AGENDA ITEM E 15
• CITY OF LODI
%V COUNCIL COMMUNICATION
,M
AGENDA TITLE: Adopt Resolution Awarding Annual Contractfor Curb, Gutter and Sidewalk
Replacementto Jeff Case Construction, of Galt ($46,570)
MEETING DATE: June 17,2009
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt a resolution awarding the annual contract for curb, gutter and
sidewalk replacement to Jeff Case Construction, of Galt, in the
amount of $46,570.
BACKGROUND INFORMATION: The curb, gutter and sidewalk replacement is an annual contract
administered by the Streets and Drainage Division for miscellaneous
concretework, as needed during the course of the year and guided by
the Sidewalk Replacement Program. The work could include
new sidewalks as part of the City's installation program, replacementwork resulting from maintenance
projects, repair of defective concrete, and repairs of utilitywork. The contract includes a wide range of
work items and unit prices for each. In addition, the prices would be made available to property owners
who wish to have work in the public right-of-way done by the City's contractor. Bid packets were
distributed to nine local contractors. Four bids were received on June 4, 2009. The specifications were
approved by City Council on May 20, 2009, and are on file in the Public Works Department at the
Municipal Service Center.
Bidder
Location
Bid
Engineer's Estimate
$
50,000
Jeff Case Construction
Galt
$
46,570
Popuch Concrete
Lodi
$
50,010
Diede Construction
Woodbridge
$
58,928
Granite Construction
Stockton
$
63,520
FISCAL IMPACT: This contract reduces the risk of liability and improves pedestrian mobility in Lodi.
FUNDING AVAILABLE: The money for this contract will becoming from the Street Operating Budget
composed of Gas Tax, TDA funds for Streets, Bike and Ped routes in the
proposed 2009/10 budget.
MBueted F nd: Street Funds (1241014) $50,000
J -0 -Nan Ayers
Deputy City Manager/Internal Services Director)
-Laa44
F. Wally ndelin
Public Works Director
Prepared by Curt Juran, Assistant Streets and Drainage Manager
FWS/CJJ/dsg
cc: D. Stephen Schwabauer, City Attorney George M. Bradley, Streets and Drainage Manager
Curt Juran, Assistant Streets and Drainage Manager
APPROVED:
Blair King, naaer
K:\WP\COUNCIL\09\HwardSidewalkRepair.doc 6/8/2009
2009/2010 CURB, GUTTER, and SIDEWALK REPLACEMENT
ANNUAL CONTRACT CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and JEFF CASE CONSTRUCTION COMPANY, herein referred
to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated
herein by this reference, to -wit:
Notice Inviting Bids
The July 1992 Edition,
Information to Bidders
Standard Specifications,
General Provisions
State of California,
Special Provisions
Business and Transportation Agency,
Bid Proposal
Department of Transportation
Contract
All of the above documents, sometimes hereinafter referred to as the "Contract
Documents," are intended to cooperate so that any work called for in one and not
mentioned in the other is to be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City, the Contractor agrees with the City,
at Contractor's cost and expense, to do all the work and furnish all the materials except
such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the
satisfaction of the City the proposed improvements as shown and described in the
Contract Documentswhich are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and
does hereby employ, the Contractor to provide all materials and services not supplied by
the City and to do the work according to the terms and conditions for the price herein,
and hereby contracts to pay the same as set forth in Section 5.600, "Measurement,
Acceptance and Payment," of the General Provisions, in the manner and upon the
conditions above set forth; and the said parties for themselves, their heirs, executors,
administrators, successors and assigns, do hereby agree to the full performance of the
covenants herein contained.
R:IGROUP\STREETS\SIDEWALK\Annual Sidewalk Replacement Contracts& PO's\2009-2010\Contract#2009-2010.doc U 06/04/2009
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1 Part 7,
Division 2 of the Labor Code. The Contractor and any Subcontractor will pay the general
prevailing wage rate and other employer payments for health and welfare, pension,
vacation, travel time, and subsistence pay, apprenticeship or other training programs.
The responsibility for compliance with these Labor Code requirements is on the prime
contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and
embraced in this agreement; also for all loss or damage arising out of the nature of the
work aforesaid or from the action of the elements, or from any unforeseen difficulties or
obstructions which may arise or be encountered in the prosecution of the work until its
acceptance by the City, and for all risks of every description connected with the work;
also for all expenses incurred by or in consequence of the suspension or discontinuance
of work and for well and faithfully completing the work, and the whole thereof, in the
manner and according to the Contract Documents and the requirements of the Resident
Engineer under them, to -wit:
Perform the work necessary to remove and replace curb, gutter and sidewalk in various
locations throughout the City and other incidental and related work, all as shown on the
plans and specifications for the above project. This is an annual unit price bid and the
work will be divided into purchase orders which will usually range in price between $500
and $20,000, all as shown on the plans and specifications for "2009/2010 Sidewalk
Repair Program and Miscellaneous Concrete Work".
