HomeMy WebLinkAboutAgenda Report - November 15, 2006 E-07AGENDA ITEM 9407 �" CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Approve Task Order with RMC Water and Environment for Preparation of the City of Lodi Recycled Water Master Plan MEETING DATE: November 15, 2846 PREPA D BY: Public Works Director RECOIY1111ENDED ACTION: Approve a task order with RMC Water and Environment for preparation of the City of Lodi Recycled Water Master Plan. BACKGROUND INFORMATION: On October 27, 2006, the State Water Resources Control Board (SWRCB) issued notification of award to the City of a $75,000 Recycled Water Facilities Planning Grant. The grant application was approved by Council on February 1, 2006 and was prepared and processed by RMC Water and Environment. An important element of the City's long-term water supply is the use of recycled water to serve the water demands of the community. The 2005 Urban Water Management Plan projects that by 2030 up to 2,700 acre feet of recycled water could be used annually within the urbanized area of the community. An adopted Recycled Water Master Plan is prerequisite to future City grant applications for construction of recycled water facilities. The Recycled Water Master Plan will look at areas of use within the community, as well as the agricultural areas westerly toward White Slough Water Pollution Control Facility. The new development areas of Lodi are conditioned to install facilities that would implement the Recycled Water Master Plan. Agriculture usage will be assessed as part of the consultants' work on the master plan. The planned Study Area for this Recycled Water Master Plan has been approved by the SWRCB and is provided as Attachment A. The RMC scope of services and estimated fees are provided in Attachment B. Included in the scope of services is coordination with the concurrent Joint Stockton/Lodi Recycled Water Master Plan study. Early in the study, a Shirtsleeve Session with the City Council will be held to review key assumptions in the program and the general approach to preparing the Recycled Water Master Plan. Completion of the report is scheduled for July 2008. At that time, staff will bring forth the recommendation(s) and request Council approval for moving forward with the recommended alternative. FISCAL iIWIPACT: Not applicable. FUNDING AVAILABLE: Water Fund - $30,000 maximum Planning Grant - $75,000 New Development Funding Sources - $100,000 Reynolds Ranch - $24,000 , ��u Ruby _, PLAste, Fina' I Servie anager Richard C. Prima, Public Works Director Prepared b'1' F. Wally Sandelin, City Engineer RCPIFWSAWnt Attachment$ cc: F. Wagy Sandelin, City Engineer Paul Fernandez, Senior Traffic Engineer Sharon Welch, Senior Civil Engineer Del Kerlin, WW Treatment Superintendent Frank Beeler, W/WW Superintendent APPROVED: Blair King, C' nager JAWaterlC RMC Task Order RWMP.doc 11/10/2006 `F 9ooZ 43jew easy aauuag A04eM POIDAaaa !po-I Jo Aj!3 : � ainBi:j pn}g jo ueld uolwoll iupjJ Suluultld SOIRIPBAullo oaIS JeWM IPol;o APO «s `! .I ifRlfl A • f � • ! 9, fes.✓✓ 6 � a ' gytg" ry �tiq` ART r6� N pn}g jo ueld uolwoll iupjJ Suluultld SOIRIPBAullo oaIS JeWM IPol;o APO Exhibit B ROM I November 2, 2006 Lo�, Angeles Mr. Charles Swirnley, Jr. sacraff"W fan kraftels<0 Senior Civil Engineer San Jose Public Works Department walnut Creek City of Lodi 221 West Pine Street P.O. Box 3006 Lodi, CA 95241-1910 Subject: Task Order No. Two: Recycled Water "Master Plan Dear Mr. Swimicy_ At the City of Lodi's request, RMC Water and Environment (RMC) is pleased to present this proposal to prepare a Recycled Water Master Plan for the City. BACKwGROUND The City of Lodi recognizes several benefits for developing a Recycled Water Master Plan (RWMP) to define the recycled water market potential and identify recommended projects to deliver recycled water for non -potable uses within the City and proposed areas of annexation: ■ Inaproves Water Supply Reliability. Groundwater is currently the sole