HomeMy WebLinkAboutAgenda Report - September 15, 2004 E-13AGENDA ITEM gr
&10& CITY OF LODI
WM. COUNCIL COMMUNICATION
TM
AGENDA TITLE: Receive Impact Mitigation Fee Program Annual Report for Fiscal Year
2003/2004
MEETING DATE: September 15, 2004
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council receive the Impact Mitigation Fee Program
Annual Report for Fiscal Year 200312004.
BACKGROUND INFORMATION: The City Council adopted the "Final Report, City of Lodi
Development Impact Fee Study," prepared by Nolte and Associates
and Angus McDonald Associates in 1991, as well as the
"Development Impact Fee Update Study," prepared by
Harris & Associates. These actions established and updated the City's Development Impact Fee
program. Staff has prepared the following exhibits:
Exhibit A — A summary of the current and past fees, beginning and ending balances for each fee account,
total fees collected, interest earned, and total expenditures from each account for FY 200312004.
Exhibit B — A summary by account of public improvement projects on which fees were expended during
FY 200312004,
Per State Law, this information needs to be available to the public at least 15 days prior to review by the
City Council. The report format follows that of the recently -approved FY 2002103 report, which shows
fund balance and cash balance. This information will be brought back to the Council for a brief
presentation and acceptance in October 2004.
FUNDING: None required.
,;�LF
�4
Richard C. Prima, Jr.
Public Works Director
Prepared by Rebecca Areida, Management Analyst
RCPIRAIpmf
Attachments
cc: Wally Sandelin, City Engineer
CIMFAnnualReport_0304Aoc
9/8/2004
A B C D E I F G H I J K
1 EXHIBIT A
2 IMPACT MITIGATION FEE PROGRAM
3 FY 2003/04 Annual Report
4
5
6 Fee: Wastewater
Water
Storm Drain
Streets -Local
Streets -Regional
Police
Fire
Parks & Rec
General Facilities
Art in PP
7 Fund #: 173
182
326
327
332
1215
1216
1217
1218
1214
8
9 Fee Amount 7/1/03 - 12/31/03 (1) 525
4,105
11,813
4,784
3,465
1,613
1,577
20,249
6,517
2%
10 Fee Amount 1/1/04 - 6/30/04 (1) 544
4,257
12,252
4,962
3,594
1,673
1,635
21,003
6,760
2%
11
12 Fund Balance- Beginning of Year 640,898.00
1,146,570.00
1,785,544.00
683,520.00
(442,477.00)
901,541.00
(1,397,770.00)
2,114,886.00
292,222.00
347,675.00
13
14 Revenues:
15 Investment Revenues 7,241.00
15,105.00
30,974.00
12,365.00
8,027.00
1,091.00
21,363.00
15,676.00
3,316.00
16 Service Charges (Fees) 14,984.00
72,491.00
408,649.00
289,437.00
198,033.00
159,358.00
97,601.00
542,908.00
354,708.00
42,730.00
17 Other Revenue
5,000.00
18
19 Total Revenue 22,225.00
87,596.00
439,623.00
306,802.00
198,033.00
167,385.00
98,692.00
564,271.00
370,384.00
46,046.00
20
21
22 Expenditures:
23 Capital Projects 0.00
(130,812.59)
(35,920.12)
(178,102.78)
(114,414.55)
0.00
(325.10)
(1,769.48)
0.00
0.00
24
25Total Expenditures 0.00
(130,812.59)
(35,920.12)
(178,102.78)
(114,414.55)
0.00
(325.10)
(1,769.48)
0.00
0.00
26
27
28 Other Sources (Uses):
29 Operating Transfers In
25,154.00
3,100.00
30 Operating Transfers Out
(9,771.00)
(365,934.00)
(203,477.00)
(484,940.00)
(1,000,000.00)
(105,448.00)
(1,111,442.00)
(50,000.00)
31 Other Sources (Uses) (19.00)
(37,791.00)
32
33 Total Other Sources (Uses) (19.00)
(47,562.00)
(365,934.00)
(178,323.00)
(484,940.00)
(1,000,000.00)
(105,448.00)
(1,111,442.00)
(50,000.00)
3,100.00
34
35
36 Total Fund Balance - End of Year $663,104.00
$ 1,055,791.41
$1,823,312.88
$633,896.22
($843,798.55)
$68,926.00
($1,404,851.10)
$1,565,945.52
$612,606.00
$396,821.00
37
38 Interfund Loans
(1,396,763.48)
756,770.00
1,396,763.48
(756,770.00)
39 Cash Balance - End of Year $663,104.00
$ (340,972.07)
$1,823,312.88
$633,896.22
($87,028.55)
$68,926.00
($8,087.62)
$809,175.52
$612,606.00
$396,821.00
40
41 (1) Fees listed are per acre for one Residential Acre Equivalent (RAE). Each land use
42 presents a different demand for services that are reflected in RAE adjustment factors per LMC 15.64.070.
