HomeMy WebLinkAboutAgenda Report - August 6, 2008 E-0545 AGENDA ITEM &
CITY OF LODI
COUNCIL COMMUNICATION
rr
AGENDA TITLE: Adopt Resolution Awarding Contracts for Heating, Ventilation, and Air
Conditioning (HVAC) Equipmentfor Lodi Public Library to Intech Mechanical,
Inc., of Roseville ($181,154) and to Joseph H. Schauf Company, of Campbell
($71,157)
MEETING DATE: August 6,2008
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt a resolution awarding the contracts for the Heating,
Ventilation, and Air Conditioning (HVAC) Equipmentfor Lodi Public
Libraryto Intech Mechanical, Inc., of Roseville, in the amount of
$181,154 and to Joseph H. Schauf Company, of Campbell, in the
amount of $71,157.
BACKGROUND INFORMATION: This project consists of providing the new 120 -ton chiller, cooling
tower, tower filter, boiler, and plate and frame heat exchanger that
will be needed to replacethe Library's aged HVAC system.
This equipmentwas bid separatelyfrom the installation contract in order to meet the City's schedule for
fall installation, to accommodatethe eight to ten week lead time necessary to procure the equipment, and
to save an estimated 15-20% mark-up that would be added to the purchase price if the equipment was
provided by the installation contractor. The bids were structured so as to give the City flexibility to award
contracts based on price and delivery by separate equipment components.
The total HVAC project cost is estimated to be $650,000. This amount includes design engineering,
construction management fees, equipment purchases, installation of the energy management controls
system, contingencies and hazardous materials testing. A separate installation contract will follow the
purchase of the equipment.
Specifications for this projectwere approved on June 18, 2008. The City received the following three
bids for this project on July 23, 2008. A copy of the bid tabulation is attached.
Bidder
Engineer's Estimate
Location
Bid
$177,630
Intech Mechanical (items 1, 2, & 7) Roseville $181,154
Schauf Company (items 3 & alt, 4, 5, & 6) Campbell $ 71,157
Champion (items 1 thru 7) Modesto $264,705
FISCAL IMPACT: Replacing the HVAC system will save operational costs currently
associated with the outdated, failing HVAC equipment. Having the
APPROVED
KIWPIPROJECTSIMISCILISRARYVHVACtiEquipment\CAward doc
��
Blair Kinnager
712512008
Adopt Resolution Awarding Contracts for Heating, Ventilation, and Air Conditioning (HVAC) Equipment for
Lodi Public Libraryto Intech Mechanical, Inc., of Roseville ($181,154) and to Joseph H. Schauf Company,
of Campbell ($71,157)
August 6,2008
Page 2
equipment as "Owner Supplied" in the HVAC Installation contract will save
the City of Lodi the typical contractor mark-up.
FUNDING AVAILABLE: The money for this project will be coming from the Library HVAC Capital
Account (211813) and the Public Benefits Fund (164605). applying the
same formula of $.15 per Kwh saved as calculated for major commercial
accounts that receive Public Benefits funds, with a $20,000 maximum.
Budget Manager
4&a J2.#A14V,(1_
F. Wally Satidelin
Public Works Director
Prepared by DennisJ. Callahan, Fleet and Facilities Manager
FWSIDJCIpmf
Attachment
cc: D. Stephen Schwabauer, City Attorney
Purchasing Officer
Nancy Martinez. LibraryServic;es Manager
George Morrow, Electric Utility Directory
Rob Lechner, Customer Services and Programs Manager
Wes Fujitani, Senior Civil Engineer
Intech Mechanical
Schauf Company
Fred Rolfes, Rolfes Engineering. Inc.
CITY OF LODI
Public Works Department
Tabulation of bids received July 23, 2008
PROJECT: LODI PUBLIC LIBRARY HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) EQUIPMENT
Engineer's Estimate
Intech Mech
Champion
Schauf Co.
