HomeMy WebLinkAboutAgenda Report - June 21, 2006 K-02AGENDA ITEM %44"
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt OWsolutiion Implementing the Treatment and Direct Utilization of the
Surface Water Supply from the Woodbridge Irrigation District Contractual
Allotmont and Authorizing Solicitation of Proposals for Technical Studies of
Implerr[lenting this Option
MEETING DATE: June 21, 2006
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt a resolution initiating direct use of the
Woodbridge Irrigation District (WID) annual 6,000 acre-feet
contractual allotment by authorizing the solicitation of proposals for
technical studies as described below.
BACKGIINOUND INFORMATION: On several past occasions, the City Council has received information
regarding the usage of the City's contracted 6,000 acre-feet per year
of Mokelumne River water from WID. Copies of the most recent staff
reports are attached (Attachments A and B).
Staff has recommended direct use of this water over groundwater recharge. At the April 19, 2006
meeting, Council asked a number of questions and requested additional information and, at the request
of Mr. Ed Steffani of the North San Joaquin Water Conservation District (NSJWCD), delayed making a
decision pending the results of a recharge test at a site adjacent to Micke Grove. This report answers
those questions, provides the requested information, and summarizes the reasons for the staff
recommendation of planning for direct use of the water.
gU200M Mesut M
? What are the results of the Micke Grove recharge test?
A The test was not completed. The lease -holder did not agree to continue the test. This raises
a fundamental question of landowner consent and the City Council's willingness to pursue a
project at any given location over a property owner's or tenant's objections.
? How would the City recover recharged water at the Micke Grove site?
A In order to recover recharged water at the Micke Grove site, the City would need to install a
well field and water mains connecting the well field to the City's system (Attachment C). This
is a different project than the recharge project alternative previously discussed. Properly
sizing, locating and cost estimating a well field would require an extensive hydrogeology study
and field tests. For purposes of this concept level discussion, we assumed the same number
and cost of wells that would be needed to meet the City's needs under future conditions
(5 wells, $3 million). Also, we estimated that a 30 -inch water transmission main (and possibly
a booster pump station) would be needed at an additional cost of approximately $5 million.
Thus, the total cost of the recovery system would be appro 'mately $8 million. Note that this
APPROVED:
it King, City Manager
J:\Water\ClmplementSurfaceWaterProgram (3).doc �� %` 6/15/21106
Adopt Resolution Implementing the Treatment and Direct Utilization of the Surface Water Supply from the
Woodbridge Irrigation District Contractual Allotment and Authorizing Solicitation of Proposals for
Technicai Studies of Implementing this Option
June 21, 2006
Page 2
well field would be located in and near planned development in North Stockton. This raises
numerous complications and issues regarding the future viability of this project.
? What are the cost implications of purchasing versus leasing property?
A Lease costs versus purchase costs are estimated and summarized in the table below:
Recharge Basin - Land Cost Comparisons
Land Area: 88 Acres
Purchase Cost/Acre'): $ 30,000 $ 60,000 $ 100,000 $ 200,000 $ 300,000
Total Cost (Purchase): $ 2,640,000 $ 5,280,000 $ 8,800,000 $17,600,000 $26,400,000
Lease Terre: 40 Years
Lease CostlAcre/Year: $ 225 $ 275 $ 350 $ 500 $ 750
Initial Costsz): $ 880,000 $ 880,000 $ 880,000 $ 880,000 $ 880,000
Total Cost (40 Yr. Lease): $ 1,672,000 $ 1,848,000 $ 2,112,000 $ 2,640,000 $ 3,520,000
Notes:
1) Purchase cost includes any site development andlor conveyance costs in addition to actual basin construction costs.
2) Initial costs for lease assumes $10,000 per acre allowance to compensate owner for removal of vines, trees, etc.
Leasing is most likely to be less expensive, although depending on purchase price and lease
terms, purchasing could be less expensive over time. The above calculations do not take into
account the time value of money, future value of the land and improvements after the
assumed 40 -year term and the value of maintaining permanent open space.
What are the water chemistry issues at the Micke Grove site?
A The area is known to have DBCP contamination. The City Attorney has indicated that actions
that move or spread contamination could place the City in a difficult liability situation. Also,
while the City's costs for DBCP removal in City wells are covered under the terms of a
settlement agreement, it is not specific as to how the settlement would apply to wells placed
outside the City as part of a rechargelrecovery project. Quality of the water recovered from a
recharge site would likely be a blend of native groundwater and recharged water.
One water test was done at Armstrong and Pearson Roads, and while no DBCP was found,
the water was high in bacteria and nitrate, possibly indicating septic tank influence; see below:
J:1Water\Clmplement5urfeceWaterProgram (3).doc 6115/7!O B
Adopt Resolution Implementing the Treatment and Direct Utilization of the Surface Water Supply from the
Woodbridge Irrigation District Contractual Allotment and Authorizing Solicitation of Proposals for
Technical Studies of Implementing this Option
June 21, 2006
Page 3
Constituent
Test Site
City Well Average
Notes
Nitrafe (mg/1 . N)
6.9
2.1
MCL is 10
Total Dissolv6d Solids
(TDS) mgA
556
247
Delta Goal is 450
Total Coliforms
Bacteria
170
<1
Over 1.1 would be a
drinking water failure
? What°are the cost estimates for recharge versus a treatment plant?
A The cost estimates have a fairly wide range given the large variation in possible WW costs fdr
recharge, the unc inty over future treatment costs for well water and the lack of site and
technology assessflnent for direct use of the surface water. Based on the above land costs
and the detail cost information from Attachment A, Exhibit B, the following table summarizes
these ranges. In the short-term, recharge could cost less money. Capital costs of either
project can be recovered through Water Impact Fees or other development financing
mechanisms. Increased operational costs could be recovered through rate surcharges or
community facilities district charges for new development; however, this would effectively
mean that the City would have two rate zones, which has not been recommended by staff.
Rectorge vs. l)ir+ect Use Capilletl Costs
Low Range High Range
Rechargm $ 6,013,000 leased land @ $ 30,301,600 purchased
$350/acre for land @
40 years $300,000/acre
Recharge $ 11,013,000 above plus $ 35,301,000 above plus
wtteicoveryk transmission transmission
system system
CNrect Use: $ 29XM,000 latest estimate $ 36,700,000 2004 estimate
uCL
The reaans behind the staff recommendation for direct use of the WID water are many. Briefly, they
are:
• 1011verstfic ation of Supoy — Use of multiple supply sources is the preferred model for urban wafer
providers. In particulalr, conjunctive use of surface water and groundwater is a key element in the
California Water Plan (Attachment D). Key to this strategy is using surface water when it is
available (in -lieu rech*rge) and using groundwater in dry years. This strategy is being embraced
by many Central Valley cities.
• Sustainable Use — The groundwater basin in which Lodi draws its water is being overused to the
point the area is seeing water quality being adversely affected. This is not a sustainable practice.
The United States Geological Survey has issued a report on groundwater use in the Western
J:1Wsier\CltWemerrtSurMmWaiaProgram (S).doc 6N512OG6
Adopt RosobAon Implementi4g the Treatment and Direct Utilization of the Surface Waiter Supply from the
Woodbridge Irrigetion District�Contractual Allotment and Authorizing Solicitation of Proposals for
Technics Studies of Implemslnting this Option
June 21, 20th
Page 4
Mates thot stabs: "P nt management would give serious consideration to strategies that eely
dOi serve warner and Nold groundwater in reserve."
• Irovenvert in Wastorater Quality — Mokelumne River water is substantially lower in total
d sohed solids (TDS than our groundwater. Using this source will reduce the TDS of our
v steowater by 14% to28% depending on a variety of factors. Since our eMuent is very neer the
current goal for Delta discharges, a reduction could help forestall more expensive treatment.
• Recommendations from Others — Staff routinely meets with other water providers in the area and
hes sought out their opinions on this question. A large majority of those opinions recommend
erect use. We have received formal support for direct use from WID and NSJWCD
(Attachment E, F). The staff presentation will include comments from staff from WID, San
Joaquin County Water Resources Division and City of Stockton.
