HomeMy WebLinkAboutAgenda Report - April 6, 2011 C-09AGENDA ITEM C 0
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Contract for Municipal
Service Center Parking Lot Improvement Project with A.M. Stephens Construction
Company, Inc., of Lodi ($183,456.85) and Appropriating Funds ($91,000)
MEETING DATE: April 6, 2011
PREPARED BY: PublicWorks Director
RECOMMENDED ACTION: Adopt resolution authorizing City Managerto execute contractfor
Municipal Service Center parking lot improvement project with
A.M. Stephens Construction Company, Inc., of Lodi, in the amount
of $183,456.85 and appropriating funds in the amount of $91,000.
BACKGROUND INFORMATION: This project consists of reconstructing the Municipal Service Center
(MSC) parking lot by removing the existing asphalt and replacing it with
new asphalt (Exhibit A). This project will complete the reconstruction of
the parking areas at the MSC that was begun with the construction of
the new Transit Shop and secured -entry faci I ities. This project follows other recently -completed work,
including the decommissioning of the old shop, replacement of the PBX communicationsfacilities, and
construction of new communications and electrical conduits across the MSC yard.
This projectwas included in the adopted Fiscal Year 2010/11 Capital Improvement Plan, but an
additional appropriation of $91,000 is needed to cover costs for expanded scope of construction,
engineering, construction inspection and contingencies. The budget appropriation for the projectwas
$130,000. The total project cost is estimated to be $221,000. The project costs are jointly funded by
Measure K, Water Capital, Wastewater Capital, and Electric Utility Capital.
Plans and specifications for this projectwere approved on February 16, 2011. The City received the
following 12 bids for this project on March 16, 2011.
Bidder
Location
Bid
Engineer's Estimate
$185,455.00
A.M. Stephens Construction
Lodi
$183,456.85
Sierra Asphalt
Rancho Cordova
$184,474.75
Galedrige Construction
Alviso
$194,091.80
Knife River Construction
Stockton
$194,326.00
B&BAsphalt, Inc.
Sacramento
$196,549.00
Martin General Engineering
Rancho Cordova
$200,351.00
Granite Construction
Stockton
$208,306.00
JB Bostick Company
Roseville
$208,816.37
MCI Engineering
Stockton
$217,112.50
Robert Burns Construction
Stockton
$217,233.90
George Reed Construction
Modesto
$219,518.75
Dryco Construction
Fremont
$228,801.91
APPROVED: ztt�Z�
onradt Bartlam, ity Manager
K:\WP\PROJECTSWIISC\MSC Parking Lot\CAward.doc 3/23/2011
Adopt Resolution Authorizing City Manager to Execute Contract for Municipal Service Center Parking Lot
Improvement Project with A.M. Stephens Construction Company, Inc., of Lodi ($183,456.85) and
Appropriating Funds ($91,000)
April 6, 2011
Page 2
FISCAL IMPACT: There will be a decrease in pavement repair costs at the MSC.
FUNDING AVAILABLE: Requested Appropriation:
Measure K Maintenance Fund (325): $16,150
Water Capital Fund (181): $23,060
Wastewater Capital Fund (171): $23,060
Electric Capital Fund (161): $28,730
Total: $91,000
C-Afz;-�
Jordan Ayers
Deputy City Manager/Internal Lrxirp; Director
Eli et A. Kirkley F. Wally Sa e n
Electric Utility Director Public Works Director
Prepared by Lyman Chang, Senior Civil Engineer
FWS/LC/pmf
Attachment
cc: Deputy PublicWorks Director— Utilities
Electric Utility Director
Senior Civil EngineerChang
K:\WIRTROJECTSWISC\MSC Parking Lot\CAward.doc 3/17/2011
•Exhibit A
'• CITY OF LODI MSC Parking Lot
• PUBLIC WORKS DEPARTMENT ` Reconstruction J
..\
r
...\ 3
.............
..............._
.................. ....... •+
..... ..... _...... ._......... ..Y`^..
