HomeMy WebLinkAboutAgenda Report - December 17, 2008 E-08AGENDA ITEM OwS
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Authorizing City Managerto Execute Professional Services
Agreement with Premier Engineering and Land Surveying, Inc., of Turlock,
for Global Positioning System (GPS) Control Grid ($59,350) and
Appropriating Funds ($66,000) to be Paid from Impact Fees
MEETING DATE: December 17, 2008
PREPARED BY: Public Works Director
RECOMMENDEDACTION: Adopt a resolution authorizing the City Manager to execute a
professional services agreement in the amount of $59,350 with
Premier Engineering and Land Surveying, Inc., of Turlock, for the
planning and implementation of a horizontal control grid for the
City of Lodi and appropriating funds in the amount of $66,000 as shown below.
BACKGROUND INFORMATION: The purpose of this project is to establish a surveyed horizontal grid
of control points as the basis for future recorded maps and plats.
The grid will primarily serve the newly annexed areas of the City that
are expected to develop in the future. The slowdown in
development activity presents an ideal time to implementthis project because there are few, if any, maps
in process. The grid will be located throughout the City of Lodi and adjacent areas, with a concentration
on the outlying areas where future expansion is expected. This project will include the setting of
approximately 24 control point monuments of First Order accuracy, which is the highest level of accuracy
in surveying for measuring distances. When finished, a record of survey map will be filed with the County
Surveyor and the City.
The City of Lodi has never had a control network. As a result, it has been difficult for the City to create
and maintain the system mapping and to move forward on development of a Geographic Information
System (GIS), With the implementation of this grid, all future mapping and surveys in the City of Lodi will
be tied to the grid and, thereby, will insure mapping conformity between different projects. Most
communities in the region have a surveyed control grid.
Several survey firms were informally interviewedwith regard to experience, qualifications, approach, and
cost. The informal interview approach was selected, in part, due to staffs inexperience with this type of
specialized survey program. Premier Engineering and Land Surveying, Inc., presented the lowest cost
strategic proposal to accomplish our primary objective to install a high quality monumented control
network in the future expansion areas of the City.
FISCAL IMPACT: There will be a slight increase in cost for maintenance of permanent survey
monuments.
APPROVED:
Blair Kin ity Manager
K:1WPICOUNC IL1081GPSControlGrid.doc
12/1212008
Adopt Resolution Authorizing City Manager to Execute Professional Services Agreement with
Premier Engineering and Land Surveying, Inc., of Turlock, for Global Positioning System (GPS) Control
Grid ($59,350) and Appropriating Funds ($66,000)to be Paid from Impact Fees
December 17, 2008
Page 2
FUNDING AVAILABLE: Requested Appropriation:
Water Impact Fees (182)
$16,500
Wastewater Impact Fees (173)
$16,500
Streets Impact Fees (332)
$16,500
Storm Drain Impact Fees (326)
$16,500
Ki ans, Budget Manager
F. Wally Silindelin
Public Works Director
Prepared by Mark Chamberlain, Senior Engineering Technician— Survey
FVVSIMClpmf
Attachment
K:IWPICOUNCIL1081GPSControlGrid.doc 12/1212008
AGREEMENT FOR CONSULTING SERVICES
ARTICLE 1
PARTIES AND PURPOSE
Section 1.1 Parties
THIS AGREEMENT is entered into on by and between the
CITY OF LODI, a municipal corporation (hereinafter "CITY"), and PREMIER
ENGINEERING AND LAND SURVEYING, INC. (hereinafter "CONSULTANT").
Section 1.2 Purpose
CITY selected the CONSULANT to provide the conceptual design services
required in accordance with attached scope of services, Exhibit A.
CITY wishes to enter into an agreement with CONSULTANT for City of Lodi GPS
Control Network Land Surveying Services project (hereinafter "Project") as set forth in
the Scope of Services attached here as Exhibit A.
ARTICLE 2
SCOPE OF SERVICES
Section 2.1 Scope of Services
CONSULTANT, for the benefit and at the direction of CITY, shall perform the
scope of services as set forth in Exhibit A, attached and incorporated by this reference.