• Legal Support — While4egally either option can be done, staff sought the legal opinion of an
expert in water rights. Dan O'Hanlon, of Kronick, Moscovitz, Tiedeman & Gerard has been
assisting the City in the PCE/TCE issue and other matters. He is also legal counsel for a number
of water districts outside San Joaquin County. The City Attorney has provided the Council a
confidential memo on the subject. The Summary of Conclusions states:
"You have asked me to review the potential legal implications of alternative approaches to
use of the surf*De water supply that the City of Lodi has acquired through a contract with
Woodbridge Irrigation District. The City is considering two basic options: (1) use the
surface supply to recharge the groundwater aquifer, and continue to rely on groundwater
as its sole source of supply; or (2) treat and use the surface supply directly, and thereby
reduce its use at groundwater.
In our view, the second option, treating and directly using the surface supply, offers the
most protection for the City's rights to its water supply. Likewise, we believe that treating
and directly using the surface supply puts the City in the strongest position to satisfy its
obl gations to plion for and provide reliable water supplies. The reasons for these
conclusions are discussed below.
Our review is lionited to the potential legal implications of the two alternative courses of
action. We have not addressed and express no view regarding the relative costs of the
two courses of action, or any other relevant factors that may influence the City's ultimate
view of the best course of action."
Staff is rue" City Counc# approval to initiate implementation of the direct use option to utilize the
WID 6,040 acre -tri contractual allotment. The first steps will to to solicit proposals from three water
consultiro firms: HDR, RIC, end West Yost & Associates, all of whom were prev4ously pre -qualified for
Lodi water studies. The time tame from proposal solicitation to final deliverables is 12 months and the
estimated cost is expected to range from $250,000 to $500,000. The studies are all interrelated and will
include:
• Process Evaluation/Pitt Study — This study will evaluate various technologies for direct use of the
water, with emphasis an meeting the latest and anticipated regulatory requirements and
rrirnizing tarso and odor issues.
J:lwabotAclmoommo.%Ffomwataomgmm P"M 6/1'W*6
Adopt Resolution Implementing the Treatment and Direct Utilization of the Surface Water Supply from the
Woodbridge Irrigation District Contractual Allotment and Authorizing Solicitation of Proposals for
Technical Studies of Implementing this Option
June 21, 2006
Page 5
• Watershed Sanitary Survey — One regulatory requirement for use of surface water is a study of
the source waters to identify potential contaminants and other issues that could affect the design
of the system.
• Site Assessments — As noted, there are at least two potential sites for the necessary facilities.
These need to be evaluated in light of the two previous studies.
• Cost Estimates — These will pull together the information from the three previous studies and
evaluate alternatives on a cost basis. Included in this will be consideration of possible
arrangements with other water providers and potential for phased construction.
• Financing Plan — This will identify possible arrangements to finance the facilities and impacts to
development fees and water rates.
• Environmental/Regula" Actions — The project will need an environmental impact report and a
permit from the State Department of Health Services.
• General Plan — While this is a separate endeavor, staff will work with the General Plan
consultants to incorporate appropriate policies and implementation measures. Given that 213 of
the City's water supply will still come from groundwater, staff will recommend that the City pursue
groundwater recharge, using storm water and any other intermittent water supply that may
become available.
FISCAL IMPACT: No fiscal impact at this time. Staff will return to Council requesting
authorization to execute a professional services agreement with the
successful firm. Note that the City is paying WID $100,000 per month for
this water. The banking provisions of the agreement provide for our future
use of past paid -for water at a later date. WID has agreed to a four year extension of the banking
provisions and staff will be returning to Council for formal approval when the actual wording of the
agreement amendment is finalized.
FUNDING AVAILABLE: Water Fund
Uaw
Richard C. Prima, Jr.
Public Works Director
RCPlpmf
cc: Steve Schwabauer, City Attomey
Wally Sandelin, City Engineer
Anders Christensen, Woodbridge Irrigation District
Mel Lyne, San Joaquin County Water Resources Division
Mark t1%dison, City of Stockton Murddpal Utilities
Ed Std*ni, North San Joaquin Wafer Conservation District
Dan 0' Manion, KMT'G
J:1WatehClmplementSurfaoeWatwPrograrr (3).doc 6115/2006
ATTACHMENT A
Am CITY OF Low
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Recelve Background Information on Implementing Woodbridge 1,1hp n
Distrito SuAace Water Program
MEETING DATE: March 1, 2006
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council receive background information on
implementing the surface water treatment program utilizing the
Woodbridge Irrigation District (WID) 6,000 acre-feet contractual
allotment. This material is being provided in advance of the
March 15, 2006 Council meeting at which staff will request preliminary approvals as described.
BACKGROUND INFORMATION: On several past occasions, the Council has received information
regarding the acquisition and usage of 6,000 acre-feet per year of
Mokelumne River water from Woodbridge Irrigation District, In
May 2003, the City contracted with WID to provide untreated
surface water to Lodi for 40 years. At the September 21, 2004 Shirtsleeve meeting, the Water Supply
Options Report was presented to the Council. At the April 19, 2005 Shirtsleeve meeting, staff again
presented alternatives for implementing the 6,000 acre-feet per year surface water supply. On
April 20, 2005, Council approved hiring a consultant to further study and develop a recommendation for
full implementation of the WID surface water supply. On June 9, 2005, Council was given a copy of the
WID Surface Water Implementation Study. On November 1, 2005, Council received a presentation from
the consultant and the recommendation that the City go to a conjunctive use water supply system – one
that utilizes both groundwater and treated surface water to serve the demands of Lodi's customers.
Over the course of the past three years, a number of alternatives have been considered with the most
feasible options being "treat and drink" and "groundwater recharge". Some of the other alternatives
studied include: 1) injection well recharge, 2) raw water irrigation of paries and schools, 3) recharge
ponds within the City limits, 4) recharge ponds using North San Joaquin Water Conservation District
facilities, 5) East Bay Municipal Utility District banking, and 6) interim supply to Stockton recharge ponds.
These alternatives were ruled out primarily due to high costs and regulatory uncertainties.
At the regional level, City of Lodi has been participating in several water supply activities that will,
hopefully, bring additional water supplies to the City and the other agencies in the region. Examples
include the Mokelumne River Water and Power Authority MORE Project that seeks to capture
unappropriated peak flows in the Mokelumne River. Also, Lodi is collaborating with Stockton East Water
District, North San Joaquin Water Conservation District and WID on a pilot -scale recharge project near
Micke Grove Park. North San Joaquin Water Conservation District recently passed a groundwater
recharge assessment for their groundwater recharge and is evaluating multiple sites in its district. Note
that a large part of the City (generally, the area east of Mills Avenue) is within the District and pays this
nominal assessment.
APPROVED: /—t
Blair King, �Ci Manager
J:%WateHCWoSLd 1W8ViAWPr0QMM-doe 212312008
Receive Background Information on Implementing Surface Water Treatment Program Utilizing
Woodbridge Irrigation District Contractual Allotment
March 1, 2006
Page 2
The recently -completed 2005 Urban Water Management Plan concisely presents the City's existing and
future wafer supply vs. demand outlook (see Exhibit A). As shown on Exhibit A, the safe long-term yield
of the groundwater basin underlying the City is estimated at 15,000 acre-feet annually (afa). At present,
the City is using 17,300 afa to meet the demands of existing customers, reflecting a current need for
additional water supply and/or conservation.
The UWMP anticipates that through a combination of conservation (the on-going City-wide installation of
water meters is expected to conserve approximately 2,400 afa upon completion) and adding 6,000 afa of
WID treated surface water, the City's sustainable water supply will meet or exceed the projected water
demands up to the year 2029.
The City Council will be asked to support staffs recommendation to pursue the "treat and drink"
alternative on the basis it is the "highest and best use" of the WID water given a number of factors that
are compared below.
Cost
The estimated construction cost for a surface water treatment facility and associated facilities is
estimated to be up to $29.5 mNlion. These costs are inclusive of site acquisition, surface water diversion
piping, ultrafiltration (without pretreatment) using membrane technology, chlorine disinfection,
transmission piping, and storage tanks. This alternative does eliminate the need to construct additional
wells to serve future demands.