............. .................. ................. s3
r
. . ...�..
GAly
:WAREHOUSE::::.-::.- ............::._.... -:::.....•
............... _.._....._... .._...... _.................
........ .................. ..................................... ................. % .:..
S
................. ...........
....... .
._._._.
\— —i \ '
LORUNG DOUf
T T I� Tl- cl ..Atter-17 L 17 L I�`:';
� �.....
KOFU PARK PARKING LOT
1I L Lb,. `-. LI...lw L J L U j L ll
lu II P�,k fi.Y ✓'
.x -x
I�ENG OFSUDE GRIE �CONG BLRS� YIR
A A
cr�4�
I v Is
_--p
:AILER J EEcvu r
\\cNG rauR —
�,\�\-�
� \ OTEL LW
o \�
GARAGE \
R xR \ \\ \
0
GREA9
:RIE NEYLOCKSOX SUU] 6F
\\\\\UBLIC\\ORKS\ � -\\\\\ 1 � -
:W
\ \W
D
\:.Nf IRR D@11RDL B0X - .........
BUIWNG
J
RRF G�$ \��\ \_
O .... .....
� .. 1RRNHfbPLER
mumrl I E�.1
wx x!— ELEC LHPRGER G -VETE J:
...... _ ............. i I: ...e
0 :ISI
ANIMAL \
\S7ELER
o L \
`\
p ... �....... �:.�:
If
Ow
�WRTER SINRGFi�
BINIPB 6 LOVFHED PNUDN;
....'.�''............ I ......... .._.......... _.
PROPOSED PARKING LOT
IMPROVEMENT
I
K:\CADD\PROJECTS\2010\010D002\010D002.dwg, MSC- C2 (2), 07/21/201(1:00:08 PM
MUNICIPAL SERVICE CENTER (MSC)
PARKING LOT IMPROVEMENTS CONTRACT
1331 South Ham Lane
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and A.M. STEPHENS CONSTRUCTION COMPANY, INC., herein
referred to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents, which are filed in the Public Works
Department and which are incorporated herein by this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 2002 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
CONTRACTLOC 1 03/16/2011
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
Perform the work necessary to reconstruct the Municipal Service Center (MSC) parking lot with
asphalt concrete, all as shown on the plans and specifications for "Municipal Service Center
(MSC) Parking Lot Improvements".
TOTAL $ 183,456.85
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
Contract. DOC 2 03/16/11
CONTRACT ITEMS
ITEM
EST'D.
NO.
DESCRIPTION
UNIT
QTY
UNIT
PRICE
TOTAL PRICE
1.
Pavement Removal
SF
55,670
$
0.24
$
13,360.80
2.
Storm Water Pollution Control
Plan
LS
1
$
3,000.00
$
3,000.00
3.
Compact Original Ground
SF
55,670
$
0.22
$
12,247.40
4.
Asphalt Concrete
Ton
1,649
$
78.85
$
130,023.65
5.
Adjust Manhole Frame and
Cover to Grade
EA
1
$
600.00
$
600.00
6.
Adjust Water Valve Frame and
Cover to Grade
EA
5
$
295.00
$
1,475.00
7.
Adjust Water Meter Box to
Grade
EA
7
$
265.00
$
1,855.00
8.
Adjust Sewer Clean Out to
Grade
EA
1
$
295.00
$
295.00
9.
Install City -Furnished Traffic
Loops
LS
1
$
1,600.00
$
1,600.00
10.
Install Storm Water Interceptor
EA
1
$
19,000.00
$
19,000.00
TOTAL $ 183,456.85
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
Contract. DOC 2 03/16/11
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 20 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLEAND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Konradt Bartlam
City Manager
By: Date:
Title
(CORPORATE SEAL)
Attest:
City Clerk
Approved As To Form
113-.S-t4phin Schwabauer
City Attorney
Contract. DOC 03116111
1. AA#
2. JV#
z �
TO:
Internal Services Dept. - Budget Division
3. FROM:
Rebecca Areida-Yadav 15. DATE: 03/24/2011
4. DEPARTMENT/DIVISION: Public Works
'lease provide a description of the project, the total cost of the project, as well as justification for the
equested adjustment. If you need more space, use an additional sheet and attach to this form.
