0% CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Approve Request for Proposal to Provide Professional Services for Preliminary
EngineeringWork on the Westside Substation (EUD)
MEETING DATE: October 21,2009
PREPARED BY: Interim Electric Utility Director
RECOMMENDED ACTION: Approve requestfor proposal to provide professional services for
preliminary engineering work on the Westside Substation.
BACKGROUND INFORMATION: The Electric Utility Department (EUD) has planned to build a fifth
substation at the western area of the City limits. The substation site
has been in Lodi's electric facilities plan for some time and was
purchased in 2003 as land was available. The working name for the planned facility is the Westside
Substation. This substation will be required for continued reliable service to new and existing customers.
The requestfor proposal will cover the preliminary engineering and design activities on the new Westside
Substation. The initial task list includes the following:
1. Soil resistivitytest and geotechnical study
2. Preliminary ground grid design as per IEEE Standard 80
3. Ground potential rise (GPR) study
4. Preparation of preliminary substation layout, design criteria, and cost/benefit analysis
5. Engineering and design of perimeter block wall fence and landscape
Items 1 and 2 are needed to complete the GPR study, which will be provided to the telephone and
communication companies for ground fault protection. Item 4 will be the basis for developing the final
substation facility design. Final design, permitting, and construction activities would follow the completion
of item 5.
The location of the new Westside Substation provides a strategic site for power system interconnection
within the City of Lodi boundaries. The existing 60kV loop will terminate in the substation. The other
planned 60kV line from the Industrial Substation traversing via Harney Lane through Lower Sacramento
Road will also terminate in the substation. On June 3, 2009 as per Resolution No. 2009-74, the City
Council awarded the preparation of Lodi West 60kV Power Line Project environmental impact report to
InSite Environmental, Inc. A double -circuit, 60kV transmission line, once completed, will connect to the
Westside Substation. The substation facility will provide load serving capacity to planned development
projects like Westside Project, Southwest Gateway Project and other identified annexation areas with a
total estimated load of approximately 16MW. The Westside substation will be used to reduce existing
loads from the Henning Substation.
APPROVED: f ZD0--
Blai ' g, City Manager
Approve Request for Proposal to Provide Professional Services for Preliminary Engineering Work on the Westside
Substation (EUD)
October 21, 2009
Page 2 of 2
The construction of new substation facility entails tasks requiring lengthy execution, adjustment, and
design and engineering activities as described in the attached ExhibitA. Therefore, staff is requesting
City Council approval of the requestfor proposal for the preliminary engineering work on the Westside
Substation.
FISCAL IMPACT: The estimated cost is $150,000.
FUNDING AVAILABLE: FromAccount No. 161677with additional fund transfer cf$30,OOOtothis
account from Account No. 161651.
GM. -
Deputy City Manager/Internal Services Director
1
,Kenneth A Weisel
Interim Electric Utility Director
PREPARED BY: Demy Bucaneg, Jr., P.E., Assistant Electric Utility Director, Engineering & Operations
KW/DB/Ist
Attachments (1)
Exhibit A
Westside Substation Timetable
Preliminary Engineering Phase
- Soil resistivity test =1 week
- Preliminary ground grid design = 2 weeks
- GPR study = 2 weeks
- Preparation of preliminary substation layout, design criteria, and cost/benefit
analysis = 5-6 months
- Engineering and design of perimeter block wall = 4-6 months
II. Block Wall Construction
- Environmental study - to be determined. If an exemption =1 week
- Approval and advertisement =1-2 months
- Bid process =1 month
- Award and contract approval = 2-3 months
- Permitting = 2 weeks
- Construction and turnover = 4-5 months
III. Substation Final Design Phase
- Approval of engineering services and advertisement =1-2 months
- Bid process = 2-3 months
- Award and contract approval = 2-3 months
- Engineering and design =10-12 months
- Approve plans and specifications =1-2 months
- Prepare specifications for long lead-time equipment = 2-3 months
- Approval and advertise equipment specifications =1-2 months
- Bid process =1-2 months
- Award and PO approval =1 month
- Order and delivery =14-18 months
IV. Environmental Study
- Initial study = 3-4 months
- Public hearings = 2-3 months
- Negative declaration approval = 2-3 months
V. Substation Construction
- Advertise and bid process = 2-3 months
- Award and contract approval = 2-3 months
- Construction =10-12 months
- Test and commissioning and turnover =1 month
Note: Estimated three to three and a half year Westside Substation development.