3 reference
projects. A score of 17 or lower on any one reference will disqualify the candidate.
Section IV, Experience and Resumes, respond to the questions and provide the information
requested. Section IV is not scored. Information provided in Section IV will assist the City of
Lodi in evaluating the candidates experience related specifically to Water Treatment Plant
construction.
The City of Lodi will compile the scores based on the contractor's responses and the returned
reference questionnaires. The City of Lodi will also consider the thoroughness of the submitted
RFQ documents, attention to instruction and completeness of package. Candidates may be found
not qualified if the RFQ submission package does not include all required items.
BP Contractor Qualification Questionaire.doc 6 of30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
PART L ESSENTIAL REQUIREMENTS FOR QUALIFICATION
Contractor will be immediately disqualified if the answer to any of questions 1 through 5
is "no."
Contractor MAY be disqualified if the answer to any of questions 6, 7, 8 or 9 is "yes." If
the answer to question 8 is "yes," and if debarment would be the sole reason for denial of
pre -qualification, any pre -qualification issued will exclude the debarment period.
If a Joint Venture, each contractor must answer the Part 1 and Part 2 Questions.
Contractor possesses a valid and current California Contractor's license for the project or
projects for which it intends to submit a bid.
❑ Yes ❑ No
2. Contractor has a liability insurance policy issued by a Company licensed to do business in the
state of California with a policy limit of at least $000 per occurrence and $000 aggregate.
❑ Yes ❑ No
3. Contractor has current workers' compensation insurance policy as required by the Labor Code
or is legally self-insured ursuant to Labor Code section 3700 et. seq.
ElYes ElNo Contractor is exempt from this requirement, because it has no employees
4. Have you attached your latest copy of a reviewed or audited financial statement with
accompanying notes and supplemental information?
❑ Yes ❑ No
NOTE: A financial statement that is not either reviewed or audited is not acceptable. A
letter verifying availability of a line of credit may also be attached; however, it will be
considered as supplemental information only, and is not a substitute for the required
financial statement.
S. Have you attached a notarized statement from an admitted surety insurer (approved by the
California Department of Insurance) and authorized to issue bonds in the State of California,
which states: (a) that your current bonding capacity is sufficient for the project for which you
seek pre -qualification if you are seeking pre -qualification for a single project; or (if you are
seeking pre -qualification valid for a year) (b) your current available bonding capacity?
❑ Yes ❑ No
NOTE: Notarized statement must be from the surety company, not an agent or broker.
A sample letter is attached as exhibit "A".
6. Has your contractor's license been revoked at any time in the last ten years?
❑ Yes ❑ No
7. Has a surety firm completed a contract on your behalf, or paid for completion because your
firm was default terminated by the project owner within the last Ten (10) years?
❑ Yes ❑ No
BP Contractor Qualification Questionaire.doc 7of30 4/14/2010
City of Lodi
PROJECT
Prime Contractor
Date
8. At the time of submitting this pre -qualification form, is your firm ineligible to bid on or be
awarded a public works contract, or perform as a subcontractor on a public works contract,
pursuant to either Labor Code section 1777.1 or Labor Code section 1777.7?
❑ Yes ❑ No
If the answer is "Yes," state the beginning and ending dates of the period of debarment:
9. At any time during the last ten years, has your firm or any of its owners or officers been
convicted of a crime involving the awarding of a contract of a government constructionproject,
or the bidding or performance of a government contract?
❑ Yes ❑ No
PART II. ORGANIZATION, HISTORY, ORGANIZATIONAL PERFORMANCE,
COMPLIANCE WITH CIVIL AND CRIMINAL LAWS
Current Organization and Structure of the Business
For Firms That Are Corporations:
Ia. Date incorporated:
lb. Under the laws of what state:
lc. Provide all the following information for each person who is either (a) an officer of the
corporation (president, vice president, secretary, treasurer), or (b) the owner of at least ten per
cent of the comoration's stock.
Name Position Years with Co. % Ownership Social Security #
Dates of Person's Participation
Person's Name Construction Firm with Firm
BP Contractor Qualification Questionaire.doc 8 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
For Fi I Arc Partnerships:
Date;
Ia. Date of formation:
lb. Under the laws of what state:
lc. Provide all the following information for each partner who owns 10 per cent or more of the
firm.
Name I Position I Years with Co. I % Ownership I Social Security#
Dates of Person's Participation
Person's Name Construction Company with Company
For Firms That Are Sole Proprietorships:
Ia. Date of commencement of business.
lb. Social security number of company owner.
lc. Identify every construction firm that the business owner has been associated with (as owner,
general partner, limited partner or officer) at any time during the last five years.
NOTE: For this question, "owner" and "partner" refer to ownership of ten per cent or
more of the business. or ten Der cent or more of its stock, it the business is a corporation.
