AGENDA TITLE: Accept Improvements Under Contract for City of Lodi Public Library Lighting
Retrofit Project
MEETING DATE: May21,2008
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Accept the improvements under the "City of Lodi Public Library
Lighting Retrofit Project" contract.
BACKGROUND INFORMATION: The project was awarded to Quantum Energy Solutions, of
Rancho Murieta, on November 21, 2007, in the amount of $36,967.
The contract has been completed in substantial conformance with the
plans and specifications approved by City Council.
The contract completion date was March 3, 2008, and the actual completion date was April 23, 2008.
The differencewas due primarily to equipment and material delivery delays and scheduling difficulties.
The final contract price was $33,329, due to a deduct to eliminate the reflectors from many lighting
fixtures, saving the City of Lodi $3,638.
Following acceptance by the City Council, as required by law, the City Engineerwill file a Notice of
Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors
that the project is complete and begins their 30 -day period to tile a stop notice requiring the City to
withhold payments from the prime contractor in the event of a payment dispute.
FISCAL IMPACT: The City anticipates saving approximately $1,000 per month of energy
costs at the Library.
FUNDING AVAILABLE: Public Benefit Funds (164605)
F. Wally Vandelin
Public Works Director
Prepared by Dennis J. Callahan, Fleet and Facilities Manager
FWSIDJCIpmf
cc: Purchasing
Nancy Martinez, Library Services Director
Rob Lechner, Manager of Customer Services and Programs