AGENDA TITLE: Receive Progress Report on the City of Lodi General Plan Update
MEETING DATE: March 5,2008
PREPARED BY: Rad Bartlam, General Plan Project Manager
RECOMMENDED ACTION: Receive progress report on the City of Lodi General Plan update.
BACKGROUND INFORMATION: Early in 2006, the City Council directed the Community
Development Department to begin the process for updating the City
of Lodi General Plan. On May 17, 2006, the City Council entered
into a contract with the consulting firm of Dyett & Bhatia for services
to update the General Plan.
On September 19, 2007, the City Council authorized the City Manager to execute a contract with myself
in order to manage the program. The background information including all working papers has been
completed. Additionally, the City Council and Planning Commission held a joint session in December to
receive and comment on the information.
Since the joint session, the consultant team and City staff have met to draft the alternatives of the
General Plan. Those alternatives are being fine tuned with a goal of being tinalled by mid March.
Additionally, the fiscal model, which is being developed by Mundie Associates, is nearly complete. Once
the alternatives have been vetted against the various models, the alternatives will be presented to the
public and the formal comment period will begin. None of the General Plan alternatives will be a
"recommended" alternative, but will present various alternatives with the intention of providing a new
community preferred alternative.
SCHEDULE
The schedule represents the assumptions for completion of the various tasks for the General Plan. The
Sketch Plans (Alternatives) will be completed by mid March. The alternatives will be vetted and reviewed
by the public through the month of May. The Draft General Plan policy document and Environmental
Impact Report being complete by December. The public review process and adoption schedule would
commence after the first of the year, 2009 and the projected Final for City Council action in spring, 2009.
BUDGET
The overall program remains slightly over budget. We have made progress in tightening the gap. I remain
confident that we will be able to keep this within ten percent of the original amount from this point
forward.
APPROVED: 1-�
Blair Iity Manager
CADocuments and 5etdngsljperrin\Loca1 5ettings7emporary InternetRilesl0LKC41GeueralPlanUpdatel .DOC
Receive Progress Report on the City of Lodi General Plan Update
March 5, 2008
Page Two
FISCAL IMPACT: None.
FUNDING AVAILABLE: The cost of the above work is included in the contract for the General Plan
Update authorized by the City Council.