Dates of Person's Participation
Person's Name Construction Company with Company
BP Contractor Qualification Questionaire.doc 9 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
For Firms That Intend to Make a Bid as Part of a Joint Venture:
Date
Ia. Date of commencement of j oint venture.
lb. Provide all of the following information for each firm that is a member of the joint venture that
Name of firm % Ownership of Joint Venture
History of the Business and Organizational Performance
2. Has there been any change in ownership of the firm at any time during the last three years?
NOTE: A corporation whose shares are publicly traded is not required to answer this
uestion.
Yes ❑ No
If "yes," explain on a separate signed page.
3. Is the firm a subsidiary, parent, holding company or affiliate of another construction firm?
NOTE: Include information about other firms if one firm owns 50 per cent or more of
another, or if an owner, partner, or officer of your firm holds a similar position in
another firm.
❑ Yes ❑ No
If "yes," explain on a separate signed page.
4. Are any corporate officers, partners or owners connected to any other construction firms?
NOTE: Include information about other firms if an owner, partner, or officer of your
firm holds a similar position in another firm.
❑ Yes ❑ No
If "yes," explain on a separate signed page.
S. State your firm's gross revenues for each of the last three years:
7. If any of your firm's license(s) are held in the name of a corporation or partnership, list below
the names of the qualifying individual(s) listed on the CSLB records who meet(s) the
experience and examination requirements for each license.
8. Has your firm changed names or license number in the past five years?
❑ Yes ❑ No
If "yes," explain on a separate signed page, including the reason for the change.
9. Has any owner, partner or (for corporations): officer of your firm operated a construction
firm under any other name in the last five years?
❑ Yes ❑ No
If "yes," explain on a separate signed page, including the reason for the change.
BP Contractor Qualification Questionaire.doc 10 of 30 4/14/2010
City of Lodi
PROJECT
Prime ContractorPrequalification
Oats;
10. Bonding capacity: Provide documentation from your surety identifying the following:
Name of bonding company/surety:
Name of surety agent, address and telephone number:
11. List all other sureties (name and full address) that have written bonds for your firm during the
last five years, including the dates during which each wrote the bonds:
End of Section
BP Contractor Qualification Questionaire.doc 11 of30 4/14/2010
City of Lodi
PROJECT
Prime ContractorPrequalification Date
Example: CERTIFICATION of SURVEY
(To be submitted on agency letterhead)
Date:
To: City of Lodi
Public Works Department
Attn: GaryWiman
P.O. Box 3006
Lodi, CA 95241-1910
Name of Contractor:
City/State:
is authorized to execute bid, performance,
(Name of Bonding Agency)
and payment bonds for the above-named contractor subject to the following conditions:
ExhibitA
1. Contract price of any one contract does not exceed $_.
2. Total amount of uncompleted work on hand, both bonded and unbonded, does not exceed
3. This work authority expires unless previously rescinded in writing. Written
notice of rescission will be provided to the above addressee within seven days of such
rescission.
Signed by:
(Authorized BondingAgency Representative)
BP Contractor Qualification Questionaire.doc 12 of 30 4/14/2010
City of Lodi
PROJECT
Prime ContractorPrequalification
Section I
Ouestions about History of the Business and Organizational Performance
(16 Questions)
Date
1. How many years has your organization been in business in California as a contractor under your present
license number? Years.
Less then 3 years = 0 points
3 years to 5 years = 3 points
5 years to 10 years = 4 points.
10 years or more = 5 points
2. Is our firm currently the debtor in a bankruptcy case?
ff Yes ❑ No
"No" = 3 points" "Yes" = 0 points
3. Was your firm in bankruptcy any time during the last ten years? (This question refers only to a
bankruptcy action that was not described in answer to question 7, above).
❑ Yes ❑ No
"No" = 3 points" "Yes" = 0 points
If "yes," please attach a copy of the bankruptcy petition, showing the case number and the date on
which the petition was filed, and a copy of the Bankruptcy Court's discharge order, or of any other
document that ended the case, if no discharge order was issued.
4. Has any CSLB license held by your firm or its Responsible Managing Employee (RME) or
Responsible Managing Officer (RMO) been suspended within the last ten years?
❑ Yes ❑ No
No = 5 points Yes = 0 points
If "yes," please explain on a separate signed sheet.
5. At any time in the last ten years, has your firm been assessed and paid liquidated damages after
completion of a project, under a construction contract with either a public or private owner?
❑ Yes ❑ No
No projects with liquidated damages = 5 points.
Yes answer = 0 points
If yes, explain on a separate signed page, identifying all such projects by owner, owner's address, the
date of completion of the project, amount of liquidated damages assessed and all other information
necessary to fully explain the assessment of liquidated damages.
