AGENDA TITLE: Contract Award for Blakely Park Restroom Remodel
MEETING DATE: October 16, 1991
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the
contract for the
above project to McDonald Glenn Company in the
amount of $45,219.00.
BACKGROUND INFORMATION: This project
will renovate the
deteriorated restroom in .
Blakely Park
by replacing the existing flat roof with a
pitched roof
snd providing handicap accessibility inside.
Community Development Block Grant Funds will be used to
finance this
project.
Plans and specifications for this project were approved
on September 18, 1991. The
City received the following five bids
for this project:
Bidder
Locaticn
Bid
Engineer's Estimate
$ 51,453.00
McDonald Glenn Company
Manteca
$ 45,219.00
Paragon Construction
Stockton
$ 48,711.00
Neth Construction
Stockton
$ 52,815.00
Diede Construction
Woodbridge
$ 55,000.00
RLA Construction
Stockton
$ 58,766.00
APPROVED:
THOMAS A. PETERSON
City Managw
CBLAKELY.1/TXTW.02M (CO.COM)
Cal
October 9, 1991
Contract Award. for Blakely Park Restroom Remodel
October 16, 1991
Page 2
FUNDING: Originall Budgeted:
Budgeted und:
Current Appropriation:
Total Project Estimate
Bid Opening Date:
1990
Community Development Block Grant Fund
$59,000
$59,000
ID/9/91
azdw)
. Jack L. Rm%ka
Public Works Director
Prepared by Wesley Fujitani , Senior Civil Engineer
JLR/WF/1m
Attachment
cc: City Attorney
Purchasing Officer
Senior Civil Engineer
Parks and Recreation Director
Eric Veerkamp
Wenell Mattheis Bowe
CBLAKELY.I/TXTW.02M (CO.COM)
October 9, 1991
RE90LUHON NO. 91-188
------------------------
........................
A RESOLUHON OF THE LODI CITY COUNCIL
AWARDING THE CONTRACT FOR GLAKELY PARK RESTROOM REMODEL
WHEREAS, in answer to notice duly published in accordance with
law and the order of this City Council, sealed bids were received and
publicly opened on October 9, 1991 at 11:00 a.m. for the contract for
Blakely Park Restroom Remodel, described in the specifications
therefor approved by the City Council on September 18, 1991; and
WHEREAS, said bids have been compared, checked, and tabulated .and
a report thereof filed with the City Manager as follows:
Bidder
Location
Bid
McDonald Glenn Company
Manteca
$
45,219.00
Paragon Construction
Stockton
$
48,711.00
Neth Construction
Stockton
$
52,815.00
Diede Construction
Woodbridge
$
55,000.00
RLA Construction
Stockton
$
58,766.00
WHEREAS, the City Manager recommends that award of the contract
for Blakely Park Restroom Remodel be made to the low bidder, McDonald
G1 enn Company;
NOW, THEREFORE, BE IT RINMMD by the Lodi City Council that
award of contract for Blakely Park Restroom Remodel be a: d the sme is
hereby awarded to McDonald Glenn Company, the low bidder, in the
amount of $45; 19.00.
Dated: October 16, 1991
I hereby certify that Resolution No. 91-188 was passed and
adopted by the City Council of the City of Lodi in a regular meeting
held October 16, 19 S'• y the following vote:
Ayes: Council Members - Pennino, Pinkerton, Sieglock, Snider
and Hinchman (Mayor)
Noes: Council Membets - None
Absent: Council Members - None
Alice M. Reimche
City Clerk
91-188
RES9:188/TXTA.02J