HomeMy WebLinkAboutAgenda Report - April 19, 2006 E-03AGENDA ITEM
-3
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Adopt Resolution Approving Plans and Specifications; Authorizing
Advertisement for Bids for Municipal Service Center (MSC) Compressed
Natural Gas (CNG) Fueling Station Expansion, 1331 South Ham Lane; and
Authorizing City Managerto Execute Amendment to Professional Services
Agreement with T. Mitchell Engineers and Associates ($14,600)
MEETING DATE: April 19,2006
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt a resolution approving plans and
specifications; authorizing advertisement for bids for the
Municipal Service Center (MSC) Compressed Natural Gas (CNG)
Fueling Station Expansion project at 1331 South Ham Lane; and
authorizing the City Manager to execute an amendment to the professional services agreement with
T Mitchell Engineers and Associates in the amount of $14,600.
BACKGROUND INFORMATION: At the December 7,2005, meeting, the City Council approved
specifications for the purchase of a CNG packaged electric motor
drive compressor system for the Municipal Service Center (MSC)
and authorized the City Manager to negotiate a contract with
GreenField Compression, Inc. The equipment was ordered and will soon be ready for delivery. Staff is
requesting approval of the plans and specifications to install this equipment at the MSC. In addition, at
the November 2, 2005, meeting, the City Council approved a contract with T. Mitchell Engineers and
Associates for work on the facility upgrades at the MSC and design and construction monitoring for the
CNG Expansion project (equipmentand installation).
Staff is recommending that the City Council authorize the City Manager to amend the existing agreement
with T. Mitchell Engineers and Associates to add design work for a required CNG compliant heating
system for the MSC shop and additional construction monitoring and administration. The CNG compliant
heating system is required for the MSC shop to be able to be safely heated while CNG vehicles are being
worked on (otherwise, these vehicles must be serviced outside). Staff will be returning to Council for
authorization in late spring/early summer for the actual purchase and installation of the CNG compliant
heating system. The additional construction monitoring and administration is required to ensure sufficient
oversight of the CNG installation project. When the original agreementwas drafted, it was anticipated
that City Fleet Division staff would be providing a portion of the monitoring and administration, and,
therefore, the hours included in the agreement with T. Mitchell Engineers and Associates were reduced.
Due to staffing changes, the expected staff oversight is no longer available, and, therefore, staff is
recommending amending the contract to have T. Mitchell Engineers and Associates perform the
additional work.
APPROVED:
Blair King, City Manager
J PROJECTSITRANSMCNGSTATION%MSC_CNG_ExpansionlCConstructionPS&A_Award_TMitchell doc
4/1412006
Adopt Resolution Approving Plans and Specifications; Authorizing Advertisement for Bids for Municipal
Service Center (MSC) Compressed Natural Gas (CNG) Fueling Station Expansion, 1331 South Ham Lane;
and Authorizing City Manager to Execute Amendment to Professional Services Agreement with T. Mitchell
Engineers and Associates ($14,600)
April 19, 2006
Page 2
FISCAL IMPACT: Failure to award the contract would result in the new CNG equipment sitting
in the yard, unable to be utilized. Also, the City would have no secondary
backup for the fueling facility, requiring the City to look elsewhere for fuel
should our system not function correctly. Failure to amend the agreement
with T. Mitchell Engineers and Associates would result in the MSC shop not having a compliant heating
system and would require the oversight of the equipment installation to be handled by the Fleet and
Facilities staff, who do not have the manpoweror time to do so.
FUNDING AVAILABLE: Funding for the installation and construction administration will be provided
by a Congestion Mitigation and Air Quality (CMAQ) grant from the
San Joaquin Council of Governments, using Transportation Development
Act (TDA) funds as match. The design of the CNG compliant heating
system will be funded from FTA Section 5307 and TDA.
Y� -k . f��
Ruby P ste, Interim Finance Director
I "Ok
Richard C. Prima, Jr.