The construction cost for a groundwater recharge program is estimated to be $30.3 million. This
assumes a recharge field 88 acres in size adjacent to the WID canal at $300,000 per acre, including site
improvements and pipe appurtenances. Construction of five new wells is included in the estimate.
These costs are different from other numbers that have been discussed in the past. A comparison of
former and current estimates is provided in Exhibit B.
In either scenario, new development is expected to fund the capital improvements. Operating and
maintenance costs are considerably higher for the "treat and drink" alternative, when compared to the
recharge option. The change to current rates would be an increase of approximately 15% (very rough
estimate), if the burden was shared City-wide.
Benefit
Criteria to evaluate benefits to the City of Lodi and the region include: 1) direct benefit to the
groundwater resource, 2) long-term water quality, 3) sharing the regional burden, and 4) time of use.
Each is discussed below.
Benefit to the Groundater R ource
In the context that the water demands of existing Lodi are matched by the safe yield of the groundwater
resource, the "treat and drink" alternative eliminates further mining of the groundwater and, thereby,
results in the highest direct benefit to the groundwater basin currently serving the City.
Groundwater recharge programs have a number of inherent losses including evaporation, uptake by
plant materials, and capture within the soil column. These losses can be as high as 30 percent, meaning
111G: ilii ICii it�Su i t;actiti ;ier1'ru�s airs doe 2117/2006
Receive Background Information on Implementing Surface Water Treatment Program Utilizing
Woodbridge Irrigation District Contractual Allotment
March 1, 2006
Page 3
the process is about 70% of ient. In addition, the recharge water, once it reaches the groundwater,
moves away from the Lodi point of use and toward the centralleastem-County groundwater depression.
A map of the County groundwater contours is provided in Exhibit C.
Lona -Tem Water Quality
Lodi has long enjoyed a high quality of water that is pumped from the ground through wells that are
clustered in relatively close proximity to the Mokelumne River. Not only has the quality of water been
excellent, but the yield from each well has been relatively high, with an average yield of approximately
1,400 gail!ons per minute. Based upon experience and water quality information for areas southerly and
westerly of the City, new wells in these areas are expected to have a higher salinity level and lower
yields.
For the "treat and drink" alternative, the salinity levels in the treated surface water will be lower than
levels currently found in the groundwater. Combining these two sources for potable use will result in a
lowering of salinity levels in both our drinking water and our wastewater. This provides a long-term
tangible benefit to the City as the State is expected to impose limits on salinity for discharges to the
Delta. Lowering the salinity of our "source water" will help avoid very costly improvements to remove
salinity at the wastewater end of the use cycle.
A groundwater recharge program will essentially not alter the water quality characteristics of the City's
groundwater resource.
The "treat and drink" alternative will result in chlorination of the entire City water system as is required by
State regulation. Most in the industry agree that chlorination requirements will also be imposed upon all
groundwater users in the foreseeable future.
Sharing tate Regigoal_ Burden
On a regional basis, the various cities and agencies are collaboratively working to enhance the supply
side of the region's groundwater resource. The groundwater basin Lodi shares with other agencies and
individual property owners is being mined by over 150,000 afa. This results in declining water levels in
wells, which reduces yield, increases pumping costs, and impacts water quality as more saline water is
drawn into the basin, rendering wells unfit for use. 150,000 afa and more is needed to meet the goal to
reverse and stabilize this problem. On a conceptual level, the principal strategies to achieve this goal
include: 1) securing additional surface water resources, 2) elimination or deferral of further groundwater
pumping, 3) banking through recharge or deferral of pumping, and 4) regional recharge. The MORE
project was described above. The Stockton Delta Water Supply Project includes a treatment plant that
will begin treating 56,000 afa within three years. Lodi's water treatment plant can begin producing
6,000 afa of treated drinking water within 4.5 years. A recharge program would provide somewhat less
regional benefit by virtue of the losses described above.
Time of Use
Water demands within the City are highest in the spring, summer and fall. Conversely, the lowest
demands are in the winter. Our WID water is available from March 1 through October 15, and this
perfectly matches our highest demand period. Lodi has secured high quality surface water deliveries that
meld with demands, both in quantity and in time. To store such water in the ground during periods of
peak demands does not make a lot of sense.
JAW ales Ul Ito& I laccwatorpfoos aFtt.doc 2117/2008
Receive Background Information on Implementing Surface Water Treatment Program Utilizing
Woodbridge Irrigation District Contractual Allotment
March 1, 2006
Page 4
As is the strategy of many of the regional recharge programs, excess water, that usually becomes
available in the winter months, is diverted to fallow fields for percolation. Often times, this water is
sediment laden and well suited for groundwater recharge. The City of Lodi could pursue a similar
strategy by diverting storm drainage water to recharge areas and/or by altering designs for new
developments to incorporate recharge facilities.
Staff RegWmenJp on
At the March 15 meeting, staff will be requesting City Council approval to move forward with the "treat
and drink" alternative and that the City Council authorize staff to solicit proposals for Preliminary Water
Treatment Master Planning work required to prepare preliminary design alternatives and further
recommendations. Design alternatives could include partnerships with other agencies.
Among the tasks to be done are
1. Watershed Assessment
2. Process Evaluation and Pilot Testing
3. Alternative Site Evaluations
4. Cost Estimates
5. Financing Alternatives
6. Environmental and Regulatory Considerations
Staff recognizes that this recommendation is not what we anticipated when the WID water purchase
agreement was made. Since then, a number of factors have made groundwater recharge a less
desirable alternative. Regulatory requirements on recharge projects have increased in the last few years
and, most recently, water rights and underground storage permit requirements are making recharge
projects more uncertain in the long -run. However, as noted earlier, recharge may be a viable alternative
for the irregular peak flows associated with local storms and high river runoff events.
Due to the design complexity, regulatory requirements and cost of projects of this nature, major design
decisions today are no longer made unilaterally by a project team. Instead, a consensus is reached only
after participation by members of the design team and individuals outside the team, including owners,
operators, regulatory agencies and the general public. Therefore, a process of measured steps, of which
this is the first, is our recommendation.
FISCAL IMPACT: Information only. None at this time.
FUNDING AVAILABLE: Not applicable.
Richard C. kma, Jr.
Public Works Director
Prepared by Richard Prima, Public Works Director and F. Wally Sandelin, City Engineer
RCP/FWS/pmt
Attachments
\�� 51s�1�1 ��'ti�,tti �y�'i 1,1t �'��,S�i�l��i�'51�, kM t1O, ?J17/2006
m
(� m
C,
N
ro
°O
� o
CD
[�
LO
o
o
z
C Z
}s
N
m
o_ a.,P a
ren
00
a
a
c
0
N
LO
O
N
a
v
N
t!]
a
a
N
G Q C
C
a G
C O Q
O
C C
G LO a
co N N
u7
�-
a L-0
r
LkAv) Puewaa
EXHIBIT B
Comparison of Planning Cost Estimates
Recharge Basin
Surface Water Treatment Plant
2005
2006
Construction of Recharge Basin
$593,000
$593,000
Construction Contingency 20%
$119,000
$119,000
Engineering and Other Fees 15%
$89,000
$89,000
Subtotal
$801,000
$801,000
Purchase Land for Basin
$17,600,000
$26,400,000
CEQA/NEPA
$100,000
$100,000
Water Wells
$36,700,000
$3,000,000 z
Total
$18,501,000
$30,301,000
Surface Water Treatment Plant
(1) The land cost for 88 acres is assumed to be $300,000 per acre compared to
$200,000 per acre as reflected in the West Yost Lodi Surface Water
Implementation TM. (West Yost TM)
(2) Five new wells are required for the groundwater recharge alternative and the
estimated construction cost is $600,000 per well or $3,000,000. This cost was
not included in the West Yost TM.
(3) Further research into the type of treatment processes and after visitation to three
Northern California plants, a better planning estimate has been determined to be
$20,000,000 for constructing a 10 MGD treatment plant and associated
transmission facilities.
(4) The land cost for 5 acres is assumed to be $300,000 per acre, compared to
$200,000 per acres as reflected in the West Yost TM.
(5) The West Yost TM presented a $50 million number that was $36.7 million
adjusted to the forecast mid -point of construction.
