AGENDA ITEM K
CITY OF LODI
COUNCIL COMMUNICATION
TH
AGENDA TITLE: Adopt Resolution Approving DeBenedetti Park Modified Grading Design, Directing
Preparationof Plans and Specifications for Phased Improvements,Authorizing
City Managerto Execute Contract Amendment for DeBenedetti Park Rough Grading
Contract with A.M. Stephens Construction Company, Inc., of Lodi ($163,000) and
Appropriating Additional Funds ($180,000) from Impact Mitigation Fees
MEETING DATE: May 6,2009
PREPARED BY: Public Works Director and Interim Parks and Recreation Director
RECOMMENDED ACTION: Adopt a resolution approving the DeBenedetti Park modified grading
design, directing preparation of plans and specifications for phased
improvements, authorizing the City Manager to execute a contract
amendment for the DeBenedetti Park Rough Grading contract with
A.M. Stephens Construction Company, Inc., of Lodi, in the amount of $163,000 and appropriating
$180,000 from Impact Mitigation Fees for contract and staff costs.
BACKGROUND INFORMATION: The contract for the DeBenedetti Park/Basin G Rough Grading was
awarded to A.M. Stephens Construction Company, Inc., at the
December 17, 2003 Council meeting. This project consisted of the
excavation, rough grading and export of material from the
DeBenedetti Park site and also included site fencing, mowstrips, rip -rap and other drainage related work.
The original contract completion date was October 31, 2006. A.M. Stephens Construction Company
requested additional time to complete the excavation and rough grading of the park, and the contract
completion date was extended to December 31, 2008. This contract has been suspended until
May 1,2009.
The Parks and Recreation Commission, at its meeting of November 6, 2008, and again at its
March 12, 2009 meeting, approved a modified grading design of DeBenedetti Park which would trade
3.3 acres between play field and storm drainage, make the storm drain area 10 feet shallower, and
simultaneously provide for phased improvementsto DeBenedetti Park. Without modificationsto the
storm drain area, the 30 -foot storm drain basin will remain permanently. The modified grading design is
attached as Exhibit A.
At the January 7, 2009 City Council meeting, staff was requested to bring back more detailed cost
information comparing the alternative plans. As modified, the park and storm drainage construction costs
are estimated to be $14 million in contrast to the existing plan that would cost $18 million to construct.
Full funding does not currently exist for either alternative. Included in the construction cost savings is a
reduction in pump station construction costs estimated to be $300,000.
At the April 14, 2009 Shirtsleeve Session, City Council visited the park site and received a presentation
on the alternative park/drainage grading plans.
APPROVED:
Blair King, Citger
K:\WP\PROJECTS\PARKS\DeBenedetti(G-Basin)\CCDeBencontract extension.doc 4/30/2009
Adopt Resolution Approving DeBenedetti Park Modified Grading Design, Directing Preparation of Plans
and Specifications for Phased Improvements, Authorizing City Managerto Execute Contract Amendment
for DeBenedetti Park Rough Grading Contract with A.M. Stephens Construction Company, Inc., of Lodi
($163,000) and Appropriating Additional Funds ($180,000) from Impact Mitigation Fees
May 6,2009
Page 2
Staff recommends that A. M. Stephens Construction Company receive a five-month extension on the
contract to complete the modified grading plan. The contract amendment (Exhibit B) would require
A.M. Stephens Construction Company to remove approximately 57,000 cubic yards of dirt from the
3.3 acre high ground area and place it in the bottom of the existing basin, thereby decreasing the depth
of the basin by 10 feet. Included in the City's compensation to A.M. Stephens Construction Company are
added costs for weed and dust control.
Upon completion of the work, the City will be able to proceed with park and storm drainage improvements
in the park and the basin. The initial phase of improvements comprises turf and irrigation at the north
side of the park that would be installed in Fall 2009 or Spring 2010 resulting in the creation of three new
playing fields.
