HomeMy WebLinkAboutAgenda Report - March 7, 1990 (48)�CITY OP LODI
PUBLIC WORKS DEPARTMENT
COUNCIL COMMUNICATION
RECOMMENDED ACTION: That the City Council approve the plans and
specifications for the above project and authorize advertising for bids.
BACKGROUND INFORMATION: This project consists of placing approximately
1,250 tons of asphalt concrete; 6,060 square yards of pavement reinforcing
fabric; 3,430 square feet of pavement repair; 5,415 linear feet of pavement
grinding, and other incidental and related work, all as shown on the plans
and specifications for the project.
ack . Ronsko
ubli Works Director
JLR/LC/mt
cc: Purchasing Officer
Street Superintendent
APPROVED:
COVERLA5/TXTW.
na
FILE NO.
ca, 7390
Project Data
Originally B�ted:i
1989
T0:
City Council
Budgeted Fund: General Gas
Tax & TDA
Amount Budgeted:
$108,000
FROM:
City Manager
Total Project Estimate:
$109,000
Bid Opening Date:
3/21/90
MEETING DATE:
March 7, 1990
AGENDA TITLE:
Plans and Specifications and Advertisement for Bids
for
1990 Asphalt Overlay,
Tokay Street and Lodi. Avenue
RECOMMENDED ACTION: That the City Council approve the plans and
specifications for the above project and authorize advertising for bids.
BACKGROUND INFORMATION: This project consists of placing approximately
1,250 tons of asphalt concrete; 6,060 square yards of pavement reinforcing
fabric; 3,430 square feet of pavement repair; 5,415 linear feet of pavement
grinding, and other incidental and related work, all as shown on the plans
and specifications for the project.
ack . Ronsko
ubli Works Director
JLR/LC/mt
cc: Purchasing Officer
Street Superintendent
APPROVED:
COVERLA5/TXTW.
na
FILE NO.
ca, 7390