6. In the last ten years has your firm, or any firm with which any of your company's owners, officers or
partners was associated, been debarred, disqualified, removed or otherwise prevented from bidding on,
or completing, any government agency or public works project for any reason?
NOTE: "Associated with" refers to another construction firm in which an owner, partner or
officer of your firm held a similar position, and which is listed in response to question 1 c or 1d on
this form.
❑ Yes ❑ No
No = 5 points Yes = 0 points
If "yes," explain on a separate signed page. State whether the firm involved was the firm applying for
pre -qualification here or another firm. Identify by name of the company, the name of the person within
your firm who was associated with that company, the year of the event, the owner of the project, the
project and the basis for the action.
BP Contractor Qualification Questionaire.doc 13 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
7. In the last ten years, has your firm been denied an award of a public works contract based on a finding
b a public agency that your company was not a responsible bidder?
Yes ❑ No
No = 5 points Yes = 0 points
If "yes," explain on a separate signed page. Identify the year of the event, the owner, the project and the
basis for the finding by the public agency.
NOTE: The following two questions refer only to disputes between your firm and the owner of a project.
You need not include information about disputes between your firm and a supplier, another contractor,
or subcontractor. You need not include information about "pass-through" disputes in which the actual
dispute is between a sub -contractor and a project owner. Also, you may omit reference to all disputes
about amounts of less than $25,000.
8. In the past ten years, has any claim against your firm concerning your firm's work on a construction
project, been filed in court or arbitration?
❑ Yes ❑ No If "yes" How Many?
5 points for "No".
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if 2 or more instances.
If "yes," on separate signed sheets of paper identify the claim(s) by providing the project name, date
of the claim, name of the claimant, a brief description of the nature of the claim, the court in which
the case was filed and a brief description of the status of the claim (pending or, if resolved, a brief
description of the resolution).
9. In the past ten years, has your firm made any claim against a project owner concerning work on a
�ro.ect or payment for a contract, and filed that claim in court or arbitration?
] Yes ❑ No If "yes" How Many?
5 points for "No".
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if 2 or more instances
If "yes," on separate signed sheets of paper identify the claim by providing the project name, date of
the claim, name of the entity (or entities) against whom the claim was filed, a brief description of the
nature of the claim, the court in which the case was filed and a brief description of the status of the
claim (pending, or if resolved, a brief description of the resolution).
10. At any time during the past ten years, has any surety company made any payments on your firm's
behalf as a result of a default, to satisfy any claims made against a performance or payment bond
issued on your firm's behalf in connection with a construction project, either public or private?
❑ Yes ❑ No If "yes" How Many?
5 points for "No".
3 points for "Yes" indicating no more than 1 such claim
0 points for "Yes" if 2 more instances
Subtract five points for "Yes" if more than 2 such claims
If "yes," explain on a separate signed page the amount of each such claim, the name and telephone
number of the claimant, the date of the claim, the grounds for the claim, the present status of the
claim, the date of resolution of such claim if resolved, the method by which such was resolved if
resolved, the nature of the resolution and the amount, if any, at which the claim was resolved.
BP Contractor Qualification Questionaire.doc 14 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
11. In the last ten years, has any insurance carrier, for any form of insurance, refused to renew the
insurance policy for your firm?
❑ Yes ❑ No If "yes" How Many?
5 points for "No".
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if more than 1 such instances.
If "yes," explain on a separate signed page. Name the insurance carrier, the form of insurance and the
year of the refusal.
12. Has your firm or any of its owners, officers, or partners ever been found liable in a civil suit, or
found guilty in a criminal action, for making any false claim or material misrepresentation to any
6blic agency or entity?
Yes❑ No
No = 5 points Yes = subtract 5 points
If "yes," explain on a separate signed page, including identifying who was involved, the name of the
public agency, the date of the investigation and the grounds for the finding.
13. Has your firm or any of its owners, officers or partners ever been convicted of a crime involving any
federal, state, or local law related to construction?
❑ Yes ❑ No
No = 5 points Yes = subtract 5 points
If "yes," explain on a separate signed page, including identifying who was involved, the name of the
public agency, the date of the conviction and the grounds for the conviction.
14. Has your firm or any of its owners, officers or partners ever been convicted of a federal or state
crime of fraud, theft, or any other act of dishonesty?
❑ Yes ❑ No
No = 5 points Yes = subtract 5 points
If "yes," identify on a separate signed page the person or persons convicted, the court (the county if a
state court, the district or location of the federal court), the year and the criminal conduct.
15. If your firm was required to pay a premium of more than one per cent for a performance and
payment bond on any project(s) on which your firm worked at any time during the last three years,
state the percentage that your firm was required to pay. You may provide an explanation for a
percentage rate higher than one per cent, if you wish to do so.
5 points if the rate is no more than 0.8%
3 points if the rate was no higher than 1.0%
0 points for any other answer.