J:\Water\ClnfoSurfaceWaterProgram_ExB.doc
2005
2006
Surface Water Treatment Plant
and Associated Transmission
Facilities
$25,700,000
$20,000,000(3)
Construction Contingency 20%
$5,100,000
$4,000,000
Engineering and Other Fees 15%
$3,900,000
$3,000,000
Subtotal
$34,700,000
$27,000,000
Purchase Land for Plant
$1,000,000
$1,500,000
CEQA/NEPA
$1,000,000
$1,000,000
Total
$36,700,000
$29,500,000
(1) The land cost for 88 acres is assumed to be $300,000 per acre compared to
$200,000 per acre as reflected in the West Yost Lodi Surface Water
Implementation TM. (West Yost TM)
(2) Five new wells are required for the groundwater recharge alternative and the
estimated construction cost is $600,000 per well or $3,000,000. This cost was
not included in the West Yost TM.
(3) Further research into the type of treatment processes and after visitation to three
Northern California plants, a better planning estimate has been determined to be
$20,000,000 for constructing a 10 MGD treatment plant and associated
transmission facilities.
(4) The land cost for 5 acres is assumed to be $300,000 per acre, compared to
$200,000 per acres as reflected in the West Yost TM.
(5) The West Yost TM presented a $50 million number that was $36.7 million
adjusted to the forecast mid -point of construction.
J:\Water\ClnfoSurfaceWaterProgram_ExB.doc
Exhibit C
ATTACHMENT B
CITY OF LODI
%W COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Implementing Surface Water Treatment Program Utilizing
Woodbridge Irrigation District Contractual Allotment and Authorizing
Solicitation of Water Treatment Plant Proposals
MEETING DATE: April 19, 2006
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt a resolution implementing the surface
water treatment program utilizing the Woodbridge Irrigation District
(WID) 6,000 acre-feet contractual allotment by authorizing the
solicitation of proposals from three water consulting firms for
preliminary water treatment plant studies. This staff report contains similar information to that
presented at the March 1, 2006 Council meeting. Additional information to address comments
received by staff have been added and are identified by bold text.
BACKGROUND INFORMATION: On several past occasions, the City Council has received information
regarding the acquisition and usage of 6,000 acre-feet per year of
Mokelumne River water from Woodbridge Irrigation District. In
May 2003, the City contracted with WID to provide untreated
surface water to Lodi for 40 years. At the September 21, 2004 Shirtsleeve Meeting, the Water Supply
Options Report was presented to the Council. At the April 19, 2005 Shirtsleeve meeting, staff again
presented alternatives for implementing the 6,000 acre-feet per year surface water supply. On
April 20, 2005, Council approved hiring a consultant to further study and develop a recommendation for
full implementation of the WID surface water supply. On June 9, 2005, Council was sent a copy of the
WID Surface Water Implementation Study. On November 1, 2005, Council received a presentation from
the consultant and the recommendation that the City go to a conjunctive use water supply system — one
that utilizes ground water and treated surface water to serve the demands of Lodi's customers.
Over the course of the past three years, a number of alternatives have been considered with the most
effort focused upon "treat and drink" and "groundwater recharge." Some of the other alternatives
included: 1) injection well recharge, 2) raw water irrigation of parks and schools, 3) recharge ponds
within the City limits, 4) recharge ponds using North San Joaquin Water Conservation District facilities,
5) East Bay Municipal Utility District banking, and 6) interim supply to Stockton recharge ponds.
At the regional level, City of Lodi has been participating in several water supply programs that will, in the
future, bring additional water supplies to the City and the other agencies in the region. Examples include
the Mokelumne River Water and Power Authority MORE Project that seeks to capture unappropriated
flows in the Mokelumne River. Also, Lodi is collaborating with Stockton East Water District and North
San Joaquin Water Conservation District on a pilot -scale recharge project next to Micke Grove Park.
North San Joaquin Water Conservation District recently passed a land -use assessment for a pilot
groundwater recharge project and is evaluating multiple sites in its district.
APPROVED: �Q'
Blair ity Manager
J:\Water\GlmplemenlSurfaceWaterProgram (2).doc 4/13/2006
Adopt Resolution Implementing Surface Water Treatment Program Utilizing Woodbridge Irrigation District
Contractual Allotment and Authorizing Solicitation of Water Treatment Plant Proposals
April 19, 2006
Page 2
At present, the City is using 17,300 acre-feet per year to meet the demands of existing customers.
Resulting from the installation of water meters that is currently underway, a reduction in demand (through
conservation) is realistically expected to be 2,400 acre-feet per year. Therefore, the anticipated future
demand for existing Lodi will be approximately 15,000 acre-feet per year. As presented in the 2005
Urban Water Management Plan, the safe, long-term yield of the groundwater underlying the City is
15,000 acre-feet per year.
The City Council is being asked to support staffs recommendation to pursue the "treat and drink"
alternative on the basis it is the "highest and best use" of the WID water, given a number of factors that
are compared below.
Cost
The estimated construction cost for a surface water treatment plant and associated facilities is estimated
to be up to $25 million. These costs are inclusive of site acquisition, surface water diversion piping,
ultrafiltration (without pretreatment) using membrane technology, chlorine disinfection, distribution piping,
and storage tanks. This alternative does eliminate the need to construct additional wells to serve new
demands.
The estimated construction cost for a groundwater recharge program is estimated to be $30 million. This
assumes a recharge field 88 acres in size adjacent to the WID canal at $300,000 per acre, including site
improvements and pipe appurtenances. Construction of five new wells is included in the estimate.
In either scenario, new development is expected to fund the capital improvements. Operating and
maintenance costs are considerably higher for the "treat and drink" alternative. The estimated change to
current rates would be an increase of approximately 15%, if the burden were shared City-wide.
Staff has received comments stating the recharge option costs have been over estimated and that
the Micke Grove Trust lands could be acquired for constructing the recharge basins at a minimal
cost. However, the current lease holder has stated intent to farm the Trust property and may not
be willing to surrender the lease for the purpose of constructing recharge basins. Therefore, the
estimate is based on purchasing the land needed for constructing the recharge basins in the
immediate vicinity of the Lodi City limits or adjacent to the current General Plan boundary.
Certainly, if land costs are lower, the recharge project would have a lower capital and operating
cost compared to the treatment plant option. However, this assumes current conditions
pertaining to water quality (see later comments).
Groundwater Rights
The rights to groundwater resulting from surface recharge are not clearly defined in a
groundwater basin in an overdraft condition that is not yet adjudicated. Further, the City is
assuming we would be getting credit from a recharge program toward meeting requirements of
SB 221/SB 610 Water Supply Assessments. Discussions with legal experts on the issue indicated
the City's rights to recharged groundwater would best be secured by obtaining a formal
resolution from each water agency within the basin limits. It is staffs opinion this could be a
daunting task. And, the recommendation relative to securing water supply credits to meet
SB221/SB610 requirements was to treat and drink the water.
J:\Water\ClmplementSurfaceWaterProgram (2).doc 4/13/2006
Adopt Resolution Implementing Surface Water Treatment Program Utilizing Woodbridge Irrigation District
Contractual Allotment and Authorizing Solicitation of Water Treatment Plant Proposals
April 19, 2006
Page 3
Benefit
Criteria to evaluate benefits to the City of Lodi and the region include: 1) direct benefit to the
groundwater resource, 2) long-term water quality, 3) sharing the regional burden, and 4) time of use.
Each is discussed below.
Benefit to the Groundwater Resource
In the context that the water demands of existing Lodi are matched by the safe yield of the groundwater
resource, the "treat and drink" alternative eliminates further mining of the groundwater and, thereby,
results in the highest direct benefit.
Groundwater recharge programs have a number of inherent losses, including evaporation, uptake by
plant materials, and capture within the soil column. These losses can be as high as 30 percent although
proper basin location and construction could improve performance and efficiency. In addition, the
recharge water, once it reaches the groundwater "stream", moves away for the Lodi point of use and
toward the central -county depression.
Currently, the groundwater depression is located south and east of Lodi. Recent modeling work
performed by San Joaquin County suggests the groundwater depression will shift from its
current location to a location (south easterly) more directly east or northeast of Lodi over the next
20+ years. If this prediction becomes reality, the City would want to construct recharge basins at
the westerly boundary of the City to assure the City could then extract the water from the ground
through its wells.
