HomeMy WebLinkAboutAgenda Report - April 15, 2009 E-05AGENDA ITEM E70045
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Approve Plans and Specifications and Authorize Advertisement for Bids for
Multimodal Station Driveway Replacement, 24 South Sacramento Street
MEETING DATE: April 15, 2009
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Approve the plans and specifications for the Multimodal Station
Driveway Replacement, 24 South Sacramento Street project and
authorize advertising for bids.
BACKGROUND INFORMATION: This project consists of the removal and replacement of
approximately 5,600 square feet of concrete driveway at the
Multimodal Station.
The Multimodal Station and its concrete driveway were constructed in 1999. During the past 10 years,
bus and truck traffic have broken the concrete driveway and required temporary patching to allow its
continued use. This project will replace the existing driveway with a thicker, stronger concrete pavement
section. The plans and specifications are on file in the Public Works Department. The planned bid
opening date is May 20, 2009.
FISCAL IMPACT: The replacement of the existing driveway should reduce maintenance costs
and provide a safer, more attractive approach to the Multimodal Station.
FUNDING AVAILABLE: The project estimate is $120,000. The money for this projectwill be coming
from Federal Transit Administration (FTA) funds and Transportation
DevelopmentAct (TDA) funds. A requestfor appropriation of funds will be
made at contract award.
Prepared by Wesley K. Fujitani, Senior Civil Engineer
FWSIWKFIpmf
cc: PurchasingOfricer
Paula Fernandez. Transpoltation Manager
APPROVED
K IWPIPROJECTSITRANSrr\MultimodaiDdveway\CPS&A doc
nr -,A�0.1�..._.
F. Wally S delin
Public Works Director
Blair Ki 7!�o
Manager
313112009