AGENDA TITLE: Acceptance of Improvements Under Zupo Fie d Backstop and Fencing,
350 N. Washington Street, Contract
1VlEETW DATE: June 19, 1991
PREPARED BY: Public Waits Director
RECOMMENDED AC UN. That the City Council accept the improvements under the
"Zupo Field Backstop and Fencing" contract anerect. tt e
Public Works Director to file a Notice of come e 1 on wit the
County Recorder's office.
BACKGROUND P43DFA A3M The contract was awarded to Scrimsher and Mineni
Construction of Modesto on January 2, 1991 in the amount of
$35,921.39. The contract has been c m leted in substantial
conformance with the plans and specifications approved by
the City Council.
The contract com,�letign date was July. 8, 1991 and the actual cpmpletion date was
June 10, 1991. e final contract price was $43,897.23. The difference between the
contract amount and the final contract price is mainly due to a redesign of the
backstop to reduce the size of the posts.
FUNDM Originally Budgeted: 1988/89
Budgeted Fund: Capital Outlay Reserve
Current Appropriation: $46,934.19
Total Project Estimate: $46,000.00
Bid Opening Date: 11/14/90
dk-,Ronsko
orks Director
Prepared by Wesley K. F u j i t a n i, Senior Civil Engineer
JLR/4/mt
cc: Purchasing Officer
Parks and Recreation Director
APPROVED:
THOMAS A. PETERSON
CZUP04/TXTW.02M (CO. COM) June 11, 1991