Roseville
Modesto
Campbell
Item
Description
Qty
Unit
Price
Price
Price
Price
1
Furnish and Deliver Chiller
1
LS
$120,000.00
$148,566.00
($139,455.00)
No Bid
Delivery Time
12 Weeks
12-14 Weeks
2
Assemble Chiller
1
LS
$3,000.00
N/A
Included
No Bid
3
Cooling Tower
1
LS
$14,000.00
N/A
($18,200.00)
$22,358.00
Add Cold Water Basin
1
LS
N/A
$13,247.00
$11,724.00
Delivery Time
7 weeks
6-8 Weeks
4
Liquid -Solids Separation System
1
LS
$3,500.00
N/A
($5,200.00)
$7,752.00
Delivery Time
7 weeks
6-8 Weeks
5
Non -Chemical Cooling Tower Water Treatment
1
LS
$10,000.00
N/A
($15,100.00)
$18,875.00
Delivery Time
7 weeks
6-8 Weeks
6
Plate and Frame Heat Exchanger
1
LS
$7,500.00
N/A
(9,300.00)
12,359.00
Delivery Time
7 weeks
6-8 Weeks
7
Boiler
1
LS
$19,630.00
$32,588.00
($26,753.00)
No Bid
Delivery Time
8-9 Weeks
9-10 Weeks
Package Price All Quoted Items
$ 177,630.00
181,154.00
$ 264,705.00
$ 71,157.00
Package Price All Quoted Items- No Cold Water Basin
$ 251,458.00
$ 59,433.00
Items 1, 2 and Item 7
$181,154.00
$ 186,205.00
Items 3 (with cold water basin), 4, 5, and 6
$ 98,497.00
$ 71,157.00
LODI PUBLIC LIBRARY HEATING, VENTILATION
AND AIR CONDITIONING (HVAC) EQUIPMENT CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and JOSEPH H. SCHAUF COMPANY, herein referred to as the
"Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 2002 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
CONTRACT-SCHAUFDOC 1 07/24/2008
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of furnishing, delivering and assembling a new 120 -ton chiller, cooling tower,
liquid -solids separation system, boiler, plate and frame heat exchanger to the Lodi Public
Library, and other incidental and related work, all as shown on the specifications for the above
project. NOTE: Removal of existing equipment and installation of new equipment is NOT
included but will be included as part of a separate contract.
CONTRACT ITEMS
ITEM
EST'D.
NO. DESCRIPTION
UNIT QTY
UNIT PRICE
TOTAL PRICE
3. Cooling Tower
LS 1
$ 22,358.00
$22,358.00
Stainless Steel Cold Water
Basin
LS 1
$ 11,724.00
$11,724.00
DeliveryTime:
6-8 Weeks
4. Liquid -Solids
Separation System
LS 1
$ 7,752.00
$ 7,752.00
DeliveryTime: 6-8 Weeks
5. Non -Chemical Cooling
Tower Water Treatment LS 1 $ 18,875.00 $18,875.00
DeliveryTime: 6-8 Weeks
6. Plate and Frame Heat
Exchanger LS 1 $ 12,359.00 $12,359.00
DeliveryTime: 6-8 Weeks
TOTAL $71,157.00"
*Purchase all four items under a single purchase contract for the reduced price of $71,157.
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
Contract_Schauf.DOC 2 07/24/08
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - THE CONTRACTOR AGREES TO COMMENCE WORK ON THE DATE
STIPULATED IN THE NOTICE TO PROCEED, AFTER BOTH PARTIES HAVE SIGNED THE
CONTRACT, AND TO COMPLETE THE WORK WITHIN 60 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Title
(CORPORATE SEAL)
By:
Blair King
City Manager
Date:
Attest:
City Clerk
Approved As To Form
D. Stephen Schwabauer
City Attorney
Contract_Schauf.DOC 3 07124108
LODI PUBLIC LIBRARY HEATING, VENTILATION
AND AIR CONDITIONING (HVAC) EQUIPMENT CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California. herein
referred to as the "City," and INTECH MECHANICAL, INC., herein referred to as the
"contractor:'
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 2002 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
CONTRACT-INTECH.DOC I 07/24/2008
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor,
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of furnishing, delivering and assembling a new 120 -ton chiller, cooling tower,
liquid -solids separation system, boiler, plate and frame heat exchanger to the Lodi Public
Library, and other incidental and related work, all as shown on the specifications for the above
project. NOTE: Removal of existing equipment and installation of new equipment is NOT
included but will be included as part of a separate contract.