Lona -Term Water Qualitv
Lodi has long enjoyed a high quality of water that is pumped from the ground through wells that are
clustered in relatively close proximity to the Mokelumne River. Not only has the quality of water been
excellent, but the yield from each well has been relatively high, with an average of approximately
1,400 gallons per minute per well. Based upon experience and water quality information for areas
southerly and westerly of the City, new wells in these areas are expected to have higher salinity levels
and lower yields. As the basin continues to be overdrafted, there is a high risk that groundwater
quality will degrade and that future wells will need treatment systems that are not included in the
cost estimate.
For the "treat and drink" alternative, the salinity in the water will be lower than found in the groundwater
and this will result in a lowering of salinity levels in the wastewater. This provides a long-term tangible
benefit to the City as the State is expected to impose limits on salinity for discharges to the Delta.
Lowering the salinity of our "source water" will avoid very costly improvements to remove salinity at the
wastewater end of the use cycle.
A groundwater recharge program will essentially not alter the water quality characteristics of the City's
groundwater resource.
The "treat and drink" alternative will result in chlorination of the entire City water system, as is required by
State regulation. Most in the industry agree that chlorination requirements will also be imposed upon all
groundwater users in the foreseeable future. Lodi is the largest community in the State solely using
groundwater without regular chlorination.
J:\Water\ClmplementSurfaceWaterProgram (2).doc 4/13/2006
Adopt Resolution Implementing Surface Water Treatment Program Utilizing Woodbridge Irrigation District
Contractual Allotment and Authorizing Solicitation of Water Treatment Plant Proposals
April 19, 2006
Page 4
Sharing the Regional Burden
On a regional basis, the various cities and agencies are collaboratively working to enhance the supply
side of the region's groundwater resource. On a conceptual level, the principal strategies to achieve this
goal include: 1) securing additional surface water resources, 2) elimination or deferral of further
groundwater pumping, 3) banking through recharge or deferral of pumping, and 4) regional recharge.
The MORE project was described above. Stockton Delta Water Treatment Plant will begin treating
56,000 acre-feet per year within three years. Lodi's water treatment plant can begin producing 6,000
acre-feet per year of drinking water within 4.5 years. A recharge program would provide somewhat less
regional benefit by virtue of the losses described above.
Time of Use
Water demands within the City are highest in the spring, summer and fall. Conversely, the lowest
demands are in the winter. Our WID water is available from March 1 through October 15 and this
perfectly matches our highest demand period. Lodi has secured high quality water that melds with
demands, both in quantity and in time. To store such water in the ground to be pumped out later does
not make a lot of sense.
As is the strategy of many of the regional recharge programs, excess water that usually becomes
available in the winter months is diverted to fallow fields for percolation. Often times, this water is
sediment laden and well suited for groundwater recharge. The City of Lodi could pursue a similar
strategy by diverting storm drainage water to recharge areas and/or by altering designs for new
developments to incorporate recharge facilities.
Recommendation
Staff is requesting City Council approval to initiate implementation of a surface water treatment program
that would utilize the WID 6,000 acre-feet contractual allotment. The first steps will be to solicit proposals
from three water consulting firms: HDR, RMC, and West Yost & Associates, all of whom were previously
pre -qualified for Lodi water studies. The time frame from proposal solicitation to final deliverables is 12
months and the estimated cost is expected to range from $250,000 to $500,000. Three alternative
treatment plant scenarios are currently envisioned: 1) stand-alone Lodi plant, 2) partnering in the
Stockton Delta Water Treatment Plant, and 3) stand-alone Lodi plant sharing "source water" with the
Stockton Delta Water Treatment Plant.
FISCAL IMPACT: No fiscal impact at this time. Staff will return to Council requesting
authorization to execute a professional services agreement with the
successful firm.
FUNDING AVAILABLE: Not applicable.
"A
Richard C. Prima, Jr.
Public Works Director
Prepared by F. Wally Sandelin, City Engineer
RCP/FWS/pmf
J:1Water\ClmplementSurfaceWaterProgram (2).doc 4/11/2006
ATTACHMENT C
M:\OPEN\EXHIBITS\06X031.dwg, Layoutl, 6/12/2006 7:31:50 AM, jpizzo
Chapter 4
California Water Plan Update 2005
ATTACHMENT D
Conjunctive Management and Groundwater Storage
Conjunctive management is the coordinated operation of surface water storage and use, groundwater storage and use, and
conveyance facilities to meet water management objectives. Although surface water and groundwater are sometimes con-
sidered to be separate resources, they are connected by the hydrologic cycle. Conjunctive management allows surface water
and groundwater to be managed in an efficient manner by taking advantage of the ability of surface storage to capture and
temporarily store storm water and the ability of aquifers to serve as long-term storage.
There are three primary components to a conjunctive manage-
ment project when the primary objective is to increase average
water deliveries. The first is to recharge groundwater when
surface water is available to increase groundwater storage
(see Box 4-1). In some areas this is accomplished by reducing
groundwater use and substituting it with surface water, allow-
ing natural recharge to increase groundwater storage (also
called in -lieu recharge). The second component is to switch to
groundwater use in dry years when surface water is scarce. The
third component is to have an ongoing monitoring program to
evaluate and allow water managers to respond to changes in
groundwater, surface water, or environmental conditions that
could violate management objectives or impact other water
users. Together these components make up a conjunctive man-
agement project. Conjunctive management projects may have
other objectives in place of or in addition to improving average
water deliveries. These other objectives may include improv-
ing water quality, reducing salt water intrusion, and reducing
groundwater overdraft.
Box 4-1 Groundwater Recharge
Groundwater recharge is the movement of surface water
from the land surface, through the topsoil and subsurface,
and into de -watered aquifer space. Recharge occurs
naturally from precipitation falling on the land surface,
from water stored in lakes, and from creeks and rivers
carrying storm runoff. Recharge also occurs when water
is placed into constructed recharge ponds (also called
spreading basins), when water is injected into the sub -
Other topics in the Water Plan that are related to conjunctive
management include the strategies on Groundwater Remedia-
tion /Aquifer Remediation, Recharge Areas Protection, Water
Transfers, and System Reoperation.
Conjunctive Management in California
Conjunctive management has been practiced in California to
varying degrees since the Spanish mission era. The first known
artificial recharge of groundwater in California occurred in
Southern California during the late 1800s and is now used as a
managementtool in manyareas. Two examples illustrate the types
of conjunctive management underway on a regional and local
scale. In Southern California, including Kern County, conjunctive
management has increased average -year water deliveries by
more than 2 million acre-feet (AGWA, 2000). Over a period
of years, artificial recharge in these areas has increased the
water now in groundwater storage by about 7 million acre-feet.
surface by wells, and when water is released into creeks
and rivers beyond what occurs from the natural hydrol-
ogy (for example, by releases of imported water). These
later examples of recharge are often called artificial,
intentional, managed or induced recharge. Significant
amounts of recharge can also occur either intentionally
or incidentally from applied irrigation water and from
water placed into unlined conveyance facilities.
Chapter Conjunctive Management and Groundwater Storage 4 1 1
DIRECTORS
WILLIAM STOKES
PRESIDENT
EO LUCCHESI
VICE PRESIDENT
SILL SHINN
AVERY MCQUEEN
HENRY P. VAN EXEL
WOODBRIDGE IRRIGATION DISTRICT
18777 N. LOWER SACRAMENTO ROAD
WOODBRIDGE, CALIFORNIA 96268
[209] 369-6808
FAX: 369-6823
Friday, May 5, 2006
Susan Hitchcock, Mayor
c/o City Clerk's Office
P.O. Box 3006
Lodi, CA 95241-1910
Dear Mayor Hitchcock,
RECEIVED
MAY 8 2006
,, 0# CITY oOFRKS nELODIPUBLIC T
REC
ATTACHMENT E
ANGERS CHRISTENSEN
MANAGER
SECRETARY/TREASUREER
JIM BHULTG
SUPERINTENDENT
The Woodbridge Irrigation District recently passed Resolution 03-09-06-01 authorizing
an amendment to extend the 2003 Lodi Water Sale Agreement for four additional years to
allow Lodi to develop its plan to use the 6,000 acre feet of water without losing banked
water. Under the amendment, a total of 42,000 acre feet of water could be banked and
the contract is extended from May 13, 2043 to September 30, 2047. The Resolution
passed recognizes Lodi's need of up to four years to construct a new 10 MGD surface
water treatment plant and stated,
"the District also believes strongly that the highest and best use of water by the
City would be through a new surface water treatment plant and delivery to the
City's customers rather than through ground water recharge".
