AGENDA TITLE: Contract Change Order - Lodi Lake Picnic Facilities
MEETING DATE: August 19. 1992
PREPARED BY: Public Works Director
RECOMMENDED ACTION: This item i s for information only. Nc action is required.
BACKGROUND INFORMATION: This information is being given to the City Council
in accordance with the contract change order policy
approved by Resolution 85-72. One of the requirements of
this policy i s that vie inform the City Council of a I I
change orders over the larger of $5,000 or 10" of the contract amount.
This attached contract change order, approved by the City Manager, was i n the amount
of $20,110 which i s 20.671 of the contract. The major items of work in this change
order are:
1) Installing lights in the Hughes Beach and South Point picnic
structures
2) Increasing the parking lot size in the Hughes Beach area
3) Installing electrical conduit for future lighting in the youth group
area
The City has a State grant of $140,000 tO help pay for the design End construction
of the picnic facilities at Lodi Lake. $20,000 wac alsc appropriated from the
General Fund to meet the original project estimate of 5160.000. Tvw conditions of
the grant were that the City use its 520,000 first and any money remaining in the
account at the completion of the project must be returned to the State.
Richard Bigler and Associates. the architect for this project. revised his construc-
tion estimate to $190,000 just prior to putting the plans and specifications out to
bid. Bid items were deleted to keep the project within budget and K Marc Lee. Inc.
was the low bidder at $97.500.
The additional work shown in the change order w i I I reduce the amount of money that
must be returned. The project officer from the State Parks and Recreation
Department has reviewed and approved the changes in the scope of work.
APPROVED,_- I!�Vl�
THOAAAS A. PETERSON
Cc' r
CLOOILAK. 2/TXTW .02M (C0. COM) August 6, 1997
Contract Change Order - Lodi Lake Picnir Facilities
August 19, 1992
Page 2
FUNDING: Originally Budgeted:
Budgeted Fund:
Contract Amount:
Prepared by Uesley K. Fujitani
JLR/4/lm
Attachment
5160.000
Per Capita Grant Program and General Fund
b117.610
Jack, L. Ronsko
Public Works Director
r
Senior Civil Engineer
cc: City Attorney
Parks and Recreation Director
Community Development Block Grant Coordinator
CLODILAK.2/TXTW.02M (CO.COM) August 6, 1992
CITY OF LODI
PUBLIC WORKS DEPARTMENT CONTRACT CHANGE OPUR NO. 1
Sheet 1 of 2
Date July 29. 1992
Account No. .3-r .1
PROJECT: Lodi Lake Picnic Facilities
CONTRACTOR: H. Max Lee. 1 nc .
You are directed to make the following changes or do the following work not included
in the Plans and Specifications on this contract.
............................................
Description of work to be done. estimate of quantities, and prices to be paid.
Specify whether additional work is at contract price, agreed price. or force
account. Unless otherwise stated, rates for rental of equipment cover only such
time as equipment is actually used and no allowance w i I I be made for idle time.
1. Do the following work for the agreed upon price of
a) Delete 1" electrical conduit as shown on the plans
and install conduit as shnwn on the revised Electric
Utility Department plan the Youth Group Area
b Install City -furnished luminaire in Youth Group Area
C Furnish 100 amp load center at sink
d) Install 1" PVC conduits for future lighting in
Youth Group Area
2. Remove exfsting flagpole in Youth Group Area
(Continued on Page 2)
Original Contract Price
Total Cost of This Change Order NOT TO EXCEED
Previous Change Orders
Total Cost of A I I Change Orders to Date
Contract Price, including a I I Change Orders, w i l l be:
S 7,080
Add
$5.010
Add
1.610
Add
115
Add
345
Price not to e_cceed 960
S 97.500
iTtT—
S
PERCENT OF
OON RAC: f
20.6
20.6
Time of completion w i I I be adjusted as follows: Add 12 working days
Submitted byAV [ Date 79Z
Approval Recommended, Date
Appro ,Publ r s irector '�'- E - `�� Date G-7 - r z
App J it' Ka j..i#--a�cer larger of or each or 525, t to CCOs
tG[ �f hotnas A. Peterson Date 9 It 92-
1Y
Z1y Manager
The undersigned contractor. having carefully considered the change proposed, agrees,
if this proposal is approved, to provide all equipment. furnish all materials. except
as otherwise noted above, perform all services necessary for the work above specified,
and accept as full payment the prices shown above.
ACCEPTED: Date Contractor
BY Ti tIe__ _
11Fthe Contractor does not s)cn acceptance of this order. the Contractor should refer
to Section 4-1.03A of the Standard Specifications regarding filing a written protest
within the specified tiEne.
CITY OF LODI
PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 1
Sheet 2 of 2
DateJu 29,T§92
Account No.
PROJECT: Lodi Lake Picnic Facilities
CONTRACTOR_ -H_ !ax Lee, - Inc - - - - - - - - - - - - - - -
- - - -
- - - - - -
- - -
3.
Install lights in South Point Area as shown on
Electric Utility drawing
",greed
upon price
5 2,445
4.
Install lights i n Hughes Beach Area as shown on
Electric Utility drawing
Agreed
upon price
2.650
5.
Grade and pave 1,204 SF for parking lot at
Hughes Beach
Agreed
upon price
3,740
6.
Water seal shingles on picnic structures at
Hughes Beach and South Point
Agreed
upon price
575
7.
Install header board around decomposed
granite path
Agreed
upon price
2,660
TOTAL 520,110
WF/ lm