16. During the last ten years, has your firm ever been denied bond credit by a surety company, or has there
ever been a period of time when your firm had no surety bond in place during a public construction
6roject when one was required?
Yes ❑ No
No = 5 points Yes = 0 points
If yes, provide details on a separate signed sheet indicating the date when your firm was denied
coverage and the name of the company or companies which denied coverage; and the period during
which you had no surety bond in place.
End of Section I
BP Contractor Qualification Questionaire.doc 15 of 30 4114/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
Date
Section II
Questions about compliance with safety, workers compensation, prevailing wage and apprenticeship laws.
(11 questions)
1. Has CAL OSHA cited and assessed penalties against your firm for any "serious," "willful" or "repeat"
violations of its safety or health regulations in the past ten years?
Note: If you have filed an appeal of a citation and the Occupational Safety and Health Appeals
Board has not yet ruled on your appeal, you need not include information about it.
❑ Yes ❑ No If "yes" How Many?
5 points for "No" such instance.
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if more than 1 such instances.
If "yes," attached a separate signed page describing the citations, including information about the
dates of the citations, the nature of the violation, the project on which the citation(s) was or were
issued, the amount of penalty paid, if any. If the citation was appealed to the Occupational Safety
and Health Appeals Board and a decision has been issued, state the case number and the date of the
decision.
2. Has the federal Occupational Safety and Health Administration cited and assessed penalties against
your firm in the past ten years?
Note: If you have filed an appeal of a citation and the appropriate appeals Board has not yet
ruled on your appeal, you need not include information about it.
❑ Yes ❑ No If "yes" How Many?
If yes, attach a separate signed page describing each citation.
5 points for "No" such instance.
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if more than 1 such instance.
If "yes," attach a separate signed page describing each citation.
3. Has the EPA or any Air Quality Management District or any Regional Water Quality Control Board
cited and assessed penalties against either your firm or the owner of a project on which your firm
was the contractor, in the past ten years?
NOTE: If you have filed an appeal of a citation and the Appeals Board has not yet ruled on
your appeal, or if there is a court appeal pending, you need riot include information about the
citation.
❑ Yes ❑ No If "yes" How Many?
5 points for "No" such instance.
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" if more than 1 such instance.
If "yes," attach a separate signed page describing each citation.
4. How often do you require documented safety meetings to be held for construction employees and field
supervisors during the course of a project?
5 Points for answer of twice each week or more often.
3 points for an answer of once each week.
0 points for any other answer
BP Contractor Qualification Questionaire.doc 16 of 30 4114/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
Date
List your firm's Experience Modification Rate (EMR) (California workers' Compensation insurance) for
each of the past three premium years:
NOTE: An Experience Modification Rate is issued to your firm annually by your workers'
compensation insurance carrier.
Current year:
Previous year:
Year prior to previous year:
If your EMR for any of these three years is or was 1.00 or higher, you may, if you wish, attach a
letter of explanation.
NOTE: An Experience Modification Rate is issued to your firm annually by your workers'
compensation insurance carrier.
5 points for three-year average EMR of .85 or less
3 points for three-year average of EMR of more than .85 but no more than 1.00
0 points for any other EMR
6. Within the last ten years, has there ever been a period when your firm had employees but was without
workers' compensation insurance or state -approved self-insurance?
❑ Yes ❑ No
5 points for "No".
0 points for or "Yes"
If "yes," please explain the reason for the absence of workers' compensation insurance on a separate
signed page. If "No," please provide a statement by your current workers' compensation insurance
carrier that verifies periods of workers' compensation insurance coverage for the last five years. (If your
firm has been in the construction business for less than five years, provide a statement by your workers'
compensation insurance carrier verifying continuous workers' compensation insurance coverage for the
period that your firm has been in the construction business.)
7. Has there been more than one occasion during the last five years on which your firm was required to pay
either back wages or penalties for your own firm's failure to comply with the state's prevailing wage
laws?
❑ Yes ❑ No If "yes" How Many?
NOTE: This question refers only to your own firm's violation of prevailing wage laws, not to
violations of the prevailing wage laws by a subcontractor.
5 points for "No" such instance.
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" and more than 1 such instance.
If "yes," attach a separate signed page or pages, describing the nature of each violation, identifying the
name of the project, the date of its completion, the public agency for which it was constructed; the
number of employees who were initially underpaid and the amount of back wages and penalties that you
were required to pay.
BP Contractor Qualification Questionaire.doc 17 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Dale
8. During the last five years, has there been more than one occasion on which your own firm has been
penalized or required to pay back wages for failure to comply with the federal Davis -Bacon prevailing
wage requirements?
❑ Yes ❑ No If "yes" How Many?
5 points for "No" such instance.
3 points for "Yes" indicating 1 such instance.
0 points for "Yes" and more than 1 such instance.