The water sold to Lodi comes from the District's pre -1914 water rights not subject to
California Legislative or State Water Resource Control Board (SWRCB) control. If this
water is placed in the ground, State agencies such as the SWRCB and its Regional Water
Quality Control Board could possibly assert authority to control of recharged waters.
Such waters may be subject to State control and therefore do not have the same priority
as the pre -1914 water used directly by the `treat and drink" option. In WID's opinion,
Lodi's use of the water under the treatment plant option has the highest priority and such
use would not be subject to a future entanglement in the event of an adjudication of the
ground water basin or in disputes with landowners regarding changes to ground water
levels or quality. Lodi's use of water through the proposed treatment plant would
strengthen its long term water rights into the future as state regulators add new
regulations and the competition for limited water intensifies.
We are proud to announce that WID plans to build a new state of the art fish screen that
further serves to enhance and protect WID's rights to divert water from the Mokelumne
and would serve Lodi's long-term interests as well. The estimated $3 million dollar
Susan Hitchcock, Mayor
Friday, May 5, 2006
investment in the new screen will meet the current standards for fish screen as regulated
by the California Department of Fish & Game (CDFG) and NOAA Fisheries for the
protection and preservation of fish for all life stages, particularly steelhead and salmon.
The District will continue to make sound investments in its infrastructure in anticipation
of being able to provide for the future urban and agricultural needs of Lodi and the
surrounding area
Sincerely,
William Stokes, President
Cc: Lodi City Council\
Richard Prima, Director of Public Works
WID Board of Directors
Enc: WID Resolution 03-09-06-01
RESOLUTION NO. 03-09-06-01
Of WOODBRIDGE IRRIGATION DISTRICT
AUTHORIZING EXECUTION OF AN AMENDMENT EXTENDING THE
AGREEMENT WITH LODI FOR ADDITONAL FOUR YEARS
WHEREAS. The City of Lodi has requested that its 40 -year Agreement for
Purchase of Water from the District, entered into on May 13, 2003, be extended for an
additional four years, and also that the City be allowed to continue to bank unused water
for an additional four years beyond the existing cutoff date of May 13, 2006; and
WHEREAS, the Board of Directors of the District are agreeable to granting such
extension in the form of an Amendment as finally approved by the President; and
WHEREAS, the Board of Directors also wishes to inform Lodi that the District
believes strongly that the highest and best use of the water by the City would be through
a new surface water treatment plant and delivery to the City's customers rather than
through groundwater recharge;
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF WOODBRIDGE
IRRIGATION DISTRICT, as follows:
Section 1. The President and Secretary are authorized and directed to execute a
First Amended Agreement with the City of Lodi, to extend the termination date of the
Agreement from May 13, 2043 to September 30, 2047, and to allow the City to continue
to bank unused water up to 6,000 acre-feet per annum for an additional four years from
May 13, 2006 to October 15, 2010, not to exceed a total of 24,000 acre feet. The First
Amended Agreement shall in form and substance as recommended by the Manager and
Attorney and approved by the President.
ADOPTED the 9t' day of March, 2006, by the following vote:
AYES: Directors Stokes, Shinn, Van Exel and McQueen
NOES: None
ABSENT: Luchessi
Signed:
William Stokes, President
Attest:
Anders Christensen, Secretary
ATTACHMENT F
DIRECTORS
John Ferreira NORTH SAN J OAQ U I N WAT E R
Thomas Hoffman
Joe
Matthysys Van
Gaalen
CONSERVATION DISTRICT
an
Fred Weybret 221 W. Pine St., Lodi, CA 95240
June 12, 2006
Mayor Susan Hitchcock
City Council Members
City of Lodi
221 West Pine Street
Lodi, CA 95240
SUBJECT: Groundwater Recharge
Dear Mayor Hitchcock and Council Members,
GENERAL MANAGER
Edward M. Steffan!
LEGAL COUNSEL
Stewart C. Adams, Jr.
We are writing to thank you for postponing your water treatment plant decision until the
District could complete its recharge test on the Micke Trust Property, and to sadly report
that the late rains and the tenant's need to plant a vineyard have made early completion
of the test improbable.
The District Board understands the City's need to move ahead with the treatment plant
decision, and we ask only that the plant be sized to allow for combination treatment and
recharge projects in cooperation with the District.
The District has a right to 20,000 acre-feet per year of Mokelumne River water but only
uses 3,000. The remaining 17,000 acre-feet are available for City treatment and/or
recharge. Although not available every year, the water can be diverted from
December 1 st to November 15th. including the 1987 —1992 drought, water has been
available 75% of the last 29 years.
It is the District's understanding that the Woodbridge Irrigation District water is available
to the City only during the irrigation season. The District water could be used by the City
during the other months of normal and wet years, and the District water would be
available at virtually no cost to the City.
We agree with Public Works Director Prima that the Micke Trust Land is not the only
promising site for recharge. We would like to work with him to find sites which could
benefit the City and District.
We would be pleased to meet at any time to discuss use of District water for City
treatment and for recharge projects.
Si erely,
Fred Weybret
President
FW:bs
J:\STEFFANI\LETTERS\LHITCHCOCK AND CITY COUNCIL GROUNDWATER RECHARGE.DOC
RESOLUTION NO. 2006-
A RESOLUTION OF THE LODI CITY COUNCIL
INITIATING DIRECT USE OF THE WOODBRIDGE
IRRIGATION DISTRICT CONTRACTUAL ALLOTMENT
AND AUTHORIZING SOLICITATION OF PROPOSALS
FOR TECHNICAL STUDIES
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council hereby
initiates direct use of the Woodbridge Irrigation District 6,000 acre-feet contractual
allotment, and further authorizes solicitation of Proposals for technical studies.
Dated: June 21, 2006
-------------------------------------------------------------------
-------------------------------------------------------------------
I hereby certify that Resolution No. 2006- was passed and adopted by the
City Council of the City of Lodi in a regular meeting held June 21, 2006, by the following
vote:
AYES: COUNCIL MEMBERS —
NOES: COUNCIL MEMBERS —
ABSENT: COUNCIL MEMBERS —
ABSTAIN: COUNCIL MEMBERS —
JENNIFER M. PERRIN
Interim City Clerk
2006-
7 F- N N
c
June 21, 2006
Fork in the Road
Slide 2
unmrampnif.,omonnevisirmaavnrz
ii
s
` ° "ms`s . �►�'-� �_ _ - x'. ..tiQ�+ir .
of~a,S 'I -� - M1 I .- '. •_ Ly i, .5
= i. � • a '� '_ - 17'��
General
I
:.Av � F
groundwater
movement }�_ ' y�I� f,Y .::.a:kNA
;�
direction �,1�=:..._ `�°•.•• _:�' _� �.'.� .�� �� ���r�;� ._ . , _� ����� - � �
r .TMat�_ t: -,1;, '.f 'r 1,`ir•� ��—�` -1 -
I�}� ►Ly+III I` r' -ti f_ s�+,P f +l -
F
General site °_ - : • � : _-. _ �� _ � ��: ..�=.} �� �•� � •_*�
areas
3}'
- - I _` —__ ` AFI - �i �' �,•..L':'�� I�1�1 �� 1
�,�I Hlyl j' m.. r+t _�. I 'V'�4'� Le I ..s..
win
.........rte..:.. ....� I _
�T
ft
MAIN
Rd.
BOOSTER
PUMP
STATION
ACRES
Water
nsmission
TM&i-nTVT
Micke Grove Test Site
'�'
);o -Test not completed
➢ Recharged water
MI&Ay Grove
Park&Zoo
recovery issues
• Practical
a
Legal
m
➢ Water Quality Issues?
w
��� me
➢ Lease vs. Purchase?