source of water supply used within the City. With the groundwater basin in a state of overdraft, the City of Lodi is in need of alternative supply sources to meet future water demands, which are projected to more than double between ''005 and 2040. Use of recycled water to serve non -potable demands within this area would preserve groundwater supplies for potable uses and provide additional supply reliability for the City. • Reduces Wastewater Discharges. The City of Lodi, like other wastewater dischargers in the Central Valley, is facing increasingly stringent wastewater discharge regulations. Increased use of recycled water is a key strategy for complying with these future discharge regulations and helps to position the City for ultimately achieving zero discharge. ■ Provides Interim Solution for Use of Supplemental WID Supply. The City of Lodi currently contracts with Woodbridge irrigation District (WID) for an annual surface water supply of 6,000 AFY which is currently unused because the City does not yet have facilities in place to develop that supply. Early construction of portions aory Street of the recycled water distribution infrastructure could provide the City of Lodi with 9th Floof an interim usage of the raw water supplies from WID to serve non -potable irrigation demands. These demands would ultimately be served by recycled water once construction of all of the recycled water distribution facilities is completed. Y p 415.32 3 .,4401 �= ��v.€r�jc uuart�r.r.om The scope of work presented below is for development of a Recycled Water Master Plan which will evaluate the potential for recycled water use within the City limits and bl"ovrativeSolutions for proposed westside annexation areas Water and the Environment l%ge2of5 November 2, 2006 MOF WORK *ntifi�d the fo$owing tasks to complete the scope of works for this project. The tasks associated v*h his scope of work c*ply with the requirements set forth in Appendix B of the Water Recycling lending Program Guidelines. Ift sk 1 Project tion 'L is twk involves the co tion std communications between the RMC team and the City throughout the duration of the project, an4 the Quality Assurance/ Quality Control (QA/QC) activities for project deliverables. An initial kiilkoff meeting will be held with the Project Team to confirm overall approach and sehcdule. RMC will also provide the City with monthly status updates for the project. I3rliverables: 1. Kick off Meeting 2, Monthly Status Resorts urea kjp 'ors: • RMC will attend * total of four (4) coordination meetings (including the Kickoff meeting) with the City to discuss pr*ct status as needed. Mosk 2 locycied Water Feasibility Study l lC will document the r yeled water potential in the City of Lodi by evaluating potential markets and confirming the giomtity arl quality of available recycled water supplies. As part of this task, RMC will complete the following: icy AssumWflons Teehnbal Memoranda. RMC will prepare a technical memorandum documenting the kid assumptions that will ire used in the development of the RWMP, including but not limited to: market asoessrnent methodology, design criteria, and cost criteria. The TM will be revised based on comments from the City. proach Workshop. U#on completion of the Key Assumptions TNT, RMC will conduct a xvoii.shop \N Ali C y Council to review thekey assumptions and general approach of tip,; RVV'NIP. Ties workshop ,4 ii1 aim , irlude discussion of how the RWMP will interface with the Joint RWMP that the City is conducting with S*cklun. Dinka Cohen aired Review. RMC will collect and review any pertinent information for this project (e.g., p*vious pining reports; land use information; water use records to determine nota -potable demands; raoycled/raw water supply and quality data; available survey/geotechnical data; etc). 