If "yes," attach a separate signed page or pages describing the nature of the violation, identifying the
name of the project, the date of its completion, the public agency for which it was constructed; the
number of employees who were initially underpaid, the amount of back wages you were required to
pay along with the amount of any penalty paid.
9. Provide the name, address and telephone number of the apprenticeship program sponsor(s)
(approved by the California Division of Apprenticeship Standards) that will provide apprentices to
your company for use on any public work project for which you are awarded a contract by the City
of Lodi.
5 points if at least one approved apprenticeship program is listed.
0 points for any other answer.
10. State the number of individuals who were:
(a) Employed by your firm as apprentices at any time during the past three years
(b) Identify the craft or crafts in which your firm employed apprenticeship training in the past
three years.
(c) State the number of individuals who, during the past three years, completed apprenticeships in
each craft while employed by your firm.
5 points if one or more persons completed apprenticeship while employed by your firm.
0 points if no persons completed apprenticeship while employed by your firm.
11. At any time during the last five years, has your firm been found to have violated any provision of
California apprenticeship laws or regulations, or the laws pertaining to use of apprentices on public
works?
❑ Yes ❑ No. If "yes" How Many?
If yes, provide the date(s) of such findings, and attach copies of the Department's final decision(s).
5 points for either "No," or "Yes" indicating either 1 or 2 such instance.
3 points for "Yes" indicating 3 such instances.
0 points for "Yes" and more than 3 such instances.
If "yes," provide the date(s) of such findings, and attach copies of the Department's final decision(s).
End of Section II
BP Contractor Qualification Questionaire.doc 18 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Preaualification
Section III
Ouestion concerning recent construction proiects completed
Project Examples
Dale
Using the attached Project Data Sheets, you must submit three (3) of the largest
(Dollar Value) completed or ongoing projects in the last five (5) years that are more
than 75% complete by your firm, and which demonstrate technical complexity in
materials and construction methods for projects similar to the City of Lodi
PROJECT
Provide the names of the projects, the owners, the project managers, the size of the
projects and when those projects were completed (if completed) as well as all other
information requested on the attached "Project Data Sheet", for each project. The
City will forward the reference questionnaire directly to the listed owners for
completion and return to the City of Lodi. The individual furnishing the information
in the reference questionnaire should be the project managers or the heads of the
department in charge of the construction of the projects listed. The City of Lodi
reserves the right to seek additional information from any individual who has
information about the listed projects.
To effectuate the candid completion of the information requested in the reference
questionnaire in section III, you are required to execute and submit the attached
Reiease and Waiver of Liability in favor of each individuai furnishing information
requested in the questionnaire.
The highest possible score for each reference is 30 points. If a contractor scores
less than 17 points on a single reference, the contractor is NOT qualified to bid on
this project.
BP Contractor Qualification Questionaire.doc 19 of 30 4/14/200
City of Lodi
P12OJEc'r
Prime Contractor Preaualification Date
Candidate Name: Date:
PROJECT DATA SHEET (One of Three References)
Project Name:
Location:
Owner:
Owner Contact (name, email and current phone number):
Architect or Engineer:
Architect or Engineer Contact (name, email and current phone number):
Construction Manager (name, email and current phone number):
Registered Managing Employee (name, email and current phone number):
Description of Project, Scope of Work Performed:
Total Value of Construction (including change orders):
Original Scheduled Completion Date:
Time Extensions Granted (number of days):
Actual Date of Completion:
Liquidated Damages? Yes No
Claims? Yes
1\l•7
BP Contractor Qualification Questionaire.doc 20 of 30 4/14/2010
City of Lodi
PROJLC1,
Prime Contractor Prequalification
Candidate Name: Date:
PROJECT DATA SHEET (Two of Three References)
Project Name:
Location:
Owner:
Owner Contact (name, email and current phone number):
Architect or Engineer:
Architect or Engineer Contact (name, email and current phone number):
Construction Manager (name, email and current phone number):
Registered Managing Employee (name, email and current phone number):
Description of Project, Scope of Work Performed:
Total Value of Construction (including change orders):
Original Scheduled Completion Date:
Time Extensions Granted (number of days):
Actual Date of Completion:
Liquidated Damages? Yes
No Claims? Yes
IR
Date
BP Contractor Qualification Questionaire.doc 21 of30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
Candidate Name:
Project Name:
Location:
Date:
PROJECT DATA SHEET (Three of Three References)
Owner:
Owner Contact (name, email and current phone number):
Architect or Engineer:
Architect or EngineerContact (name, email and current phone number):
Construction Manager (name, email and current phone number):
Registered Managing Employee (name, email and current phone number):
Description of Project, Scope of Work Performed:
Total Value of Construction (including change orders):
Original Scheduled Completion Date:
Time Extensions Granted (number of days):
Actual Date of Completion:
Liquidated Damages? Yes No Claims? Yes No
Date
BP Contractor Qualification Questionaire.doc 22 of 30 4/14/2010
City of Lodi
PROJECT
T
Prime Contractor Prequalification Date
RELEASE AND WAIVER AGREEMENT
This Release and Waiver of Liability (hereinafterthe "Release") is entered into between the
City of Lodi (City) and
"General Contractor').