Section 2.2 Time For Commencement and Completion of Work
CONSULTANT shall commence work within ten (10) days of executing this
Agreement, and complete work under this Agreement based on a mutually agreed upon
timeline.
CONSULTANT shall submit to CITY one full-size and mylar copy of the Record
of Survey, monument descriptions, and the final GPS closure and network report.
CONSULTANT shall establish up to 24 new monuments consisting of a 2 '/2 -inch brass
disk set in a concrete pillar and monument box, as indicated in the attached project
scope of services.
CONSULTANT shall not be responsible for delays caused by the failure of CITY
staff or agents to provide required data or review documents within the appropriate time
frames. The review time by CITY and any other agencies involved in the project shall
not be counted against CONSULTANT's contract performance period. Also, any delays
due to weather, vandalism, acts of God, etc., shall not be counted. CONSULTANT shall
K:\WP\FORMS\ProfSrvAgnnt_PremierEnginee ring. doc 1
remain in contact with reviewing agencies and make all efforts to review and return all
comments.
Section 2.3 Meetings
CONSULTANT shall attend meetings as indicated in the Scope of Services,
Exhibit A.
Section 2.4 Staffing
CONSULTANT acknowledges that CITY has relied on CONSULTANT's
capabilities and on the qualifications of CONSULTANT's principals and staff as identified
in its proposal to CITY. The scope of services shall be performed by CONSULTANT,
unless agreed to otherwise by CITY in writing. CITY shall be notified by CONSULTANT
of any change of Project Manager and CITY is granted the right of approval of all
original, additional and replacement personnel in CITY's sole discretion and shall be
notified by CONSULTANT of any changes of CONSULTANT's project staff prior to any
change.
CONSULTANT represents that it is prepared to and can perform all services
within the scope of services specified in Exhibit A. CONSULTANT represents that it has,
or will have at the time this Agreement is executed, all licenses, permits, qualifications,
insurance and approvals of whatsoever nature are legally required for CONSULTANT to
practice its profession, and that CONSULTANT shall, at its own cost and expense, keep
in effect during the life of this Agreement all such licenses, permits, qualifications,
insurance and approvals.
Section 2.5 Subcontracts
CITY acknowledges that CONSULTANT may subcontract certain portions of the
scope of services to subconsultants as specified and identified in Exhibit A. Should any
subconsultants be replaced or added after CITY's approval, CITY shall be notified within
ten (10) days and said subconsultants shall be subject to CITY's approval prior to
initiating any work on the Project. CONSULTANT shall remain fully responsible for the
complete and full performance of said services and shall pay all such subconsultants.
K:\WP\FORMS\ProfSrvAgmt_PremierEngineering.doc 2
ARTICLE 3
COMPENSATION
Section 3.1 Compensation
CONSULTANT's compensation for all work under this Agreement shall not
exceed the amount of Fee Proposal, attached as a portion of Exhibit A.
CONSULTANT shall not undertake any work beyond the scope of this
Agreement unless such additional work is approved in advance and in writing by CITY.
Section 3.2 Method of Payment
CONSULTANT shall submit invoices for completed work on a monthly basis,
providing, without limitation, details as to amount of hours, individual performing said
work, hourly rate, and indicating to what aspect of the scope of services said work is
attributable.
Section 3.3 Costs
The fees shown on Exhibit A include all reimbursable costs required for the
performance of the individual work tasks by CONSULTANT and/or subconsultant and
references to reimbursable costs located on any fee schedules shall not apply. Payment
of additional reimbursable costs considered to be over and above those inherent in the
original Scope of Services shall be approved by CITY.
CONSULTANT charge rates are attached and incorporated with Exhibit A. The
charge rates for CONSULTANT shall remain in effect and unchanged for the duration of
the Project unless approved by CITY.
Section 3.4 Auditing
CITY reserves the right to periodically audit all charges made by CONSULTANT
to CITY for services under this Agreement. Upon request, CONSULTANT agrees to
furnish CITY, or a designated representative, with necessary information and assistance.
CONSULTANT agrees that CITY or its delegate will have the right to review,
obtain and copy all records pertaining to performance of this Agreement.