11Orket Aaaesement. RMC will build upon previous studies to conduct a detailed recycled water market a essment for the City. Tjlis assessment will involve the following tasks: • User Iden ficW oai RMC will identify both urban, industrial and agricultural users within and surrounding the Ci* of Lodi that could potentially use recycled water to meet non -potable demands. This will include identification of both existing and future recycled water users. ■ Dewnd_AssessmUsing water use records and evapotranspiration (E/i') data, RMC will determine the timif and quantity of non -potable demands for each of the potential recycled water users identified. TVs will include quantification of average annual demands, peak month demands, and peak hour derntlnds. ■ Water Suphe Asseasment. RMC will document the timing and quantity of recycled water and raw water WID supplies available to serve the non -potable demands within and around the City of Lodi, including peak mor*h and annual supply availability. Page 3 of 5 November 2, 2006 •#ert Iffy As4itssmet. RMC will gather water quality data for the various water supply sources currently used in'the study area, including (1) existing recycled water; (2) raw surface water (Mokelurme Rivett) supplies; and (3) groundwater supplies. RMC will also evaluate water quality data projected for future recycled water supplies when the Lodi starts using the surface water supplies from WID. RMC will evaluate the quality of each of these supplies in relation to the water quality needs of the potential urban, industrial and agricultural recycled water users. This will include evaluation of various water quality parameters of intcrest (e.g., total dissolved solids (TDS), chloride, sodium, anunonia, nitrate, nitrite, etc) to determine suitability as an irrigation supply, especially for sensitive crops types. Recycled Water Feasibility Workshop. RMC will hold a workshop with the City and other interested stokeholders to present the preliminary results from the recycled water market assessment and review assumptions and outstanding items. I liverabla:: I. Draft and final Key Assumptions TM 2. Approach Worksltbp 3. Project Feasibility°Workshop u #ions: • Pertinent informa*n will be readily accessible. • The Recycled Wa6r Feasibility workshop will be a half-day workshop, hosted by the City of Lodi Task 3 AlternatiDevelopment and Evaluation 1C will develop and ev*uate recycled water alternatives for delivering recycled water and non -potable Y*cr to potential recycie&water customers within the City of Lodi. This task will involve the following: Development or Conceptual :Utrrnatkvs. B;rsed nn the resul? ; of Oie market RNIC will develop cone tual alternatives, including preliwir,ary alignilwats (e.g. specific 1)ip(�iine rut+:cs) for the recycled wilter and non -potable distribution systems, pumping/storage facility locations, and potential demands served by each alternative. Potential satellite treatment opportunities will be developed as appropriate. These conceptual alternatives .will include an interim alternative to use raw water WID s*lies to serve non -potable demands. RMC will prepare a technical memorandum describing the Cotceptual Alternatives for the City's review and feedback. As part of this task, these alternatives will be compared to potential potable water supply alternatives that can be implemented to meet demands. • Alternative Refitment and Evaluation. Based on preliminary feedback on the conceptual alternatives, RMC will rcfine the conceptual alternatives. A hydraulic model (e.g. H2O Map) will be used to determine facility requirements and sizing (e.g., pipeline, storage, pumping) for each alternative. In addition, planning level cost estimates (including capital costs, operation and mairstenance costs, and unit costs) will be developed for each alternative. • Alternatives Ev*ation Workshop/Mid-Course Review Meeting. RMC will present the preliminary results -of the alternatives evaluation at a workshop with the City and other interested stakeholders, including representatives from the State Water Resources Control Board. Dri