AGENDA TITLE: Approve Plan and Specifications and Authorize Advertisement for Bids for
Water "128 Pump and Motor and Site Improvements
MEETING DATE: November 15, 2006
PREPARED BY: Public /Works Director
RECOMINENt3ED ACTION: Approve pians and specification and authorize advertisement for
bids for the Well 28 pump and motor and site improvements.
BACKGROUND INFORMATION: The project will have the contractor famish and install a
150 -horsepower deep well turbine pump and motor, 442 linear feet of
10 -inch water main, 340 linear feet of storm drainage pipe, 410 linear
feet of 8 -foot chain link fence with gate, and other incidental and related
work, all as shown on the plans and specifications for the "Water Well 28 Pump and Motor and Site
Improvements, 2800 West Ketftman Lane" project.
This is the final phase of the well improvement. The well is located on the site of the future Westside
substation and will ultimately be enclosed within the walls of the substation. The completed well will provide
much-needed peak demand water, as well as fire protection for the western edge of the City.
The plans and specifications are on file in the Public Works Department.
FISCAL WPACT: The completed water well will require regular maintenance and operation
costs which will be offset by the water rates.
Project Estimate: $300,000
Planned Bid Opening Date: December 20, 2006
FUNDING AVAILABLE: The project is accounted for in the FY 06/07 Water Impact Fee account in
the amount of $175,000. Staff will return to Council after the bid opening
for project award and ditionai opriation, if required.
Prepared by: Lyman Chang, Associate Civil Engineer
RC PILC/pmf
cc: Water/Wastewater Superintendent
Associde Civil Engineer, Chang
APPROVED: -: -`
Blair Kin Manager
J:IPROJECTSWATER\WeU28Pump&Motor\CPS&A.doc 11/9/2006