Approval by the City Council of the modified grading design will remove 3.3 acres from the original park
conceptual development plan. As a result of the shift in acres from park use to storm drainage basin, the
overall project development cost split will change from 53%/47% to 50%/50% (park vs. storm drainage)
and transfers between the impact fee accounts will be made to reconcile past expenses to the new cost
split.
FISCAL IMPACT: Eventual operation and maintenance cost for the park and storm drainage
facilities will be substantially reduced compared to the current conceptual
development plan.
FUNDING AVAILABLE: Requested Appropriation:
Parks and Recreation Impact Mitigation Fee Fund (1217) $90,000
Storm Drain Impact Mitigation Fee Fund (326017) $90,000
C-�� A�=W -1 44
Jordan Ayers
Deputy City Manager/Internal b"ervices Director
James M. Rodems'`
Interim Parks and Recreation Director
Prepared by F. Wally Sandelin, Public Works Director
FWS/pmf
Attachments
cc: Affected Property Owners
t
F. Wally San elin
Public Works Director
K:\WP\PROJECTS\PARKS\DeBenedetti(G-Basin)\CCDeBencontract extension.doc 4/30/2009
SIiEAFLA
• .aG. 45,, SQFT.
1 } � "tri J'.' .= • '.. j. : -
1'dlSl'QirISTuu=- — - i - - -- - ��r''i;ALT.
I LIM ACRUS
_
VA
I
- - - HARDBALL _T 1 HARDBALL
- _ Li r 1
101,
I.OW FLAW AREA y ---
562.G84SQFT.
1190 A{tFS -
DEBENEDETTI PARI.
EXIBIT "A"
CITY OF LODI
PUBLIC WORKS DEPARTMENT
PROJECT: DeBenedetti Park/Basin G Rough Grading
CONTRACTOR: A.M. Stephens Construction
CONTRACT CHANGE ORDER NO.4
Sheet 1 of 1
Date: December 23, 2008
Account No. 326017
You are directed to make the following changes or do the following work not included in the
Plans and Specifications on this contract.
----------------------------------------------------------------------
Description of work to be done, estimate of quantities, and prices to be paid. Unless otherwise
stated, rates for rental of equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
1. Regrade deep basin area to raise bottom approximately 10 feet.
Agreed Upon Price not to exceed $163,000
PERCENT OF
CONTRACT
Original Contract Price $ 266,678.00
Total Cost of This Change Order NOT TO EXCEED $ 163,000.00 61.1%
Previous Change Orders ($ 38,984.50) (14.6%)
Total Cost of All Change Orders to Date $ 124,015.50 46.5%
Contract Price, Including All Change Orders, Will Be: $ 390,693.50
Time of completion will be adjusted as follows: New completion date shall be October 1, 2009
Submitted By Date
Approval Recommended Date
Approved, Public Works Director
Date
Approved, City Manager (Per Public Works Policies and Procedures, Administration 4.1)
Date
The undersigned contractor, having carefully considered the change proposed, agrees, if this
proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted
above, perform all services necessary for the work above specified, and accept as full payment
the prices shown above.
ACCEPTED: Date
By
Contractor
Title
If the contractor does not sign acceptance of this order, the contractor should refer to Section 4-
1.03A of the Standard Specifications regarding filing a written protest within the specified time.
CC04.doc
RESOLUTION NO. 2009-57
A RESOLUTION OF THE LODI CITY COUNCIL APPROVING
DEBENEDETTI PARK MODIFIED GRADING DESIGN, DIRECTING
PREPARATION OF PLANS AND SPECIFICATIONS FOR PHASED
IMPROVEMENTS, AUTHORIZING THE CITY MANAGER TO EXECUTE
CONTRACT AMENDMENT FORTHE DEBENEDETTI PARWBASIN G
ROUGH GRADING WITH A.M. STEPHENS CONSTRUCTION, INC.,
AND FURTHER APPROPRIATING FUNDS
WHEREAS, City Council awarded the contract for the DeBenedetti Park/Basin G
Rough Grading to A.M. Stephens Construction Company, Inc., on December 17, 2003. The
project consisted of the excavation, rough grading, and export of material from the
DeBenedetti Park site and also included site fencing, mowstrips, rip -rap, and other drainage
related work; and
WHEREAS, the original contract completion date was October 31, 2006.