I
PROPOSEDNEW
CITY W ELLS
ITYP)
I
oli
■
A
is
ts)
■
i ae
r
ts waste
dved soli
11
Am
Recharge Basin - Land Cost Comparisons (88 Acre Basin)
Range of Purchase Costs
per Acre'): $ 30,000 $ 60,000 $ 100,000 $ 200,000 $ 300,000
Total Cost (Purchase): $ 2,640,000 $ 5,280,000 $ 8,800,000 $17,600,000 $26,400,000
Lease Cost/Acre/Year:
$ 225
$ 275
$ 350
$
500
$
750
Initial Costs2):
$ 880,000
$ 880,000
$ 880,000
$
880,000
$
880,000
Total Cost (40 Yr. Lease):
$ 1,672,000
$ 1,848,000
$ 2,112,000
$
2,640,000
$
3,520,000
Notes:
1) Purchase cost includes any site development and/or conveyance costs in addition to actual basin construction costs
2) Initial costs for lease assumes $10,000 per acre allowance to compensate owner for removal of vines, trees, etc.
All
LOBI
MUNEPAL
LAKE
ANN
th
Mr
W001:Ir
.
TFEATkUT pWANT
4 .......
R
IF
WAT�K
POTENTIAL ILF
6
TFF-ATNMT PLA I
LORI SITE L4
■
■
NNN
W. KETTLEM
A- LANE/HWY 1
PROPOSED
STORAGE
TN#(
CENTURY
Recharge vs. Direct Use Capital Costs
Low Range
High Range
Recharge: $ 6,013,000 leased land @ $ 30,301,000 purchased land @
$350/acre for 40 $300,000/acre
years
Recharge $11,013,000 above plus $ 35,301,000 above plus
w/Recovery: transmission transmission
system system
Direct Use: $29,500,000 latest estimate $ 36,700,000 2004 estimate
Supply Diversitv
:4011010
tv
Ah
SGS Circular 1261, 2005)
>irect Use — 1--xnp,
_egai
— Dan O'Hanlon, K
D n -1 n -1 r
ou rces
*Two Options: Direct Use or Recharge
+Law Allows Either Option
+Direct Use
— Most protective to City's right to use the water
*Essential Difference
— Direct Use — maintain exclusive control
— Recharge — store in source used in common
by many
rl
*GW Recharge:
— May store in aquifer and maintain right
provided ultimately put to use
— Right to claim augmented amount
I
;e
p
cl-
or
i n
gar
TI
rge
nigh
to
ng; co
•
ch
I
rJ
A
iter SHnniv Plann-ina Imni-Ireqt-le
*Conclusion: Direct Use
—Best protects City's right to use of WID
supply, and helps meet supply planning
obligation
Ah
0
of Studies:
Irocess Ev
Nate rs h e d
s
ma
3P
-SPCC
cation/Pilot. Stu
n i to ry Survey
mental/Reaul
Action
iND
+ General Plan - Recharge with Storm Water, other
intermittent water
+Supply diversification, best use
+Sustainable practice
+Improvement in wastewater quality
+Recommendations from others
+Legal Support
*Questions/Answers/Discussion
*Direction
RM
.'l r0
I=:N
2030 Deficit.
i o De mase up wi
+Additional conso
*Additional WID
+ Recvcled water
eith
r
RESOLUTION NO. 0-09-0"l
Of WOODBRIDGE IRRIGATION DISTRICT
AUTHORIZING EXECUTION OF AN AMENDMENT EXTENDING THE
AGREEMENT WTTH LODI FOR ADDITONAL FOUR YEARS
WHEREAS. The City of Lodi has requested that its 40 -year Agreement for
Purchase of Water from the District, entered into on May 13, 2003, be extended for an
additional four years, and also that the City be allowed to continue to bank unused water
for an additional four years beyond the existing cutoff date of May 13, 2006; and
WHEREAS, the Board of Directors of the District are agreeable to granting such
extension in the form of an Amendment as finally approved by the President; and
WHEREAS, the Board of Directors also wishes to inform Lodi that the District
believes strongly that the highest and best use of the water by the City would be through
a new surface water treatment plant and delivery to the City's customers rather than
through groundwater recharge;
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF WOODBRIDGE
IRRIGATION DISTRICT, as follows:
Section 1. The President and Secretary are authorized and directed to execute a
First Amended Agreement with the City of Lodi, to extend the termination date of the
Agreement from May 13, 2043 to September 30, 2047, and to allow the City to continue
to bank unused water up to 6,000 acre-feet per annum for an additional four years from
May 13, 2006 to October 15, 2010, not to exceed a total of 24,000 acre feet_ The First
Amended Agreement shall in form and substance as recommended by the Manager and
Attorney and approved by the President.
ADOPTED the 9h day of March, 2006, by the following vote:
AYES: Directors Stokes, Shinn, Van Exel and McQueen
NOES: None
AB SENT : Luchessi
Signed:
William Stokes, President
f►
DESIGN CRITERIA:
WMUM APPROACH VELOCITY 0.3 fps
VNIMUM DWERSION 414 cfs AT POOL ELEV 40.75'
WOGE WIRE OR PROFILE BAR SCREEN AT 1.75 mm CLEAR
MM(IMIJM RESERVOIR ELEV 41.0'
ELECTIVE SCREEN HT ELEV 41.5'
FISH BYPASS FLOW 8-13 cfs
AWOMATED BRUSH CLEAMING SYSTEM
im
NF *eke*
NEW DEBRIS
BOOM
0 50 100
SCALE IN FEET
DIVERSION NEW SCREEN STRUCTURE
OVMRALL SITE PLAN
' WOODEIRIDGE IRRIGATION DISTRICT
JUNE 13 2W6
FMM
C-0
i
NEW OVER SHOT GATES
(2 REQUIRED)
NEW V -SCREEN
NEW SCREEN
STRUCTURE
A
�
I FFimff I )1)f))
RAMP._
DOWN DOWN I
bNFMISH
NEW FISH BYPASS
FLUME
TO NEW
ASS FLUME
4
Q
Q
I I I i
f I I I
I I I
I I
NEW SHEET PILE WALL
GRATING OVER NEW
FISH BYPASS FLUME
NOT SHOWN FOR
CLARITY
EXISTING FISH BYPASS
(5-18 c#s)
--.`-a -L — —_.._
1
NEW TRASH
RACK
20 40
SCALE IN FEET
CANAL.. DIVERSION NEW SCREEN STRUCTURE
FM SITE PLAN
11WOODBRIDGE IRRIGATION DISTRICT
DAW
JUNE 13 2006
C-1
'A':: 03 58 P -V
CITY OF STOC KTON
DEPARTMENT OF MUNICIPAL UTILI'T'IES
2500 Navy Drive • Stockton, CA 95206-1191 - 209/937-8750 - Fax 209/937-8708
www.stocktongov.com
June 21, 2006
Richard Prima
Director of Public Works
City of Lodi
221 W. Pine Street
Lodi, CA 95241
TY OF 1,001 BECISQM ON A SAJRFACE WATER TREATMENT PLANT
The City of Stockton acknowledges your efforts to pursue a surface wafter treatment plant to make
use of the raw surface water currently purchased from the Woodbridge Irrigation District. As you
know, the City of Stockton has worked diligently towards a program to divert and treat surface water
from the Sacramento -San Joaquin Delta.
The Delta Water Supply Project, as a conjunctive use project, has been shown to be the best
solution for Stockton to ensure long-term reliability of our water delivery system. The clear benefits
of this project are to provide a long-term supply of surface water to the Stockton Metropolitan Area
and assist in the protection of the groundwater basin. We see the "Treat and Drink" option presently
under consideration.by the City of Lodi to be a viable option for the use of Woodbridge surface water
for those same reasons.
Direct use of surface water for potable supply enhances groundwater recharge through in -lieu
techniques and in -lieu recharge has been demonstrated to be one of the most efficient means of
groundwater recharge. Considering the groundwater quality issues facing both Cities, enhanced use
of surface water supply should be strongly considered.