CONSULTANT agrees to provide CITY or its delegate with any relevant information
requested and shall permit CITY or its delegate access to its premises, upon reasonable
notice, during normal business hours for the purpose of interviewing employees and
inspecting and copying such books, records, accounts, and other material that may be
relevant to a matter under investigation for the purpose of determining compliance with
this requirement. CONSULTANT further agrees to maintain such records for a period of
three (3) years after final payment under this Agreement.
K:\WP\FORMS\ProfSrvAgmt_PremierEngineering.doc 3
ARTICLE 4
5 EI EMS PROVISIONS
Section 4.1 Nondiscrimination
In performing services under this Agreement, CONSULTANT shall not
discriminate in the employment of its employees or in the engagement of any
subconsultants on the basis of race, color, religion, sex, sexual orientation, marital
status, national origin, ancestry, age, or any other criteria prohibited by law.
Section 4.2 Responsibility for Damage
CONSULTANT shall indemnify and save harmless the City of Lodi, the City
Council, elected and appointed Boards, Commissions, all officers and employees or
agent from any suits, claims or actions brought by any person or persons for or on
account of any injuries or damages sustained or arising from the services performed in
this Agreement but only to the extent caused by the negligent acts, errors or omissions
of the consultant and except those injuries or damages arising out of the active
negligence of the City of Lodi or its agents, officers or agents.
Section 4.3 No Personal Liability
Neither the City Council, the City Engineer, nor any other officer or authorized
assistant or agent or employee shall be personally responsible for any liability arising
under this Agreement.
Section 4.4 Responsibility of CITY
CITY shall not be held responsible for the care or protection of any material or
parts of the work prior to final acceptance, except as expressly provided herein.
Section 4.5 Insurance Requirements for CONSULTANT
CONSULTANT shall take out and maintain during the life of this Agreement,
insurance coverage as listed below. These insurance policies shall protect
CONSULTANT and any subcontractor performing work covered by this Agreement from
claims for damages for personal injury, including accidental death, as well as from
claims for property damages, which may arise from CONSULTANT'S operations under
this Agreement, whether such operations be by CONSULTANT or by any subcontractor
or by anyone directly or indirectly employed by either of them, and the amount of such
insurance shall be as follows:
K:\WP\FORMS\ProfSrvAgmt—PremierEngineering.doc 4
1. COMPREHENSIVE GENERAL LIABILITY
$1,000,000 Bodily Injury -
Ea. Occurrence/Aggregate
$1,000,000 Property Damage -
Ea. Occurrence/Aggregate
or
$1,000,000 Combined Single Limits
2. COMPREHENSIVE AUTOMOBILE LIABILITY
$1,000,000 Bodily Injury - Ea. Person
$1,000,000 Bodily Injury - Ea. Occurrence
$1,000,000 Property Damage - Ea. Occurrence
or
$1,000,000 Combined Single Limits
NOTE: CONSULTANT agrees and stipulates that any insurance coverage
provided to CITY shall provide for a claims period following termination of coverage.
A copy of the certificate of insurance with the following endorsements shall be
furnished to CITY:
(a) Additional Named Insured Endorsement
Such insurance as is afforded by this policy shall also apply to the City of Lodi, its
elected and appointed Boards, Commissions, Officers, Agents, Employees and
Volunteers as additional named insureds insofar as work performed by the insured
underwritten Agreement with CITY. (This endorsement shall be on a form furnished
to CITY and shall be included with CONSULTANT'S policies.)
(b) Primary Insurance Endorsement
Such insurance as is afforded by the endorsement for the Additional Insureds shall
apply as primary insurance. Any other insurance maintained by the City of Lodi or
its officers and employees shall be excess only and not contributing with the
insurance afforded by this endorsement.
K:\WP\FORMS\ProfSrvAgmt—PremierEngineering.doc 5
(c) Severability of Interest Clause
The term "insured" is used severally and not collectively, but the inclusion herein of
more than one insured shall not operate to increase the limit of the company's
liability.
(d) Notice of Cancellation or Change in Coverage Endorsement
This policy may not be canceled by the company without 30 days' prior written
notice of such cancellation to the City Attorney, City of Lodi, P.O. Box 3006, Lodi,
CA, 95241.
