HomeMy WebLinkAboutAgenda Report - February 1, 2006 E-06AGENDA ITEM E640
CITY OF LODI
COUNCIL COMMUNICATION
M
AGENDA TITLE: Receivefor Informational Purposes Contract Change Order- Kettleman Lane
Gap Closure Project, Lower Sacramento Road to Ham Lane and
Stockton Street to Cherokee Lane
MEETING DATE: February 1,2006
PREPARED BY: Public Works Director
RECOMMENDEDACTION: This item is for information only. No action is required.
BACKGROUND INFORMATION: This information is being given to Council in accordance with the
Contract Change Order Policy approved by Resolution 85-173. One
of the requirements of this policy is that we inform the City Council
of all change orders over 10 percent of the contract amount.
The attached contract change order, approved by the City Manager, was in the amount of $268,098.26,
which is 13% of the contract. The work includes the reconstruction of approximately 480 lineal feet of
Mills Avenue south of Kettleman Lane ($101,578.65), the additional work needed to install water service
taps in the medians ($36,538.62), additional labor and equipment needed to pothole and locate utilities at
street light locations ($12,000), new commercial driveways and sidewalk at Voelker Drive and
Kettleman Lane ($12,000), the additional cost to bore conduit for the signal interconnect cable across
Cherokee Lane ($8,308.65), and the additional costs related to the project because of delays in relocating
utility poles along the north side of Kettleman Lane ($84,436.62). City staff is having discussions with SBC
regarding their participation in payment for these delay costs. The remainder of this contract change order
covers minor items of additional work and adjustments to the contract pay quantities.
FISCAL IMPACT:
FUNDING AVAILABLE
This contract change order should not create any change in the fiscal
impact of this project other than a slight reduction in pavement
maintenance on that portion of Mills Avenue which was reconstructed
ContractAmount:
Budgeted Fund:
$2,418,115.62
Measure K Flexible Congestion Relief
�l 6K. -0a'(.L�
Ruby PdAte, Interim Finance Director
� la
Riafwd C. Prima. Jr.
Public Works Director
Prepared by Wesley Fujitani, Senior Civil Engineer
RCP/WKFtpmf
Attachment
APPROVED: �'�--
Blair King, City anager
J%PROJECTSISTREETSIKettlemanGaplCC_cco2 doc
112012006
CITY OF LODI
PUBLIC WORKS DEPARTMENT �Q
CONTRACT CHANGE ORDER NO.2
tion' TQC)Sheet 1 of 2
4/Q ��, O�5 Date December 8,2005
4Q. OPV 0� Account No. 325088
PROJECT: Kettleman Lane Gap Closure Pct
(Lower Sacramento Road to Lane; Stockton Street to Cherokee Lane)
CONTRACTOR: Teichert Construction
You are directed to make the following changes or do the following work not included in the
Plans and Specifications on this contract.
----------------------------------------------------------------------
Description of work to be done, estimate of quantities, and prices to be paid. Unless otherwise
stated, rates for rental of equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
1. Spray Vegetation for Weed Control (9005)
Agreed Upon Price
$
575.00
2. Relocate Staging Area (9008)
Agreed Upon Price
$
1,725.00
2. Renew Storm Drain Permit (9014)
Agreed Upon Price
$
708.40
3. Pothole Utilities for Street Light Foundations (9015)
Agreed Upon Price
$ 12,000.00
4. Review Stage Two Signage (9016)
Agreed Upon Price
$
3,265.09
5. Restrpe Walmart Driveway (9017)
Storm Drain Agreed Upon Price
$
636.58
6. Abandon Water Service on Mills Ave (9018)
Agreed Upon Price
$
351.95
7. Add Irrigation Conduit Across WI Canal (9019)
Agreed Upon Price
$
838.05
8. Reconstruct Mills Avenue (9020)
Agreed Upon Price
$101,578.65
9. Provide Signs and Hardware (9021)
Agreed Upon Price
$
5,970.00
10. Bore SIC Conduit Across Cherokee Lane (9022)
Agreed Upon Price
$
8,308.65
10. Remove AC in Median Near Jack-in-the-Box (9024)
Agreed Upon Price
$
2,507.71
11. Provide Irrigation to Medians (9025,9029)
Agreed Upon Price
$
36,538.62
12. Install Driveways at Voelker Drive (9026)
Agreed Upon Price
$
12, 000.00
13. Repair Landscaping at Payless Shoes (9029)
Agreed Upon Price
$
1,485.10
14. Additional Sign Rental and Maintenance
Agreed Upon Price
$
750.13
15. Electrical work for Walmart Sign
Agreed Upon Price
$
4,462.50
MM
CITY OF LODI
PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO.2
Sheet 2of 2
Date December 8, 2005
Account No. 325088
PROJECT: Kettleman Lane Gap Closure Project
(Lower Sacramento Road to Ham Lane; Stockton Street to Cherokee Lane)
CONTRACTOR: Teichert Construction
----------------------------------------------------------------------
16. Repair Loops
Agreed Upon Price
$ 887.25
17. Additional Signs at Ham Lane
Agreed Upon Price
$ 1,096.20
18. Delay costs
Agreed Upcn Price
$ 84,436.62
19. Temporary Striping CRIP
Agreed Upon Price
($21,275.59)
20. Adjust Quantity for Contract Item #12 Remove Yellow Stripe
Add 621.5 M at $6.50/M Agreed Upon Price
$ 4,039.75
21. Adjust Quantity for Contract Item #15 Remove Pavement Markers
Add 666 Ea at $1.1 /Ea Agreed Upon Price
$ 732.60
22. Adjust Quantity for Contract Item #49 Reflec. Pavement Markers
Add 1,280 Ea at 3.50/Ea Agreed Upon Price
$ 4.480.00
PERCENT OF
CONTRACT
Original Contract Price
$2,060,827.00
Total Cost of This Change Order NOT TO EXCEED
$ 268,098.26
13%
Previous Change Orders
$ 89,190.36
Total Cost of All Change Orders to Date
$ 357,288.62
17%
Contract Price, Including All Change Orders, Will Be:
$2,418,115.62
Submitted By
Approval Recommended
Approved, Public Works Director
Approved City Manager (Per Public Works Policies and
Date II Z- 08 -oS
Administrafion 4. 1)
Date 15- o f -
The undersigned contractor, having carefully considered the change proposed, agrees, if this
proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted
above, perform all services necessaryfor the work above specified, and accept as full payment
the prices shown above.
AC P E D e /Z� 2/—O S Contractor
B Title �'%9.�1