HomeMy WebLinkAboutAgenda Report - May 7, 2008 E-077 AGENDA ITEM &
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Awarding Contract for Lower Sacramento Road West
Frontage Road Wastewater Pipe Improvement (Bayberry Drive to
Tejon Street) to Granite Construction Company, of Watsonville ($83,677), and
Appropriating Funds ($100,400)
MEETING DATE: May 7,2008
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt a resolution awarding the contract for the
Lower Sacramento Road West Frontage Road Wastewater Pipe
Improvement (Bayberry Drive to Tejon Street) to Granite Construction
Company, of Watsonville, in the amount of $83,677 and appropriating
funds in accordance with the recommendation shown below.
BACKGROUND INFORMATION: This project consists of installing 980 lineal feet of 6 -inch
wastewater pipe, constructing four wastewater manholes,
recon necti ng fourteen wastewater laterals, and other incidental and
related work, all as shown on the plans and specification for the
above project. The locations of the affected homes are shown on the attached Exhibit A.
Plans and specifications for this project were approved on April 2, 2008. The City received the following
eight bids for this project on April 23, 2008.
Bidder
Location
Base Bid
Engineer's Estimate
$87,350.00
Granite Construction Company
Watsonville
$83,677.00
L.R. Gomez Construction
Dixon
$85,044.00
Preston Pipelines, Inc.
Milpitas
$85,162.00
DSS Company
Stockton
$89,334.00
Teichert Construction
Stockton
$102,882.00
Hydro X Services, Inc.
Woodbridge
$114,423.26
William G. McCullough Company
Antioch
$120,332.00
Sierra National Construction
Carmichael
$171,460.72
FISCAL IMPACT: There will be a
slight increase in the long-term
maintenance of the added
wastewater pipe and manholes. However, this project will also decrease
the amount of maintenance required for service of the laterals in this area
APPROVED:
Bla' i , City Manager
K:1W PIPROJ ECTSIS EW E R1LwrSacW W PipelmpvlCAward. doc
412312008
Adopt Resolution Awarding Contract for Lower Sacramento Road West Frontage Road Wastewater Pipe
Improvement (Bayberry Drive to Tejon Street) to Granite Construction Company, of Watsonville
($83,677), and Appropriating Funds ($100,400)
May 7,2008
Page 2
FUNDING AVAILABLE: The requested appropriation includes contingencies, contract
administration and construction inspection.
Requested Appropriation ($100,400): Wastewater Capital (171010)
, Budget Manager
F. Wally Sifidelin
Public Works Director
Prepared by Lyman Chang, Senior Civil Engineer
FWS/LC/pmf
Attachment
cc: City Attorney
Purchasing Officer
Water Services Manager
K:1WP`PROSECTSISEWER%LwrSacW WPipelmpvlCAward.doc 4/23/2008
LOWER SACRAMENTO ROAD WEST FRONTAGE ROAD
WASTEWATER PIPE IMPROVEMENTS
(BAYBERRY DRIVE TO TEJON STREET)
CITY OF LODI, CALIFORNIA
CONTRACT
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred
to as the "City," and GRANITE CONSTRUCTION COMPANY, herein referred to as the
"Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 2002 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are
intended to cooperate so that any work called for in one and not mentioned in the other is to be
executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with
the City, at Contractor's cost and expense, to do all the work and furnish all the materials except
such as are mentioned in the specifications to be furnished by the City, necessary to construct
and complete in a good workmanlike and substantial manner and to the satisfaction of the City
the proposed improvements as shown and described in the Contract Documents which are
hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
CONTRACT. DOC -I 04/25/2008
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
Perform the work necessary to trench and install 978 lineal feet of 8 -inch wastewater pipe,
construct 4 wastewater manholes, reconnect 14 wastewater services, and other incidental and
related work, all as shown on the plans and specifications for "Lower Sacramento Road West
Frontage Road Wastewater Pipe Improvements (Bayberry Drive to Tejon Street)".
ITEM
NO. DESCRIPTION
1. Traffic Control
2. Excavation Safety
3. Trench and Install 8 -Inch
CONTRACT ITEMS
EST'D.
UNIT QTY UNIT PRICE TOTAL PRICE
LS
1
$
7,000.00
$
7,000.00
LS
1
$
2,500.00
$
2,500.00
Wastewater Pipe
LF
978
4. Reconnect 4 -Inch Wastewater
Service
EA
14
5. 48 -Inch Wastewater Manhole
EA
4
6. Wastewater Service
Abandonment
EA
14
TOTAL
$ 46.50 $45,477.00
$ 1,000.00 $14,000.00
$ 3,500.00 $14,000.00
$ 50.00 $ 700.00
$83,677.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
Contract.DOC 2 04/25/08
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 18 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR:
By:
Title
(CORPORATE SEAL)
CITY OF LODI
By:
Blair King
City Manager
Date:
Attest:
City Clerk
Approved As To Form
D. Stephen Schwabauer
City Attorney
Contract -DOG 3 04123108
RESOLUTION NO. 2008-78
A RESOLUTION OF THE LODI CITY COUNCILAWARDING THE CONTRACT
FOR THE LOWER SACRAMENTO ROAD WEST FRONTAGE ROAD
WASTEWATER PIPE IMPROVEMENT (BAYBERRY DRIVE TO TEJON
STREET) AND FURTHER APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on April 23, 2008, at
11:00 a.m., for the Lower Sacramento Road West Frontage Road Wastewater Pipe
Improvement (Bayberry Drive to Tejon Street), described in the specifications therefore
approved by the City Council on April 2,2008; and
WHEREAS, said bids have been compared, checked, and tabulated and a report thereof
filed with the City Manager as follows:
Bidder
Location
Base Bid
Engineer's Estimate
$87,350.00
Granite Construction Company
Watsonville
$83,677.00
L.A. Gomez Construction
Dixon
$85,044.00
Preston Pipelines, Inc.
Milpitas
$85,162.00
DSS Company
Stockton
$89,334.00
Teichert Construction
Stockton
$102,882.00
HydroX Services, Inc.
Woodbridge
$114,423.26
William G. McCullough Company
Antioch
$120,332.00
Sierra National Construction
Carmichael
$171,460.72
WHEREAS, staff recommends award of the contract to Granite Construction Company,
of Watsonville, California, in the amount of $83,677.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council hereby awards the
contract for the Lower Sacramento Road West Frontage Road Wastewater Pipe Improvement
(Bayberry Drive to Tejon Street) to Granite Construction Company, of Watsonville, California, in
the amount of $83,677; and
BE IT FURTHER RESOLVED that funds in the amount of $100,400 be appropriated
from Wastewater Capital funds (171010).
Dated: May 7, 2008
hereby certify that Resolution No. 2008-78 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held May 7, 2008, by the following vote:
AYES: COUNCIL MEMBERS— Hansen, Hitchcock, Johnson, and Katzakian
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS—None
ABSTAIN: COUNCIL MEMBERS— Mayor Mounce