(e) CONSULTANT agrees and stipulates that any insurance coverage provided to
CITY shall provide for a claims period following termination of coverage which is at
least consistent with the claims period or statutes of limitations found in the
California Tort Claims Act (California Government Code Section 810 et seq.).
"Claims made" coverage requiring the insureds to give notice of any potential
liability during a time period shorter than that found in the Tort Claims Act shall be
unacceptable.
Section 4.6 Worker's Compensation Insurance
CONSULTANT shall take out and maintain during the life of this Agreement,
Worker's Compensation Insurance for all of CONSULTANT'S employees employed at
the site of the project and, if any work is sublet, CONSULTANT shall require the
subcontractor similarly to provide Worker's Compensation Insurance for all of the latter's
employees unless such employees are covered by the protection afforded by the
CONSULTANT. In case any class of employees engaged in hazardous work under this
Agreement at the site of the project is not protected under the Worker's Compensation
Statute, CONSULTANT shall provide and shall cause each subcontractor to provide
insurance for the protection of said employees. This policy may not be canceled nor the
coverage reduced by the company without 30 days' prior written notice of such
cancellation or reduction in coverage to the City Attorney, City of Lodi, P.O. Box 3006,
Lodi, CA, 95241.
Section 4.7 Attorney's Fees
In the event any dispute between the parties arises under or regarding this
Agreement, the prevailing party in any litigation of the dispute shall be entitled to
reasonable attorney's fees from the party who does not prevail as determined by the
court.
K:\WP\FORMS\ProfSrvAgmt_PremierEngineering.doc 6
Section 4.8 Successors and Assigns
CITY and CONSULTANT each bind themselves, their partners, successors,
assigns, and legal representatives to this Agreement without the written consent of the
others. CONSULTANT shall not assign or transfer any interest in this Agreement
without the prior written consent of CITY. Consent to any such transfer shall be at the
sole discretion of CITY.
Section 4.9 Notices
Any notice required to be given by the terms of this Agreement shall be deemed
to have been given when the same is personally served or sent by certified mail or
express or overnight delivery, postage prepaid, addressed to the respective parties as
follows:
To CITY: City of Lodi
F. Wally Sandelin, Public Works Director
221 West Pine Street
P.O. Box 3006
Lodi, CA 95241-1910
To CONSULTANT: Premier Engineering & Surveying, Inc.
Kent Hysell, P.L.S., President
136 S. Center Street
Turlock, CA 95380
Section 4.10 Cooperation of CITY
CITY shall cooperate fully in a timely manner in providing relevant information
that it has at its disposal.
Section 4.11 CONSULTANT is Not an Emplovee of CITY
It is understood that CONSULTANT is not acting hereunder in any manner as an
employee of CITY, but solely under this Agreement as an independent contractor.
Section 4.12 Termination
CITY may terminate this Agreement by giving CONSULTANT at least ten (10)
days written notice. Where phases are anticipated within the Scope of Services, at
which an intermediate decision is required concerning whether to proceed further, CITY
may terminate at the conclusion of any such phase. Upon termination, CONSULTANT
shall be entitled to payment as set forth in the attached Exhibit A to the extent that the
work has been performed. Upon termination, CONSULTANT shall immediately suspend
all work on the Project and deliver any documents or work in progress to CITY.
However, CITY shall assume no liability for costs, expenses or lost profits resulting from
KAWP\FORMS\ProfSrvAgmt PremierEngineering.doc 7
services not completed or for contracts entered into by CONSULTANT with third parties
in reliance upon this Agreement.
Section 4.13 Severability
The invalidity in whole or in part of any provision of this Agreement shall not void
or affect the validity of any other provision of this Agreement.
Section 4.14 Captions
The captions of the sections and subsections of this Agreement are for
convenience only and shall not be deemed to be relevant in resolving any question or
interpretation or intent.
Section 4.15 Integration and Modification
This Agreement represents the entire integrated Agreement between
CONSULTANT and CITY; supersedes all prior negotiations, representations, or
Agreements, whether written or oral, between the parties; and may be amended only be
written instrument signed by CONSULTANT and CITY.
