HomeMy WebLinkAboutAgenda Report - August 5, 2009 E-10AGENDA ITEM e*010
&% CITY OF LODI
COUNCIL COMMUNICATION
._1M
AGENDA TITLE: Adopt Resolution Awarding Contract for Building Demolition at 17 East Elm Street
Projectto Double B Demolition, of Folsom ($39,913)
MEETING DATE: August 5, 2009
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt a resolution awarding the contract for the Building Demolition
at 17 East Elm Street Projectto Double B Demolition, of Folsom, in
the amount of $39,912.80.
BACKGROUND INFORMATION: This projectwill include the proper removal of asbestos material, the
demolition of an existing 8,000 square foot building (with a full
basement), site clean-up and grading, and the installation of
approximately 200 lineal feet of chain link fence at 17 East Elm Street.
The City -owned parcel at 17 East Elm Street includes an abandoned building which is in a state of
disrepair. The building is littered with debris, and the floor over the basement is unstable.
Community Development Block Grant Funds will be used to pay for the work involved in the asbestos
abatement, the demolition of the building, the chain link fencing, and the clean-up of this site.
Plans and specifications for this project were approved on April 15, 2009. The City received the following
eleven bids for this project on July 1, 2009.
Bidder
Location
Bid
Engineer's Estimate
$83,240.00
Double B Demolition
Folsom
$39,912.80
W.C. Maloney
Stockton
$48,717.20
Jim Thorpe Oil
Lodi
$52,896.00
Evans Brothers
Livermore
$66,565.00
Pantano Excavating
Manteca
$71,268.80
Delta Demolition
Brentwood
$72,113.40
Delta Oilfield
Woodland
$81,462.00
Diede Construction
Lodi
$84,247.29
Matthews Demolition
Fresno
$103,881.60
PARC Specialty
Sacramento
$104,890.40
Soil Enterprises
Brentwood
$127,399.40
FISCAL IMPACT: There should be a slight reduction in maintenance costs with the removal of
this building and the clean-up of this parcel.
FUNDING AVAILABLE: Community De lopment Stock Grant Funds ($46,000)
Jordan Ayers
Deputy City Ma71"
er/Internal Services Director
F. Walgandelin
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
cc: City Attorney Purchasing Officer
Fleetand Facilities Manager community Improvement Manager
APPROVED: / 2DJZ . --I
Blair King, 't anager
K:\WP\PROJECTS\MISC\Elm St Building Demo\cc_award.doc 7/20/2009
BUILDING DEMOLITION
AT 17 EAST ELM STREET
CITY OF LODI, CALIFORNIA
CONTRACT
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred
to as the "City," and DOUBLE B DEMOLITION, INC., herein referred to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by this
reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are
intended to cooperate so that any work called for in one and not mentioned in the other is to be
executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with
the City, at Contractor's cost and expense, to do all the work and furnish all the materials except
such as are mentioned in the specifications to be furnished by the City, necessary to construct
and complete in a good workmanlike and substantial manner and to the satisfaction of the City
the proposed improvements as shown and described in the Contract Documents which are
hereby made a part of the Contract.
ARTICLE If - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractorto provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts to
pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2
of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing wage
rate and other employer payments for health and welfare, pension, vacation, travel time, and
subsistence pay, apprenticeship or other training programs. The responsibility for compliance
CONTRACTLOC 1 07/20/2009
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for all
risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
Perform the work necessary to complete the abatement of asbestos material, demolition of an
8,000 square foot building (with full basement), removal and disposal of demolition debris,
backfill of basement, site grading, and other incidental and related work, all as shown on the
plans and specifications for "Building Demolition at 17 East Elm Street".
CONTRACT ITEMS
ITEM
EST'D.
NO.
DESCRIPTION
UNIT
QTY
UNIT
PRICE
TOTAL PRICE
1.
Abatement of Asbestos Material
(Roofing mastic)
LF
300 (F)
$
6.00
$ 1,800.00
2.
Site Clean -Up
LS
1
$
2,000.00
$ 2,000.00
3.
Demolition of Structure
LS
1
$
7,442.00
$ 7,442.00
4.
Basement Backfill
CY
2,400
$
3.33
$ 7,992.00
5.
Removal and Disposal of
Demolished Structure
LS
1
$
15,000.00
$15,000.00
6.
Chain -Link Fence
LF
220
$
21.04
$ 4,628.80
7.
16 -Foot Swing Gate Installation
EA
1
$
1,050.00
$ 1,050.00
TOTAL
$39,912.80
(F) Denotes Final Pay Quantity
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there
be any conflict between the terms of this instrument and the Bid Proposal of the Contractor, then
this instrument shall control and nothing herein shall be considered as an acceptance of the said
Contract.DOC 2 07/20/09
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to establish
lines and grades for the work as specified under the Special Provisions. All labor or materials
not mentioned specifically as being done by the City will be supplied by the Contractor to
accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 5
calendar days after the Contractor has been issued a building permit and to diligently prosecute
to completion within 15 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT S REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Blair King
City Manager
By: Date:
Title
(CORPORATE SEAL)
Attest:
City Clerk
Approved As To Form
D. Stephen Schwabauer
City Attorney
contract. DOC 3 07/20/09
RESOLUTION NO. 2009-104
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING CONTRACT FOR BUILDING
DEMOLITION AT 17 EAST ELM STREET
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on July 1 2009, at 11:00 a.m.
for the Building Demolition at 17 East Elm Street Project, described in the specifications
therefore approved by the City Council on April 15, 2009; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Bid
Engineer's Estimate
$83,240.00
Double B Demolition
$39,912.80
W.C. Maloney
$48,717.20
Jim Thorpe Oil
$52,896.00
Evans Brothers
$66,565.00
Pantano Excavating
$71,268.80
Delta Demolition
$72,113.40
Delta Oilfield
$81,462.00
Diede Construction
$84,247.29
Matthews Demolition
$103,881.60
PARC Specialty
$104,890.40
Soil Enterprises
$127,399.40
WHEREAS, staff recommends awarding the contract for the Building Demolition at
17 East Elm Street Projectto the low bidder, Double B Demolition, of Folsom, California.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for the Building Demolition at 17 East Elm Street Project to the low bidder,
Double B Demolition, of Folsom, California, in the amount of $39,912.80.
Dated: August 5, 2009
hereby certify that Resolution No. 2009-104 was passed and adopted by the City Council
of the City of Lodi in a regular meeting held August 5, 2009, by the following vote:
AYES: COUNCIL MEMBERS— Hitchcock, Johnson, Katzakian, Mounce, and
Mayor Hansen
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS —None
&nil
City Clerk
2009-104