HomeMy WebLinkAboutAgenda Report - July 19, 2006 E-05AGENDA ITEM E` T
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Contract Change
Order for the Elm Street Paving Stone Replacement Project, School Street to
Sacrasnento Street, and Appropriating Funds ($45,000)
MEETING DATE: July 19, 2006
PREPARED BY: Public Works Director
RECOMMIT NCeD ACTION: That the City Council adopt a resolution authorizing the
City Manager to execute a contract change order for the Elm Street
Paving Stone Replacement Project, School Street to
Sacramento Street, to perform additional downtown street paving
stone maintenance activities and appropriating an additional $45,000 in Proposition 42 Transportation
Improvement Act funds.
BACKGROUND INFORMATION: The paving stone subgrade within the travel lanes along Elm Street
between School Street and Sacramento Street was recently
repaired. The contractor completed the work within the original
contract price of $ 57,585.
However, some paving stones in areas along School Street between Locust Street and Lodi Avenue are
showing signs of wear and tear, in some cases due to loss of sand between the joints. These paving
stones were originally placed in 1995 as part of the Downtown Improvement Project. Staff requested the
Contractor submit a proposal to remove and replace the paving stones in these areas and to re -compact
the subgrade where failures have occurred. The price to perform these additional maintenance activities
is $52,728, as reflected on the attached proposal, and is comparable in price per square foot to the
original bid price. It is recommended this work be completed before the rains to prohibit further
deterioration of this downtown street. The City Attorney has reviewed and approved this process and
proposal.
Staff is requesting Council authorize the City Manager to execute a contract change order for the
Elm Street Paving Stone Replacement Project, School Street to Sacramento Street, to perform additional
downtown street paving stone maintenance activities and appropriate an additional $45,000 in
Proposition 42 Transportation Improvement Act funds.
FISCAL IMPACT: The paving stones within areas along School Street have become unstable
and will continue to further deteriorate if not addressed. The affected areas
will continue to become larger and repair costs will increase if not performed
prior to the winter months.
APPROVED:
Blair King, -City Manager
J 1PROJECTSISTREETS\EImlPavingStoneReplacement\Cchangeorder.doc 7110/2006
Adopt Resolution Authorizing City Manager to Execute Contract Change Order for the Elm Street Paving
Stone Replacement Project, School Street to Sacramento Street, and Appropriating Funds ($45,000)
July 19, 2006
Page 2
FINDING AVAILABLE: The money for this project will be coming from Proposition 42 Transportation
Improvement Act Funds.
Original Appropriation: $ 75,000
Original Contract Price: $ 57,585
Proposed Change Order: $ 52,728
Revised Contract Price: $110,313
Additional Appropriation Request: $ 45,000
yyyi
U y Paiste, Interim Finance Director
WWAM
Richard C. Prima, Jr.
Public Works Director
Prepared by Charlie Swimley, Senior Civil Engineer
RCPICES/smf
Attachment
cc: Joel Harris, Purchasing Officer
F. Wally Sandelin, City Engineer
George Bradley, Street Superintendent
J1PRQJECTSISTREETS1EimlPavingStoneReplacement\Cchangeorder.doc 71712006
page 1
J uro 15, 2046
Wes Fujitani
Citi of Lodi
RE: Paver Work on Scheel Street From North at Locust to South at Lodi Ave.
Arm 1 From Locust to S*u* Side of Elm we attacked drawlog.
Remove, add mW and re staii pavers 3 arcs approximate total of 430 sq.ft.
Orrice for R & R work is ........................ S 3,900M
Sating and sweeping ofentire black and intersection 19,917 sq.ft. @ S .21/sq.ft.
AMR 2 Frost Elam to Som Side of nue set atUmbed drawing.
Remove, add sand and r l pavers 5 areas approximate total of 1,519 sq.ft.
Our primo for R & R work, is ........................ S 12,000.00
Sa ng arW sweeping ofentire block and intersection 20,360 sq.ft. @ S .21/sq.ft.