Section 4.16 Applicable Law and Venue
This Agreement shall be governed by the laws of the State of California. Venue
for any court proceeding brought under this Agreement will be with the San Joaquin
County Superior Court.
Section 4.17 Contract Terms Prevail
All exhibits and this Agreement are intended to be construed as a single
document. Should any inconsistency occur between the specific terms of this
Agreement and the attached exhibits, the terms of this Agreement shall prevail.
Section 4.18 Authority
The undersigned hereby represent and warrant that they are authorized by the
parties to execute this Agreement.
Section 4.19 Ownership of Documents
All documents, photographs, reports, analyses, audits, computer tapes or cards,
or other material documents or data, and working papers, whether or not in final form,
which have been obtained or prepared for this project, shall be deemed the property of
CITY. Upon CITY's request, CONSULTANT shall allow CITY to inspect all such
documents during regular business hours. Upon termination or completion, all
information collected, work product and documents shall be delivered by CONSULTANT
to CITY within ten (10) days.
K:\WP\FORMS\ProfSrvAgmt—PremierEngineering.doc 8
CITY agrees to indemnify, defend and hold CONSULTANT harmless from any
liability resulting from CITY's use of such documents for any purpose other than the
purpose for which they were prepared.
IN WITNESS WHEREOF, CITY and CONSULTANT have executed this
Agreement as of the date first above written.
CITY OF LODI, a municipal corporation
ATTEST:
By By
RANDI JOHL BLAIR KING
CITY CLERK CITY MANAGER
APPROVED AS TO FORM:
Dated:
M
By:
D. STEPHEN SCHWABAUER
CITY ATTORNEY Its:
k7a)
K:\WP\FORMS\ProfSrvAgmt_PremierEngineering,doc 9
November 4,2008
City of Lodi
221 West Pine Street
Lodi, CA 95240
Attention: Mr. Wally Sandelin, P.E.
Reference: City GPS Control Network
Land Surveying Services (P08-268)
Dear Mr. Sandelin:
Exhibit A
NOV 5 2008
CITY OF LODI
PUBLIC WORKS DEPARTMENT
At your request, we are pleased to present this proposal to provide professional land surveying
services to establish a GPS control network based on the California Coordinate System. Premier
Engineering & Surveying, Inc. has been built on the foundation of over 40 years combined
experience in the surveying and civil engineering industry. Premier is centrally located in
downtown Turlock and currently has projects spanning from Sacramento to Bakersfield. The
following outlines our understanding of the scope of work and our related professional fees:
1.0 INTRODUCTION
This proposal is for a project that involves land surveying services necessary to provide
GPS control surveying services in Lodi, CA. Field surveys will be conducted utilizing
existing First Order control monuments to establish the positions of approximately 24
monuments of which 17 existing monuments will be utilized and 7 new monuments will
be installed. The new proposed monuments will either replace existing monuments that
are of the nature not to hold the positions as surveyed or be placed at areas where there
are no existing monuments to utilize. Most of the existing monuments utilized are at the
centerline of the intersections or at section corners spaced at approximately 1 mile
intervals. The new monuments will consist of a 21/Z" brass disk set in a concrete pillar in
a cast iron monument box.
Kent Hysell, P.L.S., President of our fimhas performed similar work establishing First
Order control monuments for the Ninth Street Project in Modesto, CA, monument
replacement for Caltrans along 1-5, and also a 20,000 acre Santa Lucia Preserve control
project in Monterey County. With over 25 years of surveying experience, Mr. Hysell
would be an asset providing surveying services to this project.
'136 S. Center Street m Turlock, CA 95380 iv (209) 916-6901 fah u (209) 216-6904 Fax
November 4,2008
Attn: Mr. Wally Sandelin, P.E.
Page 2 of 4
Reference: City of Lodi GPS Control Network
ILand Surveying Services
2.0 SCOPE OF SERVICES
2.1 Research
❑ Premier will research existing First Order or better control monuments with
reference to the North American Datum of 1983 (NAD 83) and North
American Vertical Datum of 1988 (NAVD 88) to utilize as primary
monuments and the basis of the survey.