RECITALS
, a general contractor (hereinafter
1. The City of Lodi has issued a Requestfor Pre-qualificationto establish a pool of general
contractors qualified to bid on the PROJECT.
2. General Contractor has submitted a response to the City's Request for Pre -qualifications and
has submitted three projects and three owners as references for its qualifications.
3. The City seeks candid comments on the General Contractor's performance on the listed
projects from the owners and the owners' representatives.
RELEASE AND WAIVER
General Contractor hereby fully and forever releases, exonerates, discharges, and covenants
not to sue the City, its commissions and boards, officers and employees, and all individuals and
entities furnishing comments on general contractors' performance from and for any and all claims,
causes of action, demands, damages and any and all other liabilities of any kind or description, in law,
equity, or otherwise arising out of information furnished about General Contractor's performance on
the projects.
IN? )EI BENEFIGARI ES
The City, its commissions and boards, officers and employees and all individuals and entities
furnishing any information relating to General Contractor's qualifications are intended beneficiariesof
this Release and Waiver and are entitled to enforce its terms.
Dated:
GENERAL CONTRACTOR
Authorized Representative
BP Contractor Qualification Questionaire.doc 23 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor
THIS PAGE PROVIDED FOR INFORMATIONAL PURPOSES ONLY
Date
REFERENCE QUESTIONNAIRE (for City of Lodi distribution to Contractor References)
The City of Lodi is undertaking a process to pre -qualify general contractors for the PROJECT.
The following general contractor: , has provided the City of
Lodi with the name of your organization and the following project:
as references regarding the Contractor's experience and
qualifications to perform work on City projects. The Contractor has signed a Release and Waiver of
Liability form as to the information you provide, a copy of which is attached for your reference.
Please complete and return the questionnaire to:
City of Lodi Public Works Department
Attention: GaryWiman
P.O. Box 3006, Lodi, CA, 95241-1910.
Please give a brief description of the project; be sure to include the value of the project and the scope
of work involved.
1. On a scale of 1-5, with 5 being the best, did the Contractor respond in a timely and responsible
manner to stop notices or liens on the project?
2. On a scale of 1-5, with 5 being the best, did the Contractor provide adequate equipment,
personnel and supervision on the job? _
3. On a scale of 1-5, with 5 being the best, was the Contractor timely in providing reports and other
paperwork, including change order paperwork and scheduling updates?
4. On a scale of 1-5, with 5 being the best, rate how the Contractor performed in the area of turning
in Operations and Maintenance manuals, completing as -built drawings, providing required training
and taking care of warranty items.
5. On a scale of 1-5, with 5 being the best, how would you rate the quality of work overall?
6. On a scale of 1-5, with 5 being the best, would you like to have this contractor perform work on a
similar contract for you in the future?
Initials of person filling out form Date
BP Contractor Qualification Questionaire.doc 24 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
SECTION IV
Experience and Resumes
Candidate Name:
Date:
Date
This form must be completed and submitted along with the Candidate Contact Information Form,
Parts, I, II and III of the Requestfor Qualifications in addition to the company resume and resumes of
any staff identified in this questionnaire if you wish to be considered a qualified candidate for:
PROJECT
Experience:
1) Do you —as a company or among your principal staff —have experience in constructing at
least three (3) PROJECT each with a minimum construction cost of $000 within the last 10
years?
YES NO
On a separate sheet of paper, please describe qualifying project experience, including;
a) Project name and location,
b) Names of principal staff responsiblefor delivery of project,
c) Scope of work performed,
d) List the treatment processes constructed or modified,
e) The owners name and contact information,
D CM firm (if applicable) including name and contact information,
g) Original contract amount/final contract amount (if different please explain, include
description of significant contract modifications),
h) Original contract duration/final duration (if different please explain, include description of
significant events/strategies impacting schedule changes)
i) List names and contacts for each of the major subcontractors managed on each listed
project. Please describe specific work performed by others and indicate your relationship
with these other firms.
2) Do you —as a company or among your principal staff —have a minimum of 10 years of
PROJECT construction experience within the last 10 years in the following?
Yes
No
Yes
No
Yes
No
Yes
No
On a separate sheet of paper, please describe qualifying project experience, including;
a) Project name and location,
b) Scope of work performed,
c) Original contract start date and final completion date,
d) If managed only, list names of involved sub -contractors,
e) Ifrelying on principal staff experience, please list names and individual years of
experience.