;ontract with A.M. Stephens for the Municipal Service Center parking lot improvement project. Appropriation request
ncludes contract amount, engineering, construction inspection and contingencies.
Council has authorized the appropriation adjustment, complete the following:
Ileeting Date: Res No: Attach copy of resolution to this form.
)epartment Head Signature:
ager Date
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
FUND #
BUS. UNIT #
ACCOUNT #
ACCOUNT TITLE
AMOUNT
A.
325
3205
Fund Balance
$
16,150.00
SOURCE OF
181
3205
Fund Balance
$
23,060.00
FINANCING
171
3205
Fund Balance
$
23,060.00
161
3205
Fund Balance
$
28,730.00
B.
USE OF
FINANCING
j
325
325357
7720
MSC Reconstruct Pavement
16 150.00
181 18135.7 1825.1200 MSC Reconstruct Pavement
23 060.00
171 171357 1825.1200 MSC Reconstruct Pavement
161 L 161357 1825.1200 MSC Reconstruct Pavement $
23 060.00
28 730.00
I i
'lease provide a description of the project, the total cost of the project, as well as justification for the
equested adjustment. If you need more space, use an additional sheet and attach to this form.
;ontract with A.M. Stephens for the Municipal Service Center parking lot improvement project. Appropriation request
ncludes contract amount, engineering, construction inspection and contingencies.
Council has authorized the appropriation adjustment, complete the following:
Ileeting Date: Res No: Attach copy of resolution to this form.
)epartment Head Signature:
ager Date
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2011-45
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING THE CITY MANAGER TO EXECUTE
CONTRACT FOR THE MUNICIPAL SERVICE CENTER
PARKING LOT IMPROVEMENT PROJECT AND FURTHER
APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of this
City Council, sealed bids were received and publicly opened on March 16, 2011, at 11:00 a.m., for
the Municipal Service Center Parking Lot Improvement Project described in the plans and
specifications therefore approved by the City Council on February 16, 2011; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with the
City Manager as follows:
Bidder
Bid
A.M. Stephens Construction
$183,456.85
Sierra Asphalt
$184,474.75
Galedrige Construction
$194,091.80
Knife River Construction
$194,326.00
B&BAsphalt, Inc.
$196,549.00
Martin General Engineering
$200,351.00
Granite Construction
$208,306.00
JB Bostick Company
$208,816.37
MCI Engineering
$217,112.50
Robert Bums Construction
$217,233.90
George Reed Construction
$219,518.75
Dryco Construction
$228,801.91
WHEREAS, staff recommends awarding the contract for the Municipal Service Center
Parking Lot Improvement Project to the low bidder, A.M. Stephens Construction Company, Inc., of
Lodi, California, in the amount of $183,456.85.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize
the City Manager to execute the contract for the Municipal Service Center Parking Lot Improvement
Project with the low bidder, A.M. Stephens Construction Company, Inc., of Lodi, California, in the
amount of $183,456.85; and
BE IT FURTHER RESOLVED that funds in the amount of $91,000 be appropriated from
Measure K Maintenance Fund, Water Capital Fund, Wastewater Capital Fund, and Electric Capital
Fund for this project.
Dated: April 6, 2011
----------------------------------------------------------------------------
----------------------------------------------------------------------------
hereby certify that Resolution No. 2011-45 was passed and adopted by the City Council of
the City of Lodi in a regular meeting held April 6, 2011, by the following vote:
AYES: COUNCIL MEMBERS— Hansen, Katzakian, Mounce, Nakanishi, and
MayorJohnson
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS—None
RANDIJOHL
City Clerk
2011-45