❑ Premier will research existing monumentation that will encompass the City
limits and areas of proposed growth to determine the monuments to be utilized
as the City control network. Network will include approximately 24
monuments. (See attached map with proposed locations.)
❑ Premier will research locations of existing monuments so as not to have
canopies of trees or other interferences that would create conflicts with GPS
i utilization.
❑ Premier will meet with the City to approve the proposed monuments and
locations to be used in the survey and reference numbering system.
2.2 GPS Control Survey
❑ Prepare a preliminary control network map for the control survey.
❑ Based on the monuments to be used for the establishment of the control
network, perform a pre -plan survey to establish the times and locations for the
occupation of the monuments.
❑ Establish traffic safety plan for the field survey.
❑ Perform a field survey utilizing four Trimble 5800 L1/L2 GPS receivers to
collect data for the network vectors. Receivers will be calibrated prior to the
survey. Multiple occupations, lengths of occupation, and redundancy
necessary to achieve the First Order accuracy standards will be performed.
❑ Field data will be processed and vectors adjusted utilizing the Trimble
Geomatics Office Ver. 1.63.
❑ A final closure report will be prepared with closures and process summary.
0
J
'
November 4,2008
Attn: Mr. Wally Sandelm, P.E.
Page 3 of 4
Reference: City of Lodi GPS Control Network
'
Land Surveying Services
' 2.3 Record of Survey
o A record of survey map will be prepared including the monuments used and
set for the control survey. A survey summary will be included on the record
of survey with the constraints used within the final adjustments.
' o Monument descriptions with the names, latitudes, longitudes, ellipsoid
heights, convergence angles, scale factors, and coordinates will be listed and
included on the Record of Survey map.
❑ A final GPS closure and network report to include all of the vectors and
constraints used will be prepared and submitted as part of the survey and
' record with the County Surveyor and also the City.
3.0 SCHEDULE
' Premier currently employs three (3) survey crews and three (3) support staff to assist with
field and office survey services. The staff at Premier is readily available for this project
' and will begin within one week of receiving the notice to proceed.
The monumentation, field survey, and network computations will be complete within 90
' days after the kick-off and coordination meeting with the City pending weather
conditions.
' The submittal of the record of survey map to the County will occur within 90 days from
the kick-off and coordination meeting with the City. Processing and recordation will be
based on the map checking turn -around from the County.
' 4.0 FEES
' Our lump sum fee for the completion of the services described above is $59,350.00.
Attached is our current hourly Fee Schedule.
' 5.0 GENERAL LIMITATIONS AND CONDITIONS
In addition to any limitations and conditions noted in the other parts of this proposal, the
I following limitations and conditions apply to this work:
5.1 The offer to provide services at the rates indicated in this proposal expires if this
proposal is not accepted by the Client within ninety (90) days after the date
indicated near the top of the first page of this letter.
' November 4, 2008
Attn: Mr. Wally Sandelm, P.E.
' Page 4 of 4
Reference:
' 5.2
City of Lodi GPS Control Network
Land Surveying Services
Examples of items that are specifically excluded from this proposal include, but
are not limited to:
o Geotechnical consulting and materials testing
o Design
o Topographic survey
o Additional monuments outside the 24 included within the survey proposal
Premier shall not be responsible for any costs associated with the above noted
exclusions.
If the Client requests that Premier provide these services, Premier will provide an
' agreement. If directed in writing by the Client to provide these services with less
than five business days notice before the work must be started, Premier will
perform the work on a time and materials basis.
1 5.3 The fee for the survey is based on the following assumptions:
o The Client must allow Premier to schedule the work such that the fieldwork is
completed in reasonable weather for surveying.
We trust that this proposal is in order. However, please do not hesitate to contact us should you
' have any questions or if you need any additional information. We look forward to working with
you on this project.
' Sincerely,
PREMIER ENGINEERING & SURVEYING, INC.
' Kent Hysell, P.L.S.