Public Works Director
Prepared by Tiffani M. Fink, Transportation Manager
RCP/TMF/pmf
cc Transportation Manager
Fleet and Facilities Manager
Tom Mitchell, T. Mitchell Engineers and Associates
J \PROJECTSITRANSMCNGSTATIONIMSC_CNG_ExpansionlCConstructionPS&A_Award_TMitchell.doc 411412006
RESOLUTION NO. 2006-56
A RESOLUTION OF THE LODI CITY COU NCI L APPROVING PLANSAND
SPECIFICATIONS, AUTHORIZING ADVERTISEMENT FOR BIDS FOR MUNICIPAL SERVICE
CENTER COMPRESSED NATURAL GAS FUELING STATION EXPANSION, 1331 SOUTH HAM
LANE; AND FURTHER AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT TO THE
PSOFESSIONAL SERVICES AGREEMENT WITH T. MITCHELL ENGINEERSAND ASSOCIATES
WHEREAS, at the December 7, 2005, meeting, the City Council approved specifications for the
purchase of a compressed natural gas (CNG) packaged electric motor drive compressor system for the
Municipal Service Center (MSC) and authorized the City Manager to negotiate a contract with GreenField
Compression, Inc.; and
WHEREAS, the equipment will soon be ready for delivery: therefore, staff recommends approval
of the plans and specificationsfor the installation of this equipment at the MSC; and
WHEREAS, at the November 2, 2005, meeting, the City Council approved a contract with
T. Mitchell Engineers and Associates for work on the facility upgrades at the MSC and design and
construction monitoring for the CNG Expansion project (equipment and installation): and
WHEREAS, staff recommends amending the existing agreement with T. Mitchell Engineers and
Associates to add design work for a required CNG compliant heating system for the MSC shop and
additional construction monitoring and administration.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve the plans
and specifications, authorizes advertisement for bids for MSC CNG Fueling Station Expansion, 1331
South Ham Lane; and
BE IT FURTHER RESOLVED that the Lodi City Council hereby authorizes the City Manager to
execute amendment to professional services agreement with T. Mitchell Engineers and Associates to add
design work for a required CNG compliant heating system for the MSC shop and additional construction
monitoring and administration in an amount not to exceed $14,600.
Dated: April 19,2006
I hereby certify that Resolution No. 2006-56 was passed and adopted by the City Council of the
City of Lodi in a regular meeting held April 19, 2006, by the following vote:
AYES: COUNCIL MEMBERS — Beckman, Hansen, Johnson, Mounce, and
Mayor Hitchcock
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS— None
SUSAN J. BLACKSTON
City Clerk
2006-56
CITY COUNCIL
CITY OF LODI
SUSAN HITCHCOCK.
BLAtR KING,
Mayor
��� y��
City Manager
BOB JOHNSON,
SUSAN J. BLACKSTON.
Mayor Pro Tempore
City Clerk
JOHN BECKMAN
LARRY D. HANSEN
0. STEPHEN SCHWABAUER.
JOANNE MOUNCE
PUBLIC WORKS DEPARTMENT
City Attorney
CITY HALL, 221 WEST PINE STREET / P.O. BOX 3006
RICHARD C. PRIMA, JR.,
LODI, CALIFORNIA 95241-1910
Public Works Director
TELEPHONE (209) 333-6706 / FAX (209) 333-6710
EMAIL pwdept@lodi.gov
http://www.lodi.gov
April 14, 2006
Mr. Tom Mitchell
T. Mitchell Engineers & Associates
5737 Thornhill Drive, Ste. 207
Oakland, CA 94611
SUBJECT: Adopt Resolution Approving Plans and Specifications; Authorizing
Advertisement for Bids for Municipal Service Center (MSC) Compressed
Natural Gas (CNG) Fueling Station Expansion, 1331 South Ham Lane; and
Authorizing City Manager to Execute Amendment to Professional Services
Agreement with T. Mitchell Engineers and Associates ($14,600)
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, April 19. 2006. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunity to address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letterto City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letterto City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Susan Blackston, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Dennis Callahan. Fleet and
`Facilities Manager, at (209) 333-6800, extension 2690.
T .
Richard C. Prima, Jr.
r. • Public Works Director
RCP/pmf
Enclosure
cc: Citv Clerk
J:IPROJECTSITRANSInCNGSTATIONWSC_CNG_ExpansionlNCConstructionPS&A Award_TMkcheli.doc