HomeMy WebLinkAboutAgenda Report - May 2, 2007 K-01AGENDA ITEM �V 1
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Water Meter Retrofit Policy
MEETING DATE: May 2,2007 (Continuedfrom April 18,2007)
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Direct staff on policy to implement the water meter retrofit program.
BACKGROUND INFORMATION: The State of California has mandated that water meters be
retrofitted on existing customer services. This matterwas brought
to the City Council in 2006 for initial discussion. The Council
requested that staff evaluate the possibility of retrofitting meters on
a "short" time frame.
The attached presentation provides background information, costs of retrofitting meters, discussion on
the meter retrofit program and a recommendation. This is an abbreviated and updated version of the
presentation for the April 10, 2007 Council Shirtsleeve Session. Based on the Shirtsleeve discussion and
comments, staff developed the following recommendation:
❖ July 2007 —Begin installing meter on all new services
❖ Second half 2007 — Develop program, amend ordinance
January 2008:
o Send letterto property owners requiring installation of meter as condition of service with
January 2009 deadline or City will install and bill
o Start four-year program to install (at no charge) pre -paid meters
❖ 2008 — Finish program details, including:
o Bid installation contract
o Adopt interim tiered residential rate structure
o Establish retrofit charge (with one-time or two-year payment plan)
o Establish low-income, owner -occupied cost reduction program (with CDBG funds)
❖ January 2009 —Start three-year contract to install meters, including service upgrades
January 1, 2010 — Start metered billing for customers with meter
❖ 2009 thru 2011— Implement program, including cost of service and rate studies
FISCAL IMPACT: Actual impact will depend on the policy direction.
FUNDING AVAILABLE: Not applicable. 'IN
Richard C. Prima, Jr.
Public Works Director
RCPlpmf
Attachment
cc: Charlie Swimley, Water Services Manager
APPROVED:
Blair King-, anager
K;1W P1PROJECTS\WATERNMeters\CRetrofaPoiicy. doc
4/2812007
Accelerated Water Meter
Retrofit Program
Lodi City
Council
Regularly
Meeting
hq•
O
May 2, 2007
fp-
M1.
yN,
Outline
Background
Shirtsleeve Session Follow-up
Meter Costs
� "Accelerated" Program
Recommendation
Background
Historically, Lodi has metered high volume non-
residential (commercial/industrial) customers
1979 — started installing water services "meter ready"
Active meter retrofit program in late 80's; discontinued
due to budget cutbacks in 1993
1992 State law required meters on new services
• Did not require charging per commodity rates
• Lodi adopted "local rule" — we would charge for meters and
install at later date when appropriate rates were established
New State law now mandates charging for water based
on usage (commodity rates) for all customers
• January 1, 2025 deadline for all customers
• January 1, 2010 deadline for customers with meters
• Allows cost recovery from rates, fees or charges
y 2006 — City installs 400 residential meters for pilot test
3
Approximately 60 pools in homes within pilot test area.
Stockton is City, not California Water Service Co. area.
Roseville is portion within San Juan Water District, not City of Roseville.
9
Shirtsleeve Follow-up
Rate Structure
➢ Tiered Rates (per Black & Veatch survey) :
Percentage of Rate Structures
Area
Uniform
Tiered
Other
Northern
36%
54%
10%
Coastal
39%
61%
0%
Central
Valley
33%
21%
46%
Southern
64%
35%
1%
Shirtsleeve Follow-up
Rates/Conservation
Based on the pilot data and assuming
existing commercial metered rates:
. If customers did not change their usage after
receiving a meter, revenue would increase.
. If customers conserved an average of 15% or
20%, revenue would decrease.
. Total revenue should be about the same as it
is now with flat rates.
. Compared to flat rates, some metered
customers will pay more, others will pay less.
6
Pre -1979 services are buried approximately 30" deep; installing a meter involves
excavation, installing fittings and a riser pipe, a meter box and valves along with the
meter itself on the service (the main line leading to the structure). The meter would
be located at the property or easement line. The estimate does not include
replacing the entire service which, in some circumstances, may be necessary.
Note that as part of the infrastructure replacement program, the City has upgraded
approximately 500 water services at no additional charge to the property owner.
The estimates do not include the higher cost for larger services at apartments or
cases where two lots share a water service.
7
"Accelerated" Program
State law allows for delayed
implementation - either "pay as you go" or
all at once prior to January 1, 2025
Council requested information on how
program could be accelerated
. concern for water conservation
. issues with some customers metered, some
not, for the next 18 years
. some customers have requested meters
8
Goal - Conversion on a "tight" time frame
• If sooner, i.e. next three years — then we need $15. 7 million in
that time frame; either:
from Water Fund
. — not feasible - Fund is nearly depleted
raise water rates
borrow $15.7 million, pay back over time
may not be feasible - roughly 20% rate increase for term of borrowing
pay as you go
may not be feasible - roughly 65% rate increase for 3 years
charge property owners of parcels needing meter
is feasible, only real option to implement soon
charge would range from $350 to $1,200 per home and higher for
apartment complexes and other situations
would not include those that have already paid for meter
charge could be spread over some short time frame, but meter wouldn't
be installed until paid in full since water utility cannot afford to front the
cash
• If later, i.e. sometime next decade — then we need to save up
$15.7+ million
if entire infrastructure replacement revenue ($2 million/year) was
dedicated to this program, it would take 8 years
given PCE and other capital needs, it would actually take much longer
Basic Choices
Who Pays?
. Owner?
. utility?
. Share? (meter by owner, service by utility; or
some other shared cost method)
When?
. Short time frame/Now
. Short time frame/Later
. Longer time frame
10
Feasibility of Choices
(within current rate structure)
* Would be "Yes" if rates were increased
Time Frame
Who Pays?
Short/Now
Short/Later
Long
Owner
Yes
Yes
Yes
Probo� bly
Shared
No
Yes
Probably
Probably
Utility
No
not*
not*
* Would be "Yes" if rates were increased
Policy Issues
During retrofit period, when do we start billing?
• Start metered billing for those who have meters; or
• Wait until required (2010)
• All feasible scenarios will have some "dual rate"
period.
• Recommendation (next slide) includes waiting until
2010
Water utility to share costs?
• by not charging individual customers for
administration of program, permits, one inspection?
• by capping meter and service upgrade costs to
individual customers?
• Recommendation assumes "Yes, we will do these".
12
Staff Recommendation for
Accelerated Program
July 2007 — Begin installing meter on all new services.
Second half 2007 — Develop program, amend ordinance.
January 2008:
• Send letter to property owners requiring installation of meter as condition of
service with January 2009 deadline or City will install & bill.
• Start 4 year program to install (at no charge) pre -paid meters.
2008 — Finish program details, including:
• Bid installation contract;
• Adopt interim tiered residential rate structure;
• Establish retrofit charge (with one-time or 2 year payment plan);
• Establish low-income, owner occupied cost reduction program (w/CDBG $)
January 2009 — Start 3 year contract to install meters, including service
upgrades.
January 1, 2010 — Start metered billing for customers with meter.
2009 thru 2011 — Implement program, including cost of service and
rate study.
13
Questions/Discussion
14