A.M. Stephens Construction Company requested additional time to complete the excavation
and rough grading of the park, and the contract completion date was extended to
December 31,2008. The contract has been suspended to May 1,2009; and
WHEREAS, the Parks and Recreation Commission, at its meetings of
November6,2008 and March 12, 2009, approved a modified grading design of
DeBenedetti Park, which would trade 3.3 acres between play field and storm drainage, make
the storm drain area ten feet shallower, and simultaneously provide for phased improvements
to DeBenedetti Park. Without modifications to the storm drain area, the 30 -foot storm drain
basin will remain permanently; and
WHEREAS, as modified, the park and storm drainage construction costs are estimated
to be $14 million in contrast to the existing plan that would cost $18 million to construct.
Included in the construction cost savings is a reduction in pump station construction costs
estimated to be $300,000; and
WHEREAS, staff recommends that A M. Stephens Construction Company receive a
five-month extension on the contract to complete the modified grading plan. The contract
would require AM. Stephens Construction Company to remove approximately 57,000 cubic
yards of dirt from the 3.3 acre high ground and place it in the bottom of the existing basin,
thereby decreasing the depth of the basin by 10 feet. Included in the City's compensation to
A. M. Stephens Construction Company are added costs for weed and dust control; and
WHEREAS, upon completion of the work, the City will be able to proceed with park and
storm drainage improvements in the park and the basin. The initial phase of improvements
comprises turf and irrigation at the north side of the park that would be installed in Fall 2009 or
Spring 2010 resulting in the creation of three new playing fields; and
WHEREAS, approval by the City Council of the modified grading design will remove
3.3 acres from the original park conceptual development plan. As a result of the shift in acres
from park use to storm drainage basin, the overall project development cost split will change
from 53%/47% to 50%/50% (park vs. storm drainage) and transfers between the impact fee
accounts will be made to reconcile past expense to the new cost split.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
approve the DeBenedetti Park modified grading design; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby direct the
preparation of plans and specifications for phased improvements at DeBenedetti Park; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
City Manager to execute a contract amendment with A. M. Stephens Construction Company,
Inc., of Lodi, California, for the DeBenedetti Park/Basin G Rough Grading in the amount of
$163,000 and granting a five-month contract extension for the purpose of regrading the storm
drain basin area of the park; and
BE IT FURTHER RESOLVED that funds in the amount of $180,000 be appropriated
from the Parks and Recreation Impact Mitigation Fee Fund and the Storm Drain Impact
Mitigation Fee Fund for the project.
Dated: May 6, 2009
-----------------------------------------------------------------------
-----------------------------------------------------------------------
hereby certify that Resolution No. 2009-57 was passed and adopted by the Lodi City
Council in a regular meeting held May 6, 2009, by the following votes:
AYES:
NOES:
ABSENT:
ABSTAIN:
COUNCIL MEMBERS — Hitchcock, Johnson, Katzakian, Mounce, and
Mayor Hansen
COUNCIL MEMBERS — None
COUNCIL MEMBERS — None
COUNCIL MEMBERS — None
2009-57
GENTURY BOULEVARD RE5TROOMB GONCESSIGNS l GOVERED PLAYSUNID
IP
ri
DGHBORHOOD(
ROUND ARZ
BASEBki PIGNJG_ Ac�
ioe
01AMOND-
MA
DIAMOND
DIAMOND
DLAM2LD.