BP Contractor QualiiicationQuestionaire,doc 25 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification
Date
3) Do you —as a company or among your principal staff —have 5 years experience in the
construction or modification of the following facilities?
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
On a separate sheet of paper, please describe qualifying project experience, including;
D Project name and location,
g) Scope of work performed,
h) Original contract start date and final completion date,
i) If managed only, list names of involved sub -contractors,
j) If relying on principal staff experience, please list names and individual years of
experience.
4) Do you —as a company or among your principal staff —have 10 years experience in
managing or building?
Yes No
Yes No
Yes No
On a separate sheet of paper, please describe qualifying project experience, including;
k) Project name and location,
I) Scope of work performed,
m) Original contract start date and final completion date,
n) If managed only, list names of involved sub -contractors,
o) If relying on principal staff experience, please list names and individual years of
experience.
5) Does your company have field engineers and/or superintendentswith a minimum of five
years experience in PROJECT work within the last 10 years?
YES NO
On a separate sheet of paper, please list names of field engineers and/or superintendents, individual
years of experience and their pump station project experience. Please include project start and end
dates, as well as each field engineer's or superintendent's position and affiliation during each project.
PLEASE PROVIDE COMPANY RESUME AND RESUMES OF PRINCIPAL STAFF IDENTIFIED
ABOVE TO DEMONSTRATE REQUIRED EXPERIENCE.
End of Section
BP Contractor Qualification Questionaire.doc 26 of 30 4/14/200
City of Lodi
PROJECT
Prime Contractor
APPENDIX A
Date;
QUALIFICATION PROTEST
PROCEDURES
BP Contractor Qualification Questionaire.doc 27 of 30 4/1412010
City of Lodi
PROJECT
Prime Contractor Prequalification
PROTEST PROCEDURES
Date
Under certain circumstances, an interested party to a procurement may protest to the City of
Lodi the Qualifications to bid on a specificproject or contract.
All solicitation documents shall include Qualification Protest Procedures, either explicitly or by
reference. These procedures are intended to ensure that valid complaints are properly handled and
responded to
The term protest is utilized to describe the controversies that arise during the Qualification
process as an objection to a decision on Qualification to provide a proposal or bid. The protests are
challenges to actual or proposed actions of the contracting officers on specific procurements. These
objections are brought by offerors, prospective offerors, or other interested parties who contend that
they have been improperly treated in the procurement process. All protests must be submitted in
writing.
CITY OF LODI PROTEST PROCEDURES
GENERAL CONDITIONS
The City of Lodi's review of any protest will be limited to violations of state or local laws or
regulations, violations of the City of Lodi's purchasing procedures, or violations of the City of Lodi's
protest procedures or failure to review a complaint or protest.
Protests must be received by the City of Lodi within a reasonable time after the Contractor
receipt of notice of non -qualification but no later than fifteen (15) caiendar days after the issuance of
the non -qualification by the City. All other protests must be received by the City of Lodi within five
(5) days of the action on which the protest is based.
The initial protest filed with the City of Lodi shall be in writing and shall:
1. Include the name, address and telephone number of the protester; and the name of a contact
person.
2. Identify the number, date and description of the solicitation.
3. Contain a statement of the grounds for protest and any supporting documentation. The
grounds for the protest must be supported to the fullest extent feasible. Additional
materials in support of an initial protest will be considered only if filed within the time
limits specified.
4. Indicate the ruling or relief desired from the City of Lodi.
A protest may be considered, even if the initial filing is late, under the following circumstances:
1. Good cause based on compelling reasons beyond the protester's control, whereby the
lateness is due to the fault of the City of Lodi in the handling of his/her protest submission.
2. The City of Lodi determines the protest raised significant issues to a procurement practice
or procedure.
3. A court of competentjurisdiction requests, expects or otherwise expresses interest in the
City of Lodi's decision.
BP Contractor QualificationQuestionaire.doc 28 of 30 411412010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
No formal briefs or other technical forms of pleading or motion are required, but a protest and
other submissions should be concise, logically arranged, clear and legible.
Any additional information requested or required by the City of Lodi from the protester, or
interested parties shall be submitted as expeditiously as possible, but in no case later than five (5) days
after the receipt of such request unless specifically excepted by the City of Lodi.
CONFIDENTIALITY
Materials submitted by a protester will not be withheld from any interested party outside of the
City of Lodi or from any Government agency which may be involved in the protest, except to the
extent that the withholding of information is permitted or required by law or regulation. If the protester
considers that the protest contains proprietary materials which should be withheld, a statement advising
of this fact may be affixed to the front page of the protest document and the alleged proprietary
information must be so identified wherever it appears.
