HomeMy WebLinkAboutAgenda Report - March 19, 2008 E-033 AGENDA ITEM I
AMA CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Approve plans and specifications and authorize advertisementfor bids for site
improvements at Lodi Lake Park, 1101 West Turner Road
MEETING DATE: March 19,2008
PREPARED BY: Interim Parks and Recreation Director
RECOMMENDED ACTION: Approve plans and specifications and authorize advertisement ion
bids for site improvements at Lodi Lake Park, 1101 West Turner
Road.
BACKGROUND INFORMATION: The Lodi Lake project was part of the Parks and Recreation
Department 2000 Park Bond Act Per Capita Grant and 2002
Resources Bond Act program request.
The new site improvements around the Lodi Lake Discovery Center are in conjunction with the new
donated boat house from Meehleis Modular and the Lodi Centennial Group.
The work consists of removing and disposing of the existing metal boat house structure, wood decking,
rock retaining wall, galvanized pipe hand railing, decorative rock steps, concrete patio slabs, concrete
walkways, fencing, gates and grinding and stockpiling of asphalt. Newwork will includethe installationof
new Keystone block retaining walls, concrete flat work, a concrete switchback ramp system with hand
railing, concrete curbing, concrete pavers, wrought iron fencing, custom steel guard railing, and
modifications to existing water, sewer and electrical services. Plans and specifications are on file in the
Parks and Recreation office.
FISCAL IMPACT There is no direct impact to the Parks and Recreation Department budget for the
site improvements at Lodi Lake Park. The State Resources Bond Act and Park
Bond Act will support the improvements of this project in its entirety. This project
has the potential to decrease maintenance efforts.
FUNDING: 2002 Resources Bond Act
Prop 40 Per Capita Funds $1 86,000.00
2002 Resources Bond Act
Prop 40 Roberti-Z'Berg Harris Block Grant $1 60,847.00
2000 Parks Bond Act
Prop 12 Roberti-Z'Berg Harris Block Grant $1 68,584.00
Total State Grant Funding: $515,431.00
Engineer's Estimate: $515,431.00
APPROVED: 1�1—
Blair k4icf, City Manager
Approve plans and specifications and authorize advertisementfor bids forsite improvementsat Lodi Lake Park, 1101 West Tumer Road
March 19, 2008
Page 2
Steve Dutra
Interim Parks and Recreation Director
Prepared by Steve Virrey, Park Project Coordinator
SD%SV:tl
cc: Susan Bjork, ManagementAnalyst
Wes Fujitani, Sr. Civil Engineer