WiVue
"54
Ohl
h
BD IDEBENEOETTI F/>gn�%R<
LODI, C,,A — 40.,AC;RES
N15
' WELL 51TE 8
MAINTENANCE WD
'C]C
0
Lu
Q
LLI
0
GENTS RY BOULEVARD
RE5 ROOM51 GONGE5510N51 GOVERED PLAY' ?R UNV
' DIAAMOND �
. o fW. , ied • pi a n'l ate $1
DIAMOND... L0 9D'Ea�SE5Ak.L r-
RAMOND
'SIA
w
;off
AM
f W, off" I of
L WELL 5ITE 8
MAINTENANCE WD
BD DBBEN BDBTTI PAR<
LOD I , GA - 40.,ACRES
CENTURY BOULEVARD RESTROOMS �NGESSIONS "GJVE:REI) PLA�r�UND
A
ta ust
d
F7
90'BA5 LL
f PICNIC, AREA5-
50CLER
DIAMOND
e efi ts
C,
WE -L 51
MAI AN'
-E YAZ"
4:
pri 9.
A
r
DIAMOND
iallow- assn by 10 t � r _
V "TW prytm, n �.�
- a, S C t rrucppn aitovw�X7 TW ,
Tw
J.-
e
�.,
r -:-�
6-
]p tilln.r. 20.0
ru 90
et -fit
�-0
ewer c'onst d
mrove
d cost p parks
storm
F-0 DE13ENEIDETTI F/>e�NR<
LOIDI, C;.,A — 40 .AC;PES
DEBENEDETTI PARK
EXHMIT "Alf
------------
RAMAM
WOWS FBMW
ry
t
St2,M SQ.in
11.78 A9
GROUND ARFA
_ i
15.51 ACRES
\'
k-----
_
`i
'I
LOWFLOWAREA
s3ACM
DEBENEDETTI PARK
EXHMIT "Alf
SIiEAFLA
• .aG. 45,, SQFT.
1 } � "tri J'.' .= • '.. j. : -
1'dlSl'QirISTuu=- — - i - - -- - ��r''i;ALT.
I LIM ACRUS
_
VA
I
- - - HARDBALL _T 1 HARDBALL
- _ Li r 1
101,
I.OW FLAW AREA y ---
562.G84SQFT.
1190 A{tFS -
DEBENEDETTI PARI.
EXIBIT "A"
CITY COUNCIL
LARRY D. HANSEN, Mayor
PHIL KATZAKIAN,
Mayor Pro Tempore
SUSAN HITCHCOCK
BOBJOHNSON
JOANNE L. MOUNCE
CITY OF LODI
PUBLIC WORKS DEPARTMENT
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209) 333-6706
FAX (209) 333-6710
EMAIL pwdept@lodi.gov
http:\\www.lodi.gov
John and B. Gerlack, Trustees
2449 Vintage Oaks Court
Lodi, CA 95242-9347
Chong A. Im, Trustee
2431 Vintage Oaks Court
Lodi, CA 95242-9347
May I , 2009
Tokay Development, Inc.
P.O. Box 1259
Woodbridge, CA 95258
John A. Carbone, Jr., Etal
2425 Vintage Oaks Court
Lodi, CA 95242-9347
BLAIR KING
City Manager
RANDIJOHL
City Clerk
D. STEVEN SCHWABAUER
City Attorney
F. WALLY SANDELIN
Public Works Director
SUBJECT: Adopt Resolution Approving DeBenedetti Park Modified Grading Design,
Directing Preparation of Plans and Specifications for Phased
Improvements, Authorizing City Managerto Execute Contract Amendment
for DeBenedetti Park Rough Grading Contractwith A.M. Stephens
Construction Company, Inc., of Lodi ($163,000) and Appropriating
Additional Funds ($180,000) from Impact Mitigation Fees
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, May 6, 2009. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the regular calendar for Council discussion. You are welcome to attend.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letterto City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately priorto the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Randi Johl, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call me at (209) 333-6709.
F. Wally Sandelin
-' Public Works Director
FWS/pmf
Enclosure
cc: City Clerk
NCCDEBENCONTRACTEXTENSION. DOC