The City of Lodi may find it useful to consider a project that maintains a high degree of local control_
It has been our experience that advancing water supply projects is difficult and •a high degree of
control will better enable you to control the timing and cost of your project.
We also compliment you and your staff on your thorough evaluation of the various alternatives and
look forward to maintaining a strong working relationship between the two cities.
If you have any questions or would like to discuss this further, feel free to contact me at 937-8700.
MARK J. MADISON
DIRE=CTOR OF MUNICIPAL UTILITIES
MJM:RLG:as
:00 MMIGRPWISE COSMU0 MUO_E.ibrary.114284.1
Arrangement will raise up to
$100 million to relicense and
up5.�d.: a system of dams.
By Edgar Sanchez
BEE STAFF WRITER
Calling it an investment that will pay off,
Placer County supervisors on Tuesday ap-
proved a plan to finance the relicensing of a
water and power system that they say is a
vital county asset.
Supervisors unanimously authorized the
county treasurer to invest in up to 5100 mil-
lion in bonds sold by another agency forihe
Middle Fork American River Proiect.
Of that, about $32 million would go for the
relicensing, a lengthy process that must be
completed by 2013 through the Federal En-
ergy Regulatory Commission.
Another $15 million would be for interest
on the outstandin& balance on the new
bonds between now and 2015.
The remainder would go for possible up-
grades to the system of dams and waterways
built 40 years ago to provide water to county
users and to generate electrical power.
Twun.beren=ties also must approve the
pian to legally activate it.
On Thursday, the Placer hunty Water
Agency's Board became the second body To
officially embrace the deal by unanimous
vote.
The third and final approval is expected
Monday from the newly created Middle Fork
► WATER
SOUTH PLACER BES 3/26/06
+-On P_, ja
Water: Agencies see
a future fiscal windfall
Project Finance Authority Board,
which will issue the bonds.
"I don't know who carne up
with this great ifinancing) idea,
but to me, it's just remarkable,"
Supervisor Bill Santucci told Trea-
surer Jenine Windeshausen be-
fore Tuesday's vote.
"You're going to save the peo-
ple within this county a whole lot
of money." Ire said, adding that
the plan "gives us the ability to
provide clean drinking water to
the people of Placer County" for
generations.
Once a new license is in place,
the water and power system also
will bring in millions of dollars in
annual revenue that will be
evenly split between the county
and the Placer County Water
Agency. The agencies could split
up to $20 million a year, accord-
ing to some projections.
"A source of financing is
needed because no power reve-
nues are available (to the county)
untii 2013," Windeshausen said
in a prepared statement. "At
present, all the revenue (from the
project) is going to PG&E and it
wili continue to until 2013."
Before the project was com-
pieted in 1967 - after the issuance
of 5115 million in voter -
approved revenue bonds by the
PCWA - thewater board signed a
50 -year contract to sell the
project's power exclusively to
PG&E.
"in exchange for all power pro-
duced until 21313, PG&E agreed to
pay all operatioris� _maintenance
costs and capital costs" for the
project, Windeshausen said.
Pacific Gas and Electric, she
added, also agreed to pay off the
$115 million debt. The last bond
will be paid off in 2013, when the
federal license that allows the
PCWA to sell the project's energy
also expires.
"1n 2413, we'll begin to be able
io sell energy contracts with the
revenue coming back to the peo-
pie of Placer County," Winde-
shausen said.
The PCWA, created in 1957 by
a special act of the Legislature to
protect the county's water re-
sources, has owned the project
since its completion.
The PCWA was governed by
the Board of Supervisors until
January 1975 when the board
made it an independent water
agency.
Earlier this year, supervisors
and the PCWA created a new
joint powers authority - the Mid-
dle Fork Project Finance Author-
ity - to finance the relicensing
process and to ensure the
project's financial viability.
Although the project will con-
tinue to be owned and operated
by the PCWA, the Middle Fork
Power Authority will issue the
bonds and continue its financial
role "for at least as long as the
bands are outstanding," Winde-
shausen said.
According to county docu-
ments, the bonds are to mature in
April 2036, unless they are paid
off sooner.
Only two members of the pub-
lic expressed reservations about
the plan at last week's meeting of
the Board of Supervisors.
One, John Greene, urged the
board to "step back and look" at
the pian "from a higher policy lev-
el --
Greene, vice chairman of the
Weimar, Applegate, Colfax Mu-
nicipal Advisory Council, said:
"We're lending to ourselves.
There's a risk in that."
Bu- GrePpe, who ernphas-:�Ettr-
that he was speaking as a private
citizen, later said that he sup-
ported the supervisors' decision
to move forward.
"1 do think some further refine-
ment has to be done - and this
might include the financing
plan," he said. "This will be a
very positive development for
the citizens of Placer County and
will leave a lasting legacy for this
board of directors."
Supervisor Robert Weygandt
said the potential payoff was too
good to pass up_
Windeshausen said the coun-
ty's initial outlay would be $W
million - an amount that in all
;ikelihood "tall do the job."
"The upper limit of $100 mil-
lion is in case we need to borrow
for major capital improvements
or in the event of a major system
failure, "she said.
The water and power project,
which includes four reservoirs,
seven dams, five hydroelectric
powerplants, and 24 miles of tun-
nels, is the state's eighth -largest
public power project. .
An independent international
engineering firm specializing in
hydroele irtcs recently com-
pleted a physical examination of
the project and found it has been
well-maintained, Windeshausen
said.
A rigorous financial evaluation
also was done by a firm specializ-
ing
pecializing in energy economics. It, too,
concluded that the project can be
expected to operate for the next
40 years "with a record similar to
what has been experienced since
the project was constructed,"
Windeshausen said in her pre-
pared statement.
■ 0
The Bee's Edgar Sanchez run
be reached at
esanchezasacbee. com_
CITY COUNCIL
CITY OF LODI
SUSAN HITCHCOCK,
EMayor 4
j2„ti
$LAIR KING,
City Manager
808 JOHNSON.
JENNIFER M. PERRIN,
Mayor Pro Tempore
Interim City Cleric
JOHN BECKMAN
+
LARRY D. HANSEN
D. STEPHEN SCHWASAUER,
JOANNE MOUNCE
PUBLIC WORKS DEPARTMENT
City Attorney
CITY HALL, 221 WEST PINE STREET / P.O. BOX 3006
RICHARD C. PRIMA, JR.,
LODI, CALIFORNIA 95241-1910
Public Works Director
TELEPHONE (209) 333-6706 / FAX (209) 333-6710
EMAIL pwdept@lodi.gov
http://www.lodi.gov
June 15, 2006
Woodbridge Irrigation District
Anders Christensen, N%nager
18777 N. Lower Sacramento Road
Woodbridge, CA 95258
City of Stockton Municipal Utilities
Mark Madison, Director
2SOO Navy Drive
Sbckton, CA 95206
Kronick, Moscovitz, Tiedemain & Gerard
Dein O'Hanllon
400 Capitol Mall, 27h Floor
Sacrarnento, CA 95814-4416
San Joaquin County Water Resources
Mel Lytle, Water Resources Coordinator
1810 E. Hazelton Avenue
Stockton, CA 95201
North San Joaquin Water Conservation District
Ed Steffani, Manager
221 W. Pine Street
Lodi, CA 95240
SUBJECT: Adopt Resolution Implementing the Treatment and Direct Utilization of the Surface
Water Supply from the Woodbridge Irrigation District Contractual Allotment and
Authorizing Solicitation of Proposals for Technical Studies of Implementing this
Option
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, June 21, 2006. The meeting will be held at 7 p.m. in the City Council Chamber,
Carnegie Forum, 305 West Pine Street.
TtNs item is on the regular calendar for Council discussion. You are welcome to attend.
If you wish to write to the City Council, please address your letter to City Council, City of Lodi,
P.O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the mail. Or, you may
haled -deliver the letter to City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's card
(available at the Carnegie Forum immediately prior to the start of the meeting) and give it to the
City Clerk. If you have any questions about communicating with the Council, please contact
Jennifer Perrin, interim City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call me at (209) 333759.
Richard C. Prima, Jr.
r ' Public Works Director
Rcplpmf
Enclosure
o*: City Cletk
J:tWaterWClmpkawnt5ufiaoGNaterProgram (3).doc