Loading...
HomeMy WebLinkAboutAgenda Report - March 15, 2006 E-05AGENDA ITEM &5 CITY OF LODI COUNCIL COMMUNICATION AGENDA TITLE: Receive for Informational Purposes Contract Change Order - Kettleman Lane Gap Closure Project, Lower Sacramento Road to Ham Lane and Stockton Street to Cherokee Lane MEETING DATE: March 15,2006 PREPARED BY: Public Works Director RECOMMENDED ACTION: This item is for information only. No action is required. BACKGROUND INFORMATION: This information is being given to Council in accordance with the Contract Change Order Policy approved by Resolution 85-173. One of the requirements of this policy is that the City Council be informed when the aggregate total of all change orders exceeds $25,000. Information concerning Contract Change Order No. 2 and the cost of Contract Change Order No.1 was provided to the City Council at its meeting of February 1, 2006. The attached Contract Change Order No. 3, approved by the City Manager, was in the amount of $8,158.86, which is 0.4% of the contract. The aggregate total of all change orders to date is $365,447.48 (17.7% of the original contract amount). The work on Contract Change Order No. 3 includes adjustments to pay quantities which differed by more than 25% from the original contract estimate. The work on this change order also includes compensation for the additional work needed to correct ponding locations along the medians at Kettleman Lane and Mills Avenue and at Kettleman Lane and Lakeshore Drive. FISCAL IMPACT: FUNDING AVAILABLE: This contract change order should not create any change in the fiscal impact of this project. Contract Amount: Budgeted Fund: $2,426,274.48 Measure K Flexible Congestion Relief Ruby P ' te, Interim Finance Director "Aa - Richard C. Prima, Public Works Director Prepared by Wesley Fujitani. Senior Civil Engineer RCPNVKF/pmf Attachment APPROVED: 3 Blair King, C' nager J 1PROJECTSkSTREETSUCettlemanGap\CC_cco3 doc 31812006 CITY OF LODI PUBLIC WORKS DEPARTMENT C V6PANGE ORDER NO.3 (JAN 3 G 223 Sheet 1 of 2 STOCKTON DISTRICfte January 25, 2006 Account No. 325088 PROJECT: Kettleman Lane Gap Closure Project (Lower Sacramento Road to Ham Lane; Stockton Street to Cherokee Lane) CONTRACTOR: Teichert Construction You are directed to make the following changes or do the following work not included in the Plans and Specifications on this contract. ...................................................................... Description of work to be done, estimate of quantities, and prices to be paid. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. 1. Adjust Quantity for Contract Item #13 Remove Traffic Stripe Add 5,750.26 M at $2.50/M Agreed Upon Price $14,375.56 2. Adjust Quantity for Contract Item#17 Remove Roadside Sign Delete 51 Ea at $11.00/Ea Agreed Upon Price ( $561.00) 3. Adjust Quantity for Contract Item#19 Remove Culvert Delete 8 M at $25.00/M Agreed Upon Price ( $200.00) 4. Adjust Quantityfor Contract Item#21 Remove Mailbox Delete 3 Ea at $200/Ea Agreed Upon Price ( $600.00) 5. Delete Contract Item#22 Relocate Roadside Sign Agreed Upon Price ( $680.00) 6. Adjust Quantity for Contract Item#23 Cold Plane Pavement Delete 545 M2 at $7.00/M2 Agreed Upon Price ( $3,815.00) 7. Adjust Quantity for Contract Item #37 Minor Concrete (collar) Delete 0.8M3 at $400.00/M3 Agreed Upon Price ( $320.00) 8. Adjust Quantity for Contract Item #47 Thermo Pavement Markers Delete 167.9 M2 at $33.00/M2 Agreed Upon Price ( $5,540.70) 9. Install median curb cuts at Kettleman Lane/Mills Avenue and Kettleman Lane/Lakeshore Drive at a cost not to exceed $5,500.00 PERCENT OF CONTRACT Original Contract Price $2,060,827.00 Total Cost of This Change Order NOT TO EXCEED $ 8,158.86 0.4% Previous Change Orders $ 357,288.62 Total Cost of All Change Orders to Date $ 365,447.48 17.7% Contract Price, Including All Change Orders, Will Be: $2,426,274.48 rrn� ,1M CITY OF LODI PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO.3 11 Sheet 2of 2 Date January 25, 2006 Account No. 325088 PROJECT: Kettleman Lane Gap Closure Project (Lower Sacramento Road to Ham Lane; Stockton Street to Cherokee Lane) CONTRACTOR: Teichert Construction Submitted By Date Approval Recommended Date 7.-87-0(. Approved, Public Works Director CgjDate Z 44 D G Manager (Per PublicWorks Policies Procedures, Administration 4.1 Date 64 The undersigned contractor, having carefully considered the change proposed, agrees, if this proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted above, perform all services necessary for the work above specified, and accept as full payment the prices shown above. ACC ED: D 2 l^moo Contractor ^�r/c -eaar B Title RoJtyr*� 1;/ iAlllzo.�i� If the contractor does not sign acceptance of this order, the contractor should refer to Section 4- 1.03A of the Standard Specifications regarding filing a written protest within the specified time. rrna Mr.