AGENDA TITLE: Report on Contract Change Order No. 2 for Lodi Lake Boathouse/Discovery
Center Improvements, 1101 West Turner Road
MEETING DATE: February4,2009
PREPARED BY: Interim Parks and Recreation Director
RECOMMENDED ACTION: Report on Contract Change Order No. 2 for Lodi Lake
Boathouse/Discovery Center Improvements, 1101 West Turner
Road.
BACKGROUND INFORMATION: This information is being given to the City Council in accordance
with the Contract Change Order Policy approved by Resolution 85-
72. One of the requirements of this policy is that we inform the City
Council cf all change orders where the total exceeds $25,000.
Contract Change Order No. 1 was presented to the City Council at its November 19, 2008, meeting and
was in the amount of $49,680.25. Contract Change Order No. 2, approved by the City Manager, is in the
amount of $34,484.50, which is 10.2% of the original contract. Change Order No. 2 also extends the
contract completion date by five working days. The original contract price was $338,250.35. Contract
Change Order No. 2 includes the additional cost to clean-up and reinforce the existing bulkhead along
the edge of the lake ($12,892), provide additional concrete work and guardrails at the Discovery Center
to meet Americans with DisabilitiesAct requirements ($8,726). powder coat the railings and add
improvementsto the existing gate ($6,596), and add a new handicap ramp at the Beach House ($2,876).
The remaining items on Contract Change Order No. 2 address miscellaneous changes to the contract
and include removal and replacement of unsuitable material in the concrete ramp subgrade, the
additional cost to change out damaged pavers, and furnish a flap gate at the storm drain outlet.
FISCAL IMPACT The $34,484.50 is slated to come from state grant funds. No General Fund
dollars are required for these items.
FUNDING AVAILABLE: There were sufficientfunds budgeted in the original project appropriation to
cover these hange orders. However, until State grant funds are released,
park r1f II temporarily cover expenses.
c ns, Management Analyst
James M. Rodems
Interim Parks and Recreation Director
cc: Steve Dutra, Parks Superintendent
Wes Fujitani, Sr. Civil Engineer