CONTRACT ITEMS
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
1. Furnish and Deliver Chiller LS 1 $148,566.00 $ 148,566.00
DeliveryTime: 12 Weeks
2. Assemble Chiller LS 1 $ 0.00 $ 0.00
7. Boiler LS 1 $ 32,588.00 $ 32,588.00
Delivery Time: 8-9 Weeks
TOTAL $ 181,154.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
Contract_Intech.DOC 2 07/24/08
ARTICLE VIII - THE CONTRACTOR AGREES TO COMMENCE WORK ON THE DATE
STIPULATED IN THE NOTICE TO PROCEED, AFTER BOTH PARTIES HAVE SIGNED THE
CONTRACT, AND TO COMPLETE THE WORK WITHIN 60 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Title
(CORPORATE SEAL)
By:
Blair King
City Manager
Attest:
City Clerk
Approved As To Form
D. Stephen Schwabauer
City Attorney
Contract—In tech. DOC 3 07124108
RESOLUTION NO. 2008-146
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING CONTRACTS FOR HEATING,
VENTILATION, AND AIR CONDITIONING
EQUIPMENT FOR LODI PUBLIC LIBRARY
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on July 23, 2008, at 11:00 a.m.
for the heating, ventilation, and air conditioning (HVAC) equipment for the Lodi Public Library,
described in the specifications therefore approved by the City Council on June 18, 2008; and
WHEREAS, said bid has been checked and tabulated and a report thereof filed with the
City Manager as follows:
Bidder Location Bid
Intech Mechanical (items 1, 2, & 7) Roseville $181,154
Schauf Company (items 3 & alt, 4, 5, & 6) Campbell $ 71,157
Champion (items 1 thru 7) Modesto $264,705
WHEREAS, the bids were structured so as to give the City flexibility to award contracts
based on price and delivery by separate equipment components; and
WHEREAS, staff recommends awarding the contract for the HVAC equipment for the
Lodi Public Library to the low bidders, Intech Mechanical, Inc., of Roseville, California, for Bid
Item Nos. I, 2, and 7 and to Joseph H. Schauf Company, of Campbell, California, for Bid Item
Nos. 3 and alternative, 4, 5, and 6.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for the HVAC equipment for the Lodi Public Library to the low bidders, Intech
Mechanical, Inc., of Roseville, California, for Bid Item Nos. 1, 2, and 7 in the amount of
$181,154 and to Joseph H. Schauf Company, of Campbell, California, for Bid Item Nos. 3 and
alternative, 4, 5, and 6 in the amount of $71,157.
Dated: August 6, 2008
hereby certify that Resolution No. 2008-146 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held August 6, 2008, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Hitchcock, Johnson, Katzakian, and
Mayor Mounce
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS— None
4ANDI JOHL
City Clerk
2008-146
CITY COUNCIL
JOANNE L. MOUNCE, Mayor
LARRY D. HANSEN,
Mayor Pro Tempore
SUSAN HITCHCOCK
BOBJOHNSON
PHIL KATZAKIAN
CITY OF LODI
PUBLIC WORKS DEPARTMENT
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LOOI, CALIFORNIA 95241-1910
(209)333-6706
FAX (209) 333-6710
EMAIL pwdept@lodi.gov
http:\\www.lodi.gov
August 1,2008
Rolfes Engineering, Inc. Intech Mechanical, Inc
1036 W. Robinhood Dr., Ste. 201 650 Commerce Drive
Stockton, CA 95207-5627 Roseville, CA 95678
BLAIR KING
City Manager
RANDI JOHL
City Clerk
D. STEVEN SCHWABAUER
City Attorney
F. WALLY SANDELIN
Public Works Director
Joseph H. Schauf Company
225 W. Hamilton Ave.
Campbell, CA 95008
SUBJECT: Adopt Resolution Awarding Contracts for Heating, Ventilation, and Air Conditioning
(HVAC) Equipmentfor Lodi Public Libraryto Intech Mechanical, Inc., of Roseville
($181,154) and to Joseph H. Schauf Company, of Campbell ($71,157)
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, August 6, 2008. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunity to address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P.O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letterto City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Randi Johl, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Dennis Callahan, Fleet and
Facilities Manager, at (209) 333-6800, extension 2690.
T'
F. Wally Sandelin
r • Public Works Director
FWS/Pmf
Enclosure
cc: City Clerk
NCAWARD.DOC