43
44
45
46
DevSer/ImpactFees/IMFAnnualReport2003-04.xis 9/9/2004
Cell: E17
Comment: F&H Construction - Stockton St. Improvements
Cell: E29
Comment: EUD portion of Harney/Stockton signal project
Cell: C30
Comment: Transfer funds from IMF water fund to water capital fund (180) for water facilities constructed prior to 1991 with capacity to serve new development
Cell: D30
Comment: $100,756.85 - Operating transfer (storm drain fund cost of services)
$265,177.15 - Transfer to General Fund for Impact Fee share of Debenedetti Park design.
Cell: E30
Comment: $85,255.44 - Cost of Services
$36,221.73 - Transfer of funds from IMF local streets fund to street fund (320) for street facilities constructed prior to 1991 with capacity to serve new development
$82,000 - Transfer to Transit Fund for Guild/Thurman St. project(MTS1028)
Cell: F30
Comment: $25,008.05 - Transfer of funds from IMF regional fund to street fund (320) for street facilities constructed before 1991 with capacity to serve new development.
$363,825.44 - Transfer to Transit Fund for Lower Sacramento Rd project (MTSI006-12 & MBC001)
$96,106 - COG loan payment for Hwy 12/99 project.
Cell: G30
Comment: Reimburse General Fund for Police Bldg. design & construction
Cell: H30
Comment: Fire truck lease payment
Cell: 130
Comment: $348,658.85 - Reimburse General Fund for design of Debenedetti Park (MPR052)
$345,107.02 - Reimburse General Fund for design of Indoor Sports Complex(MPR060)
$118,568.57 - Reimburse General Fund for design of Aquatic Center(MPR062)
$26,255.36 - Reimburse General Fund for design of Aquatic Center(MPR041)
$272,825 - Transfer to Transit Fund for Lodi Lake Westside Trail project(MPR006)
Cell: J30
Comment: Yearly transfer to General Fund for the costs associated with the administration of the IMF program
Cell: B31
Comment:
Difference between end of last FY accounts receivable/payable and this this FY accounts receivable/payable.
Cell: C31
Comment: Difference between end of last FY accounts receivable/payable and this this FY accounts receivable/payable.
Cell: C38
Comment: Loan to Fire IMF for Fire Station #4 project.
Cell: F38
Comment: Loan from Parks & Rec IMF for Lower Sacramento Rd project.
DevSer/ImpactFees/IMFAnnualReport2003-04.xis 9/9/2004
Cell: H38
Comment: Loan from Water IMF for Fire Station #4 project.
Cell: 138
Comment: Loan to Regional Street IMF for Lower Sacramento Rd project.
DevSer/ImpactFees/IMFAnnualReport2003-04.xis 9/9/2004
EXHIBIT B
IMPACT MITIGATION FEE PROGRAM
SUMMARY OF PUBLIC IMPROVEMENT PROJECT EXPENDITURES
FY 2003/04
Wastewater Water Storm Drain Streets -Local Streets -Regional Police Fire Parks & Rec General Facilities Art in Public PI
Prninrf Nn A --f Nn n ... rinfin 191 199 1119. '{9] 119 1915 loin. 1917 191a 191A
MWS0003 182041 Water Utility Planning
1,000
182460 Well 26
14,812
MWW1003 182465 Subst Test Drill
112,326
MWW1005 182466 DeBenedetti Well
2,675
MSDI017 326017 G Basin
18,108
MSD1023 326019 Lockeford St. Storm Drain
16,847
MSDI015 326031 G -Basin
966
MTS1014 327004 Century Meadows
1,986
MRRX001 327005 RR Track Removal
2,028
MTS023 327008 TS-Century/Ham
73,880
MTS1032 327013 RR Track Removal -Lodi Ave
17,295
MTS1032 327014 Central City RR Safety
42,576
327015 312/316 S. Sacramento
10,407
327016 715 S. Guild Ave
2,442
MTS1017 327017 Harney Ln. Widening
2,586
MTS013 327070 TS-Harney/Stockton
21,447
327071 Lodi/Mills Interconnect
3,456
MTS1009-12 332048 LSR - South
55,015
MTS1001-03 332088 Kettleman Gap Closure
59,400
LDF001 1216139 Fire Station #4 Construction
325
MPR059 1217004 Century Meadows Park
500
MPR052 1217017 G -Basin
1,269
Total 0 130,813 35,920 178,103 114,415 0 325 1,769 0 0