Project Data
Originally Budgeted: 1987/88
TO: City Council Budgeted Fund: 1986 Community,
Parklands'3rant
FROM: City Manager Amount Budgeted: $26,900
Final Project Cost: $17,000
MEETING DATE: February 1, 1989
AGENDA TITLE: Accept Improvements Under Armory Park Sprinklers, 333 North r
Washington Street, Contract and Direct the Public Works
Director to File a Notice of Completion with the County
Recorder's Office
fi
F
p
RECOMMENDED ACTION: That the City Council accept the improvements for
"Armory Park Sprinklers, 333 North Washington Street and direct the Public
€ ..
Works Director to file a Notice of Completion with the County Recorder's
office.
BACKGROUND INFORMATION: The contract was awaraed to Galloway & Associates,
16 1988 in the amount of $13,863.00. The contract'
of �sca on on .November has'
,.
been completed in substantial conformance with the plans and specifications
approved by the City Council.
i
The contract completion date was February 24, 1989, and the actual completion
date was January 20, 1989. The final contract price was $13,863.00. The
funds remaining in this account will be spent on other protects included in ;
the Parklands rant description. ?
t
ack Ronsko
c Works Director