President
® khyse1l(a6)remier-eng.net
Enclosures
CITYOFLODI
PROPOSED
GPS CONTROL
NETWORK
LEGEND
• PROPOSED MONUMENT LOCATION
r0, PREMIER
136 S. CENTER STREET. TURLOCK. CA 95380
(209)276-6901 PHONE (209)216-6904 FAX
C
kl"
u
2008 FEE SCHEDULE
Compensation of Premier Engineering & Surveying, Inc. for work performed on time and materials basis will be
computed as follows:
CIVIL ENGINEERING SERVICES and MAPPING $ Hourly Rat
President, Vice President.............................................................................................................................
150.00
Sr. Project Manager........................................................................................................
140.00
Project Manager, Sr. Project Surveyor...................................................................................
130.00
ProjectSurveyor............................................................................................................
120.00
Sr. Project Engineer, Sr. Project Designer..............................................................................
110.00
Project Engineer, Project Designer.............................................................................................
95.00
Engineering Associate, Survey Associate..............................................................................
90.00
Design Technician, Sr. CADD Technician.............................................................................
80.00
CADD Technician, Survey Technician.................................................................................
65.00
Jr. CADD Technician......................................................................................................
55.00
PLANNING SERVICES
SeniorPlanner...............................................................................................................
130.00
Planner........................................................................................................................
110.00
AssistantPlanner............................................................................................................
85.00
PlanningTechnician........................................................................................................
55.00
FIELD SURVEY
FieldSupervisor............................................................................................................ 125.00
FieldCoordinator............................................................................................................ 100.00
SurveyTechnician................................................................................................................. 85.00
ThreePerson Crew......................................................................................................... .230.00
TwoPerson Crew........................................................................................................... 175.00
OnePerson Crew............................................................................................................ 100.00
ADMINISTRATION
OfficeManager....................................................................................................................... 80.00
SeniorAdministration........................................................................................................ 60.00
ClericalAssistant........................................................................................................... . 40.00
MISCELLANEOUS FEES
The following services are billed at our cost plus 15%:
• Subcontracted services.
• Map and Plan check fees or filing fees advanced by us.
• Transportation, meals and lodging for overnight travel and incidental travel expenses.
• Commercial delivery services, including Federal Express, Express Mail and Messenger Services.
• Excessive long distance telephone calls, telegrams, and other costs directly applicable to the project.
• Blueprint services and printing.
MILEAGE.................................................................................................................. .58.50/mile
136 S. CENTER STREET ■ TURLOCK ■ CA ■ 95380
(209) 216-6901 PH ■ (209) 216-6904 FAX
RESOLUTION NO. 2008-243
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING CITY MANAGER TO EXECUTE
PROFESSIONAL SERVICES AGREEMENT FOR
GLOBAL POSITIONING SYSTEM CONTROL GRID
WHEREAS, the purpose of this project is to establish a new Survey Control Network as
a basis of the proposed Geographic Information System (GIS) and for future recorded maps and
plats; and
WHEREAS, the new network will have valid, current geodetic values for horizontal
position, and it is expected that the validity of these values will be maintained through efficient
Global Positioning System (GPS) surveying methods; and
WHEREAS, this project is located throughout the City of Lodi and adjacent areas, with a
concentration on the outlying areas where future expansion is expected. This project will
include the setting of approximately 24 monuments of First Order accuracy. When finished, a
record of survey map will be filed with the County Surveyor and the City; and
WHEREAS, several survey firms were informally interviewed with regard to experience,
qualifications, approach, and cost. Premier Engineering and Land Surveying, Inc., of Turlock,
California, presented the lowest cost strategic proposal to accomplish the City's primary
objective to install a high-quality monumented control network in the future expansion areas of
the City.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute a Professional Services Agreement for GPS control grid
with Premier Engineering and Land Surveying, Inc., of Turlock, California, in the amount of
$59,350; and
BE IT FURTHER RESOLVED that funds in the amount of $66,000 be appropriated from
the Water Impact Fees, Wastewater Impact Fees, Streets Impact Fees, and Storm Drain Impact
Fees for this project.
Dated: December 17,2008
---------------------------- ----
I hereby certify that Resolution No. 2008-243 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held December 17, 2008, by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Johnson, Katzakian, Mounce, and
Mayor Hansen
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS— None
k&DIHL
City Clerk
2008-243