VgW- tiles: 1. Conceptual Alternative TM 2. Alteftaative s Evalu ion Workshop ltge4of5 November 2, 2016 • No more than We recycled water alternatives, including a "No Project Alternative", will be developed. • RMC will devel a hydraulic model using H2O Map (or similar) for determination of distribution facility suing re emcnts. • The Alternatives valuation Workshop will be a half-day workshop. Task 4 Recycled;Water Outreach UIC will coaduct variou$ outreach activities to potential recycled water users and the general public u1 o0ier to educate them on I�e benefits of recycled water use. This task will involve: • Initial Meetings with Potential Recycles/ 'Vater Users/Opinion Leaders. RNIC will meet witli the largest potentijl recycled water users and opinion leaders (e.g., major vineyards) to describe the purpose of the project, gage their potential interest in using recycled water and discuss any preliminary concetns they may have relating to water quality and supply reliability. • Follow -Up Meetiogs with Potential Recycled Water Users. Following development of recycled water alternatives, RMC will hold follow-up meetings with the largest potential recycled water uses to present the alternatives and discuss any concerns they may have with implementation of the project. The results of these meetings will be incorporated into the recycled water master plan. General Public Outreach. RMC will develop a recycled water brochure that describes the proposed project, the benefits of recycled water and safety of its use. RMC will also help to facilitate a public workshop to address any questions and/or concerns that the public may have. LWiy . m6lm: 1. Large User MectirEs 2. Public Outreach 11,1]aterials 3. Public Workshop AKu2N: • There will be a tool of 5 initial meetings and 5 follow-up with the largest potential recycled water users • The budget for de*Wopment of the recycled water brochure will be limited to $10,000. TINk 3 Rocyeled Water Mewter Plan Tkis tank involves development of Recycled Water Master Plan for the City of Lodi. The RWMP will indudo at least two phases an interisn please that involves use of recycled water infrastructure to convey ra* WiD supplies; and a lgng-term phase that involves serving the annexation area, and futurve development looted in the General Plates sphere of influence. Drat RVNMP. RIAC will develop a Draft RWMP that documents the results from Tasks 2 -4 and presents the recom*iended recycled water project. Specifically, the Draft RWMP will include: o A summa* of study area characteristics, including information on project setting (e.g., hydrologic features, groundwater basins, population and land use); water supply characteristics and facilities; wastewater characteristics and facilities. o Recycled Water market assessment results (potential users and demands, water quality requirements, etc). o Specific agnments, locations and sizes for the recycled water and non -potable system alternatives and recommended project(s) ftge 5 of 5 November 2, 2006 o Preliminary cost estimates (capital, O&M, annual) for each alternative and the recoffimeW project(s). o Fbtential unding/fisancing options to implement the recommended recycled water and non - potable p$ojects. o A draft Implementation plan that outlines strategies for interagency agreements with WoodbriL— Irrigation District, additional recycled water outreach, permitting, an.i environn*ntal compliance for the recommended project(s). o Prelimin*y recycled water market assurances for the recommended project(s) and a descripti* of the ataicipated schedule for future connections. o Potential Folicy option for developers as it relates to the installation of recycled water and/or non-potale distribution piping. • Draft RWAIP Workshop. R:v1C; tivili facilitate a workshop ltiith City staff quid othir intcZVsted stakeholders to w' view the recommendations of the Dram RWMP and solicit comments and feedback. • Final RWA'IP. IMC will prepare a