FURNISHING OF INFORMATION ON PROTESTS
The City of Lodi shall, upon request, make available to any interested party, information
bearing on the substance of the protest, including:
1. Any other documents that pertain to the protest, including correspondence with the bidders;
and
2. A statement by the City of Lodi explaining its actions and the reasons for them.
A conference on the merits of the protest with members of the City of Lodi Protest Review
Panel (defined below) may be held at the request of the protester. The request for a conference should
be made in a timely manner so as not to interfere with the resolution of the protest and not later than
twenty (20) days after the initial protest was filed.
WITHHOLDING OF AWARD
When a protest has been filed before the opening of bids the City of Lodi will not make an
award for five days following its decision on the protest. When a protest has been filed after the award
but prior to the execution of a contract, the City of Lodi will not proceed with the execution of the
contract prior to the resolution of the protest. Exceptions to the above may occur if the City of Lodi
determines that:
1. The items to be procured are urgently required; or
2. Delivery or performance will be unduly delayed by failure to either make the award
promptly or to continue with the procurement; or
3. Failure to make prompt award or to continue with the procurement will otherwise cause
undue hardship to the City of Lodi or other local, state or federal governments.
BP Contractor Qualification Questionaire.doc 29 of 30 4/14/2010
City of Lodi
PROJECT
Prime Contractor Prequalification Date
PROTEST REVIEW -LEVEL ONE
Upon receipt of a protest, the City Manager will appoint an ad hoc City of Lodi Protest Review
Panel to review all relevant materials associated with the protest. The panel will be comprised of three
(3) representatives of the City of Lodi appointed by the City Manager; Including the City Department
Head, Construction Project Manager, and one other City staff member knowledgeable in the specific
project. The Panel shall determine the validity of the protest and what actions will be taken.
The panel will be directed to prepare a report within fifteen (15) calendar days. The Panel will
notify the protester and any interestedparties of their findings and actions and of the procedures for
requesting reconsideration. The report shall include the following as relevant:
1. Copies of all relevant documents;
2. A copy of the Invitation for Bid or Request for Proposal, including pertinent provisions of
the specifications.
PROTEST REVIEW -LEVEL TWO
Reconsideration of a decision by the City of Lodi may be requested by the protester or any
interested party. The request for reconsideration shall contain a detailed statement of the factual and
legal grounds upon which reversal or modification is deemed warranted, specifying any errors of law
or fact made.
The request for reconsideration of the City of Lodi Protest Review Panel's decision shall be
filed no later than ten (10) days after the Panel issues its written report, and shall be filed with the City
Attorney.
Upon receipt of the request for reconsideration, the City Manger shall schedule an informal
administrative hearing with the aggrievedparty and the City of Lodi Protest Review Panel. The
hearing shall be held not later than fifteen (15) days after the receipt of the request for reconsideration.
The City Attorney shall issue, in writing, the City of Lodi's final determination of the reconsidered
protest within five (5) days of the administrative hearing. The appellant process ends with the City
Attorney's decision; however, the aggrievedparty may ask the City Council to review the City
Attorney's decision. The aggrievedparty has those remedies afforded by the state courts, as well.
The City of Lodi may refuse to decide any protest where the matter involved is the subject of
litigation before a court of competentjurisdiction.
The City of Lodi shall not be responsible for any protests not filed in a timely manner.
End of Section
BP Contractor Qualification Questionaire.doc 30 of 30 4/14/2010
RESOLUTION NO. 2010-55
A RESOLUTION OF THE LODI CITY COUNCIL
ESTABLISHING A STANDARDIZED QUESTIONNAIRE
FOR BIDDER QUALIFICATIONS AS PROVIDED BY
PUBLIC CONTRACTS CODE 20101
WHEREAS, Public Contracts Code Section 20101 gives public entities the right
to use a Bidder Qualification Questionnaire in order to ensure that prospective bidders
have the appropriate experience, qualifications, and financial stability to perform the
work for a specific project; and
WHEREAS, the Code requires the Public Agency to adopt and apply a uniform
system of rating bidders on the basis of the completed questionnaire and financial
statements, in order to determine both the minimum requirements permitted for
qualification to bid, and the type and size of the contracts upon which each bidder shall
be deemed qualified to bid. The uniform system of rating prospective bidders shall be
based on objective criteria. An appeals process is also required to permit bidders to
appeal the rating; and
WHEREAS, the City of Lodi questionnaire is comprised from and modeled after
an example questionnaire created by the State of California Department of Industrial
Relations; and
WHEREAS, the qualification process will typically be used on very large projects
or technically -challenging projects where expertise and experience in certain trades is
required.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
establish a standardized questionnaire for bidder qualifications as provided by Public
Contracts Code Section 20101.
Dated: May 5, 2010
I hereby certify that Resolution No. 2010-55 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held May 5, 2010, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Hitchcock, Johnson, Mounce, and
Mayor Katzakian
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS— None
ZD1 JOHL
City Clerk
2010-55