HomeMy WebLinkAboutAgenda Report - July 15, 2009 E-05AGENDA ITEM 6 V S 4% CITY OF LODI COUNCIL COMMUNICATION Im AGENDA TITLE: Adopt Resolution Awarding Contractfor Grape Bowl ADA Construction Projectto ICE Builders, Inc. of Rancho Cordova ($283,039.00) and Appropriate Funds as Recommended MEETING DATE: July 15,2009 PREPARED BY: PublicWorks Director RECOMMENDED ACTION: Adopt a resolution awarding the contract for the above projectto ICE Builders, Inc., of Rancho Cordova, in the amount of $283,039.00 and appropriate funds as recommended below. BACKGROUND INFORMATION: This projectwill remove barriers to access and provide some, although limited, improved functionality of the facilities. The initial steps of the Phase I improvements are the removal of facilities that lie in the way of improved handicapped accessibility and/or are obsolete. The work consists of demolition of two restroom/concession stand buildings, miscellaneous other structures, concrete flat work, concrete footings, wood pole light standards, backfill of footings, site grading, the installation of Americans with Disabilities Act (ADA) seating and access, and other incidental and related work, all as shown on the plans and specification for the above project Plans and specifications for this projectwere approved on April 15, 2009. The City received the following three bids for this project on July 9, 2009. Bidder Location Bid Engineer's Estimate $304,350.00 ICE Builders, Inc. Rancho Cordova $283,039.00 Matt McCarty Construction Lodi $289,797.00 Diede Construction Woodbridge $319,697.40 The City has received $323,000 from San Joaquin County discretionary funds to assist in the funding for this project. Staff is recommending the appropriation of this $323,000 to cover these construction costs and other contingencies associated with this project. The next improvements at the Grape Bowl include the installation of an all-weather playing surface that will ultimately satisfy the County's funding stipulation of a 1.5 to 1 City match. Funding for the next phase consists of park impact fees, private contributions, and other City funds. APPROVED: -- Blair King,to Manager K:\WP\PROJECTS\PARKS\GrapeBowl\Phase 1 Improvements\CAward1.doc 7/10/2009 Adopt Resolution Awarding Contractfor Grape Bowl ADA Construction Project to ICD Builders, Inc. of Rancho Cordova ($283,039.00) and Appropriate Funds as Recommended July 15, 2009 Page 2 FISCAL IMPACT: This project is the first phase in the construction of ADA -related improvementsat the Grape Bowl. The completed project will result in reduced maintenance costs and the potential for additional Parks and Recreation Department revenue from increased Grape Bowl use. FUNDING AVAILABLE: County Discretionary Fund $323,000.00 Q. � Jordan Ayers Deputy City Manager/Internal Services Director James M. Rodem-s- Interim Parks and Recreation Director Prepared by Wesley Fujitani, Senior Civil Engineer FWSMKF/pmf Attachments cc: City Attorney Purchasing Officer Interim Parks and Recreation Director K:\WP\PROJECTS\PARKS\GrapeBowl\Phase 1 Improvements\CAward1.doc F. Wally S delin PublicWorks Director RESOLUTION NO. 2009-93 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT FOR GRAPE BOWL AMERICANS WITH DISABILITIES ACT CONSTRUCTION PROJECT AND APPROPRIATING FUNDS AS RECOMMENDED WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on July 9, 2009, at 11:00 a.m. for the Grape Bowl Americans with Disabilities Act (ADA) Construction Project, described in the specifications therefore approved by the City Council on April 15,2009; and WHEREAS, said bids have been checked and tabulated and a report thereof filed with the City Manager as follows: Bidder Bid Engineer's Estimate $ 304,350.00 ICE Builders, Inc. $ 283,039.00 Matt McCarty Construction $ 289,797.00 Diede Construction $ 319,697.40 WHEREAS, staff recommends awarding the contract for the Grape Bowl ADA Construction Project to ICE Builders, Inc., of Rancho Cordova, California, in the amount of $283,039.00. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the contract for the Grape Bowl ADA Construction Project to the low bidder, ICE Builders, Inc., of Rancho Cordova, California, in the amount of $283,039.00; and BE IT FURTHER RESOLVED that funds in the amount of $323,000.00 be appropriated from the County Discretionaryfund. Dated: July 15, 2009 I hereby certify that Resolution No. 2009-93 was passed and adopted by the City Council of the City of Lodi in a regular meeting held July 15, 2009, by the following vote: AYES: COUNCIL MEMBERS— Hitchcock, Johnson, Katzakian, Mounce, and Mayor Hansen NOES: COUNCIL MEMBERS— None ABSENT: COUNCIL MEMBERS— None ABSTAIN: COUNCIL MEMBERS— None &JOHL City Clerk