Area 3 From Fine to Sem Side of Oak see atumbed dry.
Remove, acid send and roo-iristall pavers 5 areas approximate tow of 376 sq.ft.
Out price for R & R wot* is ........................ S 3,444.0.♦
Sarding and sweeping o entirc block and intersection 20,010 sq.ft. @ S .21/sq.ft.
Aria 4 From Oak to SeWh Side of Wait see attacked drawing.
Remove, add swirl and re-mstell pavers 10 areas approximate total of 1,172 sq.ft.
Out price for R & R wott is ................... . . S 9,962.00
Sanding and sweeping ofentire block and intersection 18,457 sq.ft. @ S .21 sq.ft.
Ar4a S From Walnut to, edge of pavers on North Side of Lodi Ave. see attached drawing.
Remove, sued sand and re -install pavers 6 areas approximate total of 233 sq.ft.
Out Price for R & R work is ...................... S 2,731.00
Smiling and sweeping ofentire block 19,750 sq.ft. @ $ .21/sq.ft.
Osm pullet of Nam US Missies Pavers needed for replacem... 5300.00
Seep; page 2 for inclusions end exclusions.
page 2
Incudes: Labor, Equipment and Sand to remove, re -grade the sand bedding course and
re -install the existing pavers, inserting new pavers as needed from the pallet purchased
by the City of Lodi.
Union Prevailing Wage Labor ( regular daytime work hours ;
Traffic control around the immediate area of work.
( Sanding and sweeping of the entire area if that add option is accepted )
Excludes: All areas not noted as part of this proposal, any additional areas can he priced as
needed should they become an issue. Excludes re -painting any pavement markings.
All Bonds, and 11185 Additional Insurance Endorsements.
( you should have our insurance information on file from Elm St)
Prioess are based on doing one block and one intersection at a time move -in. Also, based on
being provided approximately 2 adjacent parking stalls at each area for staging as we move from
one area to the next. We will need to close the street in the area being repair or sanded.
If accepted, we will need a work/purchase order for these items. If you choose to break it up into
selected areas please cross reference our proposal and drawings.
Earth Shelter Developers
Dan Williams
QHS. ST"T :Pi.
PROPOSAL FROM EARTH SHELTERS
area 1
Locust-EIrn
49817
area 2
Elm-PIne
20M
area 3
Pine -Oak
20010
area 4
Oak -Walnut
18457
TOTAL
One pallet of 4X8 Mission
Pagers
five and R"bm
$ 3,900.00
$ 12,088.00
$ 3,444.00
$ 9,962.00
$ 11,76
$ 32,044.00
M
self
$ 4,489.57
$ 4,276.00
$ 4,202.10
$ 3,875.97
$ 20,683.74
$ 52,727.74
RESOLUTION NO. 2006-139
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
THE CITY MANAGER TO EXECUTE A CONTRACT CHANGE
ORDER FOR THE ELM STREET PAVING STONE REPLACEMENT
PROJECT, SCHOOL STREET TO SACRAMENTO STREET, AND
FURTHER APPROPRIATING FUNDS
NOW, THEREFORE, BE IT RESOLVED that the City Manager is hereby
authorized to execute a Contract Change Order for the Elm Street Paving Stone
Replacement Project, School Street to Sacramento Street, to perform additional
downtown street paving stone maintenance activities; and
BE IT FURTHER RESOLVED that $45,000 be appropriated from the Proposition
42 Transportation Improvement Act funds for this project.
Dated: July 19, 2006
I hereby certify that Resolution No. 2006-139 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held July 19, 2006, by the following
vote:
AYES: COUNCIL MEMBERS — Beckman, Hansen, Mounce,
and Mayor Hitchcock
NOES: COUNCIL MEMBERS — Johnson
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
NiFER . PERRIN
Interim City -Clerk
2006-139