HomeMy WebLinkAboutAgenda Report - June 20, 2007 E-04AGENDAITEM Elm y
ift CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Accept improvements under contract for the Blakely Park "South" Pool Deck
Improvements, 1050 S. Stockton Street
MEETING DATE: June 20,2007
PREPARED BY: Parks and Recreation Director
RECOMMENDED ACTION: Accept improvements under contract for the Blakely Park "South"
Pool Deck Improvements, 1050 S. Stockton Street.
BACKGROUND INFORMATION: The project was awarded to 100% Concrete, Inc., of Lathrop on
March 21, 2007, in the amount of $71,420.00. The contract has
been completed in substantial conformance with the plans and
specifications approved by City Council. The contract completion
date was May 25,2007.
Following acceptance by the City Council, as required by law, the Park Superintendent will file a Notice of
Completionwith the County Recorder's office. The notice serves to notify vendors and subcontractors
that the project is complete and beginstheir 30 -day period to file a stop notice requiringthe City to
withhold paymentsfrom the prime contractor in the event of a payment dispute.
FISCAL IMPACT: There is no direct impact to the Parks and Recreation Department budget for the
installation of the new polymer concrete finish. Community Development Block
Grant funds will be supporting the installation of this project in its entirety.
FUNDING: CommunitypeWlopment Block Grant Allocation: $100,000.00
, Budget Manager
Tony C/Gring 11�
Parks and Recreation Director
Preparedby Steve Virrey, Park Project Coordinator
TCGXSV:tl
cc: City Attorney
Steve Dutra, Park Superintendent
Wes Fujitani, Sr.Civii Engineer
Joseph Wood, Community Improvement Manager
Kirk Evans, Budget Manager
APPROVED:
BlairW, , City Manager