HomeMy WebLinkAboutAgenda Report - June 5, 1991 (81)OF
CITY OF LOBI
04tf
COUNCIL COMMUNICATION
AGENDA TITLE: Plans and Specifications and Advertisement for Bids for
Well 24 Pump and Motor, 640 North Stockton Street (North of Grape
Bowl Stadium)
NEEMU DATE: June 5, 1991
PREPARED BY: Publ is Works Director
RECOMMENDED AC10N- That the City Council approve the plans and specifications for
the above project and authorize advertising for bids.
BACKGROUND INFORMATION: This project is for the purchase and installation of pumping
equipment for the new water well at 640 North Stockton
Street. The equipment will include a 150 -horsepower
electric motor and pump capable of pumping approximately
1,750 gallons per minute.
FUI\DM Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate
Bid Opening Date:
1989/90
Water Capital Outlay
$295,000
$32,000 (this phase)
June 19, 1991
i 1
ack L. Ronsko
Y4Wc Works Director
Prepared by Mark J. Lindseth, Associate Civil Engineer
JLR/ML/mt
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED:' !
THOMAS A. PETERSON141.
City Manager
cc -1
CWEL(-24-3/TXTW.02M (CO.COM) May 24, 1991