Final RWMP that incorporates all comments received on the Draft. liv ra6l 1. Draft Mager Plan. 2. Final Master Plan • Tha Draf t Master lan will be provided electronically. • Tho Nks%r Plan 'orkshop will be a half-day workshop. • Ten (10) copies o6the Final Master Plan will be printed and distributed to the City. E nTtMATE T* fele estimate and for this scope of work is attached. SOHBKTU tea tativt schedule for iris scope of work is attached. R C Vva r appwiates Ws opportunity to continue providing our consulting services to the City of Lodi. If * -u have any questions 4r require fkrther information, please do not hesitate to call nye at 415.321.3414. Vey truly yours, F46C Wa *W and Enviror)sent R hael M. Wark, P.E. S or Pr+o*t Manager City of Lodi Recycled Water Master Pian Foo gsfilwge RMC Labor Nouns sfe Mark-up TOTAL Total L r Graphic Task Description RMC Labor ($) ODCs ($j (10%) COST (s) PIC PM PE 2 PN 1 Admin Hours Des' n Firm r 198/hr 1541hr 0. 75.. $1 0 ,..: ;$400 $40 t Coordination 14 40 9 63 $11,800 0 $400 $40 12,240 QA/QC 8 4 12 $2,500 $0 $0 $2,500 0 .$ :BO 0, 2A2. >04f8 5$0' S400 `. .. $40 Key Assumptions TM 2 8 16 26 $4,500 $0 $0 2A AM AwasohlMe on' of 4 8 12 $2,9170 $'0 $50 $5 filgg Data Collection 8 24 32 $5,300 $0 $150 $15 $5,465 Market Assessment 8 24 60 40 132 $21,300 $0 1 $0 $21,300 RW FeewbiSity Workshop 4 12 16 8 40 $6,800 $0 $200 $20 $7,020 1AUX 44 „94 0' 212 $"d' $6,800 1 $500 $200 $70 $50 7, Development of Conceptual Atts - TM 2 20 12 42 Alemative Refinement and Evaluation 8 2 48 60 140 $22,200 $0 3 $22,200 Alternative Evaluation Workshop 4 16 8 40 $6,800 $0 $loci S'] $7,020 O 11 36, 64 2 .tF'.;. 0 166 $". QW 41,000 $900 Large Recycled Water User Meetings 24 4" 40 104 $19,300 0 1 $0 Education Materials 2 6 16 26 $4,500 $8,000 $500 - $850 $13,850 Public Workshop 4 16 16 36 $6,500 $0 $500 $50 $7,050 as 400 0 --- 214 $34A0 $1,000 $250 Draft Master Ian 8 21 60 32 124 $20,200 $1,000 $100 1, Draft Master Plan Workshop 4 8 16 8 36 $6,000 $0 $0 $6,000 Final Master Plan 2 1 24 16 54 $8,700 $500 $1,000 5150 $10,350 SubbWffaurs 88 2: 372 184 9 919 �ubtohlcost 7 $155,700 10,000 $3,000 $1,300 iTO, ID Task Name A ! Lodi Recycled Water Master Plan 2 Task 1 - Project Coordination j- Kickoff Mtg 4 Coon*mW*n lilleetifW 9 Task 2 - RW Feasibility Study 10 Key Assumptions TM Wed 11115,*5 Approach Workshop 12 Da6 Collection 13 Market Assessment 14 RW Feasibility Workshop 15 Task 3 - Alternative Analysis 16 Develop Conceptual Atts 17 Submit TM 16 City Review 19 Alt Evaluation 20 Afts. Evaluation Workshop 21 Task 4 - Recycled Water Outreach 22 Initial Meetings with Targeted Ui 23 Follow -Up Meetings with Target( 24 Outreach Materials 25 Public Meeting 26 Task 5 - RWUP 27 Prepare Draft Wed 211 4107 Submit Draft 26 City/SWRCB Review 30 Prepare Final 31 Submit Final Duration Start Finish 184 days Wed 11/15106 Mon 7130107 149 days Wed 11/1511)b Mon 6!11107 1 day Wed 11115,*5 Wed 11,15106 131 days Mon 121111/06 Mon 6/11167 44 days Thu 11116106 Tue ili"T I. 15 days Thu 11/16/06 Wed 1216106:; I day Thu 11/30/06 Thu 11/30106 I . 5 . days . . . .... T66 11/16/06 Wed 1216/06:. 28 days Thu 1217/06 Mon 1115/07:!' I day Tue 1/16/07 Tue 1/16107 j. 62 days. Wed 1/171q7 Thu 4112/07 2 Wks. Wed 1/1711, Tue 1/30/07::.:. I day: Wed 1/31107 Wed 1131/07 2 Wks Thu 211107 Wed 211 4107 46 days Thu 2115107 Wed 4/11/07 1 day: Thu 4/12107 Thu 4112/07 153 days Thu 12171136 Mon 7/9/07:1 28 days Thu 121710F Mon 1115/07 20 days Fri 4113/07 Thu 5110/07: 23 days Fri 41131 Tue 5115107';: 1 day Mon 719 Mon 7/9/07!. 71 days Fri 4113x- Mon 7130107 20 days Fri 4113/�' Thu 5110107 I day Fri 5/11/0' Fri 5/11107:_ 30 days Mon 5114107 Fri 6/22107 14 days: Tue 7/10107 Fri 7/27107 1 day Mon 7130/07 Mon 7/30107 2007 . ..... .. .... ion . Feb € Mar i AD( i Mav Jun 11115 0 qP Lh M& 11130 Task Milestone External Tasks A asIRS, Project: Lodi RWMP Split Summary Externat Miiestorie Date: November 2006 ....... ....... Progress Project Summary Deadline Page 1 0 7/30