R:\GROUP\STREETS\SIDEWALK\Annual Sidewalk Replacement Contracts & PO'8\2009.2010\Contract#2009.2010.doc 4.2 06/04/2009
BID ITEMS
Item
I Description
Qtv
Unit
Price
Total
1
Saw Cut Concrete
50
LF
$ 4.95
$ 247.50
I
2
Remove Sidewalk or Asphalt Concrete
50
SF
4.50
225.00
3
Remove Commercial Sidewalk
0
SF
10.00
4
Remove Square -Type Curb and Gutter
0
LF
15.0,0
5
Remove Vertical -Type Curb and Gutter
0
LF
15.00
I
6
Remove Driveway -Type Curb and Gutter
0
LF
15.00
7
Remove Commercial -Type Curb and Gutter
0
LF
I 20.00
8
Root Surgery Under Sidewalk or in PlanterArea
0
EA
I 400.00
9
Root Surgery Under Curb and Gutter
0
EA
500.00
10
Install Sidewalk or Residential Driveway 0 - 75 SF
1500
SF
9.50
11
Install Sidewalk or Residential Driveway 76 - 300 SF
1500
SF
5.75
8,625.00
12
Install Sidewalk or Residential Driveway >300 SF
3025
SF
5.00
15.125.00
SF
10.00
2,500.00
R,\GROUP\STREETS\SIDEWALK\Annual Sidewalk Replacement Contracts& PO'S12009-201D\Contract#2009-2D10.doc 4.3 6/4/2009
Item
Description
Qty
Unit
Price
Tota I-
14
Install Square -Type Curb and Gutter 7 -inch or less 0 - 20 LD
20
LF
$ 30.00
600.00
15
Install Square -Type Curb and Gutter 7 -inch or less >20 LF
20
LF
25.00
500.00
16
Install Square -Type Curb and Gutter Greater than 7 -inch 0 - 20 LF
20
LF
30.00
600.00
17
Square -Type Curb and Gutter Greater than 7 -inch >20 LF
20
IF
25.00
500.00
18
Install Vertical -Type Curb and Gutter 0 - 20 LF
20
LF
30.00
600.00
19
Install Vertical -Type Curb and Gutter >20 LF
20
LF
25.00
500.00
20
Install Driveway -Type Curb and Gutter 0 - 20 LF
20
LF
30.00
600.00
21
Install Driveway -Type Curb and Gutter >20 LF
20
LF
25.00
500.00
22
Install Tree Well
1
EA
350.00
350.00
23
Install Furnished Side -Inlet Catch Basin Assembly
0
EA
700.00
24
Install Catch Basin Barrel
0
EA
1,200.00
25
Install Furnished Street Name Sian Base
1
LF
200.00
200.00
26
Miscellaneous Concrete Sub rade Compaction
50
LF
2.95
147.50
27
Move -In Cost for J o b s <$200
2
EA
250.00
500.00
TOTAL BID
$ 46,570.00
R:\GROUP\STREETS\SIDEWALK\Annual Sidewalk ReplacementContracts& PO's\2009-2010\Contract42009-2010.doc 4.4 6/4/2009
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there
be any conflict between the terms of this instrument and the Bid Proposal of the Contractor,
then this instrument shall control and nothing herein shall be considered as an acceptance of
the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications,
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract as directed
by the City during the 2009/2010 fiscal year.
RAGROMSTREETS\SIDEWALK\AnnualSidewalk Replacement Contracts&PO's\2009-2010\Contract#2009-2010.doe 4.5 6/4/2009
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FORTHIS CONTRACT IS REASONABLEAND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Blair King
City Manager
By: Date:
Title
(CORPORATE SEAL)
Attest:
Randi Johl
City Clerk
Approved as to form:
D. Stephen Schwabauer
City Attorney
R:1t3ROUP1STREETSISIDEWALKWnnual Sidewalk Replacement Contracts& PO's\2009-20101Gontract#2009-2010.doc 4.6 6/4/2009
13=�Y�1���[�1i•li•C���I�I'�%�
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE ANNUAL CONTRACT FOR CURB,
GUTTER, AND SIDEWALK REPLACEMENT
WHEREAS, in answer to notice duly published in accordance with law and the
order of this City Council, sealed bids were received and publicly opened on June 4,
2009, at 11:00 a.m. for annual curb, gutter, and sidewalk replacement, described in the
specifications therefore approved by the City Council on May 20, 2009; and
WHEREAS, said bids have been checked and tabulated and a report thereof
filed with the City Manager as follows:
Bidder Bid
Engineer's Estimate $ 50,000
Jeff Case Construction $ 46,570
Popuch Concrete $ 50,010
Diede Construction $ 58,928
Granite Construction $ 63,520
WHEREAS, staff recommends awarding the annual contract for curb, gutter, and
sidewalk replacementto the low bidder, Jeff Case Construction, of Galt, California.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
award the annual contract for curb, gutter, and sidewalk replacement to the low bidder,
Jeff Case Construction, of Galt, California, in the amount of $46,570.
Dated: June 17, 2009
-------------------------------------------------------------------
-------------------------------------------------------------------
hereby certify that Resolution No. 2009-79 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 17, 2009, by the following vote:
AYES: COUNCIL MEMBERS —Johnson, Mounce, and Mayor Hansen
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS —Hitchcock and Katzakian
ABSTAIN: COUNCIL MEMBERS —None
&JOHL
City Clerk
2009-79